G水厂根据净水工艺设置、管线布局等情况制定了通水前工艺联动调试方案,提出了反向蓄水及小循环流程、大循环流程等不同条件下工艺处理方式,实现了在无进厂水水源的情况下提前两个月对净水工艺进行系统调试、来水进厂后水源的平稳替换。在两个月的调试过程中,对水厂设备运行进行不断调整,最终达到了通水后一次性通水目标。
G water plant according to the water purification process settings, pipeline layout and other circumstances developed a pre-water technology linkage debugging program, put forward the reverse impoundment and small circulation processes, processes and other large circulation process under different conditions, to achieve no entry Plant water sources in the case of two months in advance of the water purification process for system debugging, water into the plant after the smooth replacement of water. During the two-month commissioning process, the equipment operation of the waterworks was continuously adjusted and finally the water-passing one-time target was reached.