摘 要:钻孔灌注桩是工程中常用的地基处理形式,常用于水利工程基础施工,桩内质量对于水利建筑工程质量有着至关重要的影响。本文简要论述了钻孔灌注桩在某市一排涝泵站工程施工中的应用。
关键词:钻孔灌注桩;施工工艺;质量控制;检测
The application of bored piles in water conservancy engineering
Li Ming-geng
Abstract: the bored piles are commonly used in construction of foundation treatment, often used in water conservancy engineering foundation construction, within the pile quality for water conservancy construction project quality has a crucial effect. This paper briefly discusses the bored piles in a municipal drainage pumping station the application of the engineering construction.
Keywords: bored piles; The construction technology; Quality control; detection
钻孔灌注桩系指在工程现场通过机械钻孔,在地基中形成桩孔,并在其内放置钢筋笼、灌注砼而做成的桩,是一项基础加固处理,以提高基础承载力,确保建筑稳定的施工技术。本文通过工程实例,简要介绍了钻孔灌注桩的施工工艺、质量控制及检测方法。
1.工程概况
1.1 设计概况
安徽省某市一排涝泵站工程,装机流量35.8m3/s,设计装机为4台1600ZDBX-125J型贯流泵,配套YQGN850-6电机,总装机容量2000kW。站身地基采用钢筋混凝土钻孔灌注桩加固,桩径1.0m,桩距顺水流向3.5 m,垂直水流向3.0 m,平均桩长约21m,桩顶高程4.2~7.829 m,桩底高程-15.8 m,单桩承载力设计值为1550KN。
1.2 工程地质
根据钻孔揭露,拟建站址地层自上而下依次为:
0层人工填土(Qml 4):其成分为重粉质壤土,灰黄色,可塑,稍湿~湿,土体结构较松散,属中等压缩性土。主要分布在堤身及现排涝站西侧,该段河堤部位堤身填土层厚1.30~7.80m,层底高程3.82~8.07m。
①1层淤泥质重粉质壤土(Qal 4):青灰色,流塑~软塑,很湿,含少量腐殖质。属高压缩性土。各孔均有揭露,层厚1.80~9.40m,层底高程-1.33~2.05m。
①2层淤泥质轻粉质壤土夹薄层细砂(Qal 4):灰色,软塑,,很湿,含少量腐殖质,夹有薄层细砂,具有明显的层理。属高压缩性土。各孔均有揭露,层厚1.40~5.20m,层底高程-0.38~-5.63m。
①3层淤泥质重粉质壤土(Qal 4):青灰色,流塑~软塑,很湿,含少量腐殖质。属高压缩性土。各孔均有揭露,层厚4.50~14.40m,层底高程-7.22~-14.78m。
② 层重粉质壤土(Qal 3):灰黄、棕黄色,硬可塑,稍湿,局部夹铁锰质结核及灰白色高岭土,属中等压缩性土。该层各孔均有分布,未钻穿,揭露最大层厚9.10m,相应层底高程-18.08m。
1.3 地下水
站址处地下水类型以孔隙水为主,赋存于站址区堤身填土以下各土层中,主要接受大气降水、附近的沟渠以及汛期时外河水的补给,枯水期则向外河及附近的沟渠排泄。
站址区地下水类型主要为孔隙潜水以及弱承压水,潜水主要分布于0层人工填土、①1层淤泥质重粉质壤土中,弱承压水主要分布于①2层淤泥质轻粉质壤土中夹薄层细砂。地下水主要接受大气降水、汛期时附近的沟渠、外河水的补给,枯水期则向附近的沟渠以及外河排泄。
2.施工工艺流程
定位→埋设护筒→钻机就位→钻孔→清孔(第一次)→下钢筋笼→安设导管→清孔(第二次)→浇注水下砼→拔除护筒→转移下一个桩位。
3.施工质量控制
3.1 材料
1)泥浆材料使用的膨润土和粘土质量应符合SL174—96规定。
2)水下混凝土使用的水泥、骨料和外加剂应符合现行规范的规定。
3)灌注桩钢筋笼使用的钢筋材料质量应符合有关规定。
3.2 泥浆制备和处理
泥浆的作用是防止孔壁坍塌和对孔壁起保护作用,它既能使孔内的泥浆不致流入孔外,又能使孔外的水不致渗入孔内,它的具体要求为:
比重:1.3~1.5/Tm 3 ( 用婆梅式比重计侧 )
含沙率:≤4-8%
胶体含量:≥90%,塑性指数:IP>17
(1)挖泥浆池
泥浆池应设至距桩位6-8m以外的空地为宜,坑口尺寸大约4×5m (也可根据钻机多少确定),深 1.5m为宜,四周用红砖铺砌,坡度大约600 左右,上抹20厚1:2.5 的水泥砂浆。
泥浆池必须保证一次施工30~40根桩的排放和需求,否则钻孔时,既浪费泥浆,又太麻烦。泥浆池施工完毕,应从桩位至泥浆池施工两条排浆循环沟,以便泥浆循环使用,施工方法同泥浆池。
(2)制作泥浆
泥浆的制作选用自然水和粘土或黄土拌制而成,粘土必须取样送试验室鉴定,粒径≤5mm,粒径太大必须过筛。施工时将粘土送泥浆池搅拌使用。水的选用不得使用对砼有害的水。 3.3 定位及埋设护筒
(1)钻孔施工前,先按照设计要求进行场地平整,并对软弱地面位置进行适当处理,避免出现施工机具下陷、倾斜,影响成孔质量,并注意做好泥浆、钻渣和废水的外运和排放。
(2)根据桩基设计平面图,用经纬仪或全站仪放样定点,测出中心轴线和桩位,并将轴线引至四周不易破坏的地点,便于复核桩位。
(3)护筒内径比钻孔桩孔径大100mm,上部开设两个溢浆孔,护筒埋深1~1.5m。
(4)埋设护筒时,用十字交叉法使其与桩位中心偏差控制在20mm内。护筒的倾斜度不大于1%。
(5)在干地上,护筒四周应用粘土夯实,护筒埋设应入原土200mm。
(6)钻机就位安装时,转盘中心与护筒中心偏差小于10mm。
钢护筒用4~6mm厚的钢板制造,护筒顶端应高出地面0.3m,孔内泥浆至少高于地下水位1.5m。
3.4 终孔与清孔
(1)定时检查泥浆护壁钻孔的孔位、孔径、孔深、孔斜和沉渣;钻至施工图纸规定的孔深后,进行终孔和沉渣的检查。
(2)沉管到达规定深度后,应按YSJ212-92、YBJ42-92第4.5.6条规定检测其终孔的贯入度。
(3)钻孔的孔径经检验合格后应立即进行清孔,清孔应分别选用真空吸泥法、泥浆循环法或射水冲渣法进行,其清孔标准应符合下列规定:
1)孔内排出或抽出的泥浆密度应在1.3g/cm3以下,含砂量不大于4%,用手触应无粗粒感觉。
2)钻孔灌注桩清孔的沉渣厚度应符合YSJ212-92、YBJ42-92表4.1.4的规定,沉管桩孔不得有沉渣。
3.5 钢筋笼制作与吊放
(1)钢筋笼的制作应符合YSJ212-92、YBJ42-92的规定。
(2)分段制作的钢筋笼应采用焊接连接,并应符合GBJ202-83的有关规定。
(3)钢筋笼主筋保护层的允许偏差应符合下列规定:水下浇注混凝土桩±2.0cm;
(4)应根据施工图纸规定在钢筋笼内周边设置声波测试预埋管。
(5)吊放钢筋笼应符合下列要求:
1)钢筋笼吊放前应进行垂直校正;
2)就位后钢筋笼顶底高程应符合施工图纸规定,误差不得大于5cm;
3)灌注桩桩顶应设有固定装置,就位后立即进行固定,防止上浮和下沉。
3.6 水下混凝土灌注
(1)灌注混凝土应符合下列规定:
1)桩顶混凝土灌注高程应高出施工图纸规定的桩顶高程0.5m;
2)采用人工灌注混凝土桩,在桩顶高程以下4m时,应采用棒式振捣器捣实;
3)灌注时的混凝土温度应不低于3℃,桩顶混凝土未达到设计强度50%前不得受冻。当环境温度高于30℃时,应采取缓凝措施。
(2)孔内水下混凝土灌注应采用导管法或混凝土泵施工:
1)导管直径不得小于20cm,其通过能力不小于10m3/h;大直径灌注桩导管应不小于30cm,其通过能力不小于25m3/h。导管内壁光滑圆顺;
2)导管安置在钻孔中心,下端口应高出沉渣面30~50cm;
3)灌注混凝土时,应保证导管理人混凝土面以下1.0m,人孔前混凝土应连续搅拌均匀,保证人孔坍落度,防止混凝土出现离析和压入空气;
4)混凝土输送管的直径应根据混凝土粗骨料直径选用:当粗骨料粒径为0.5~2.5cm时,应选用直径60cm的输送管;当粗骨料粒径大于2.5cm时,输送管直径应取最大粒径的4倍。
(3)灌注桩实际灌注混凝土量的充盈系数不得小于1.0。
3.7 沉管起拔
(1)配有钢筋笼的沉管,在放置钢筋笼前,混凝土应先灌到笼底高程,放置钢筋笼后再灌注混凝土至桩顶。
(2)分段起拔沉管时,前一段拔管高度应能容纳下一段灌入的混凝土量。
4 检测方法及成果
钻孔灌注桩施工结束后28天,应按JGJ94-94第9.1和9.2节的有关规定,对桩体进行检验和检测。
(1)单桩竖向抗压静载荷试验
采用锚桩在检测前一次均匀稳固在钢梁承力架上,试验采用慢速维持荷载法,分九级加荷,第一级加载值为设计承载力极限值的1/5,以后每级为1/10,首级加载620kN,最大试验荷载为3100 kN,为设计值的2倍。
通过单桩静载试验Q~S曲线、S-lgt曲线和S~lgQ曲线分析,试验加荷至3100kN,沉降量为12.12~19.79mm,抗压稳定,未达到极限荷载,单桩承载力特征值满足设计要求。
(2)钢筋混凝土灌注桩低应变法完整性检测
对桩顶进行处理,原桩顶的浮浆全部凿掉并凿平,使用武汉岩海RS-1616K(P)基桩动测仪,BW-14111型高灵敏度加速度,将加速度传感器贴在桩顶表面,运用反射波法以确定工程桩身的完整性,测试结果可靠。完整性共随机抽检30根桩,其中Ⅰ类桩为9根,占总桩数的30.0 %;Ⅱ类桩为21根,占总桩数的70.0%,全部为合格桩。
5 结语
实例证明,钻孔灌注桩施工工艺具有技术可靠、质量保证、工艺合理等特点,同时钻孔灌注桩具有低噪音、小震动、无挤土,能穿越各种复杂地层和形成较大的单桩承载力,适应各种地质条件和不同规模建筑物等优点,在桥梁、水工建筑、房屋建筑等工程中均有广泛应用。
参考文献
[1]《地基与基础工程施工及验收规范》GBJ202-83
[2]《基桩低应变动力检测规程》JGJ/T93-95
[3]《建筑桩基础技术规范》JGJ94-2008
[4]《建筑地基处理技术规范》JGJ79-913
[5]《灌注桩基础技术规程》YSJ212-92 YBJ42-92
关键词:钻孔灌注桩;施工工艺;质量控制;检测
The application of bored piles in water conservancy engineering
Li Ming-geng
Abstract: the bored piles are commonly used in construction of foundation treatment, often used in water conservancy engineering foundation construction, within the pile quality for water conservancy construction project quality has a crucial effect. This paper briefly discusses the bored piles in a municipal drainage pumping station the application of the engineering construction.
Keywords: bored piles; The construction technology; Quality control; detection
钻孔灌注桩系指在工程现场通过机械钻孔,在地基中形成桩孔,并在其内放置钢筋笼、灌注砼而做成的桩,是一项基础加固处理,以提高基础承载力,确保建筑稳定的施工技术。本文通过工程实例,简要介绍了钻孔灌注桩的施工工艺、质量控制及检测方法。
1.工程概况
1.1 设计概况
安徽省某市一排涝泵站工程,装机流量35.8m3/s,设计装机为4台1600ZDBX-125J型贯流泵,配套YQGN850-6电机,总装机容量2000kW。站身地基采用钢筋混凝土钻孔灌注桩加固,桩径1.0m,桩距顺水流向3.5 m,垂直水流向3.0 m,平均桩长约21m,桩顶高程4.2~7.829 m,桩底高程-15.8 m,单桩承载力设计值为1550KN。
1.2 工程地质
根据钻孔揭露,拟建站址地层自上而下依次为:
0层人工填土(Qml 4):其成分为重粉质壤土,灰黄色,可塑,稍湿~湿,土体结构较松散,属中等压缩性土。主要分布在堤身及现排涝站西侧,该段河堤部位堤身填土层厚1.30~7.80m,层底高程3.82~8.07m。
①1层淤泥质重粉质壤土(Qal 4):青灰色,流塑~软塑,很湿,含少量腐殖质。属高压缩性土。各孔均有揭露,层厚1.80~9.40m,层底高程-1.33~2.05m。
①2层淤泥质轻粉质壤土夹薄层细砂(Qal 4):灰色,软塑,,很湿,含少量腐殖质,夹有薄层细砂,具有明显的层理。属高压缩性土。各孔均有揭露,层厚1.40~5.20m,层底高程-0.38~-5.63m。
①3层淤泥质重粉质壤土(Qal 4):青灰色,流塑~软塑,很湿,含少量腐殖质。属高压缩性土。各孔均有揭露,层厚4.50~14.40m,层底高程-7.22~-14.78m。
② 层重粉质壤土(Qal 3):灰黄、棕黄色,硬可塑,稍湿,局部夹铁锰质结核及灰白色高岭土,属中等压缩性土。该层各孔均有分布,未钻穿,揭露最大层厚9.10m,相应层底高程-18.08m。
1.3 地下水
站址处地下水类型以孔隙水为主,赋存于站址区堤身填土以下各土层中,主要接受大气降水、附近的沟渠以及汛期时外河水的补给,枯水期则向外河及附近的沟渠排泄。
站址区地下水类型主要为孔隙潜水以及弱承压水,潜水主要分布于0层人工填土、①1层淤泥质重粉质壤土中,弱承压水主要分布于①2层淤泥质轻粉质壤土中夹薄层细砂。地下水主要接受大气降水、汛期时附近的沟渠、外河水的补给,枯水期则向附近的沟渠以及外河排泄。
2.施工工艺流程
定位→埋设护筒→钻机就位→钻孔→清孔(第一次)→下钢筋笼→安设导管→清孔(第二次)→浇注水下砼→拔除护筒→转移下一个桩位。
3.施工质量控制
3.1 材料
1)泥浆材料使用的膨润土和粘土质量应符合SL174—96规定。
2)水下混凝土使用的水泥、骨料和外加剂应符合现行规范的规定。
3)灌注桩钢筋笼使用的钢筋材料质量应符合有关规定。
3.2 泥浆制备和处理
泥浆的作用是防止孔壁坍塌和对孔壁起保护作用,它既能使孔内的泥浆不致流入孔外,又能使孔外的水不致渗入孔内,它的具体要求为:
比重:1.3~1.5/Tm 3 ( 用婆梅式比重计侧 )
含沙率:≤4-8%
胶体含量:≥90%,塑性指数:IP>17
(1)挖泥浆池
泥浆池应设至距桩位6-8m以外的空地为宜,坑口尺寸大约4×5m (也可根据钻机多少确定),深 1.5m为宜,四周用红砖铺砌,坡度大约600 左右,上抹20厚1:2.5 的水泥砂浆。
泥浆池必须保证一次施工30~40根桩的排放和需求,否则钻孔时,既浪费泥浆,又太麻烦。泥浆池施工完毕,应从桩位至泥浆池施工两条排浆循环沟,以便泥浆循环使用,施工方法同泥浆池。
(2)制作泥浆
泥浆的制作选用自然水和粘土或黄土拌制而成,粘土必须取样送试验室鉴定,粒径≤5mm,粒径太大必须过筛。施工时将粘土送泥浆池搅拌使用。水的选用不得使用对砼有害的水。 3.3 定位及埋设护筒
(1)钻孔施工前,先按照设计要求进行场地平整,并对软弱地面位置进行适当处理,避免出现施工机具下陷、倾斜,影响成孔质量,并注意做好泥浆、钻渣和废水的外运和排放。
(2)根据桩基设计平面图,用经纬仪或全站仪放样定点,测出中心轴线和桩位,并将轴线引至四周不易破坏的地点,便于复核桩位。
(3)护筒内径比钻孔桩孔径大100mm,上部开设两个溢浆孔,护筒埋深1~1.5m。
(4)埋设护筒时,用十字交叉法使其与桩位中心偏差控制在20mm内。护筒的倾斜度不大于1%。
(5)在干地上,护筒四周应用粘土夯实,护筒埋设应入原土200mm。
(6)钻机就位安装时,转盘中心与护筒中心偏差小于10mm。
钢护筒用4~6mm厚的钢板制造,护筒顶端应高出地面0.3m,孔内泥浆至少高于地下水位1.5m。
3.4 终孔与清孔
(1)定时检查泥浆护壁钻孔的孔位、孔径、孔深、孔斜和沉渣;钻至施工图纸规定的孔深后,进行终孔和沉渣的检查。
(2)沉管到达规定深度后,应按YSJ212-92、YBJ42-92第4.5.6条规定检测其终孔的贯入度。
(3)钻孔的孔径经检验合格后应立即进行清孔,清孔应分别选用真空吸泥法、泥浆循环法或射水冲渣法进行,其清孔标准应符合下列规定:
1)孔内排出或抽出的泥浆密度应在1.3g/cm3以下,含砂量不大于4%,用手触应无粗粒感觉。
2)钻孔灌注桩清孔的沉渣厚度应符合YSJ212-92、YBJ42-92表4.1.4的规定,沉管桩孔不得有沉渣。
3.5 钢筋笼制作与吊放
(1)钢筋笼的制作应符合YSJ212-92、YBJ42-92的规定。
(2)分段制作的钢筋笼应采用焊接连接,并应符合GBJ202-83的有关规定。
(3)钢筋笼主筋保护层的允许偏差应符合下列规定:水下浇注混凝土桩±2.0cm;
(4)应根据施工图纸规定在钢筋笼内周边设置声波测试预埋管。
(5)吊放钢筋笼应符合下列要求:
1)钢筋笼吊放前应进行垂直校正;
2)就位后钢筋笼顶底高程应符合施工图纸规定,误差不得大于5cm;
3)灌注桩桩顶应设有固定装置,就位后立即进行固定,防止上浮和下沉。
3.6 水下混凝土灌注
(1)灌注混凝土应符合下列规定:
1)桩顶混凝土灌注高程应高出施工图纸规定的桩顶高程0.5m;
2)采用人工灌注混凝土桩,在桩顶高程以下4m时,应采用棒式振捣器捣实;
3)灌注时的混凝土温度应不低于3℃,桩顶混凝土未达到设计强度50%前不得受冻。当环境温度高于30℃时,应采取缓凝措施。
(2)孔内水下混凝土灌注应采用导管法或混凝土泵施工:
1)导管直径不得小于20cm,其通过能力不小于10m3/h;大直径灌注桩导管应不小于30cm,其通过能力不小于25m3/h。导管内壁光滑圆顺;
2)导管安置在钻孔中心,下端口应高出沉渣面30~50cm;
3)灌注混凝土时,应保证导管理人混凝土面以下1.0m,人孔前混凝土应连续搅拌均匀,保证人孔坍落度,防止混凝土出现离析和压入空气;
4)混凝土输送管的直径应根据混凝土粗骨料直径选用:当粗骨料粒径为0.5~2.5cm时,应选用直径60cm的输送管;当粗骨料粒径大于2.5cm时,输送管直径应取最大粒径的4倍。
(3)灌注桩实际灌注混凝土量的充盈系数不得小于1.0。
3.7 沉管起拔
(1)配有钢筋笼的沉管,在放置钢筋笼前,混凝土应先灌到笼底高程,放置钢筋笼后再灌注混凝土至桩顶。
(2)分段起拔沉管时,前一段拔管高度应能容纳下一段灌入的混凝土量。
4 检测方法及成果
钻孔灌注桩施工结束后28天,应按JGJ94-94第9.1和9.2节的有关规定,对桩体进行检验和检测。
(1)单桩竖向抗压静载荷试验
采用锚桩在检测前一次均匀稳固在钢梁承力架上,试验采用慢速维持荷载法,分九级加荷,第一级加载值为设计承载力极限值的1/5,以后每级为1/10,首级加载620kN,最大试验荷载为3100 kN,为设计值的2倍。
通过单桩静载试验Q~S曲线、S-lgt曲线和S~lgQ曲线分析,试验加荷至3100kN,沉降量为12.12~19.79mm,抗压稳定,未达到极限荷载,单桩承载力特征值满足设计要求。
(2)钢筋混凝土灌注桩低应变法完整性检测
对桩顶进行处理,原桩顶的浮浆全部凿掉并凿平,使用武汉岩海RS-1616K(P)基桩动测仪,BW-14111型高灵敏度加速度,将加速度传感器贴在桩顶表面,运用反射波法以确定工程桩身的完整性,测试结果可靠。完整性共随机抽检30根桩,其中Ⅰ类桩为9根,占总桩数的30.0 %;Ⅱ类桩为21根,占总桩数的70.0%,全部为合格桩。
5 结语
实例证明,钻孔灌注桩施工工艺具有技术可靠、质量保证、工艺合理等特点,同时钻孔灌注桩具有低噪音、小震动、无挤土,能穿越各种复杂地层和形成较大的单桩承载力,适应各种地质条件和不同规模建筑物等优点,在桥梁、水工建筑、房屋建筑等工程中均有广泛应用。