历经4年的艰苦努力,苏南运河常州段整治工程已全面结束,最近通过交工验收。苏南运河常州段全长44.486km,由于年久失修,水流冲刷,岸坡坍塌,泥沙沉积,航道状况愈来愈差,制约了常州地区经济的发展。市政府分别于1984~1988年、1993~1996年进行了一、二期工程。工程实际完成开挖土方1008.3万m~3,砌筑护岸58195.8m,拆迁房屋31.11万m~2,征用土地174.45hm~2,压废
After four years of arduous efforts, the renovation project of the Changzhou section of the southern Jiangsu Canal has come to a complete end and has been recently handed over for inspection. The Changzhou section of the southern Jiangsu Canal has a total length of 44.486km. Due to the disrepair, water scour, bank collapse, sediment deposition and poor waterway conditions, the Changzhou area’s economic development has been restricted. The municipal government conducted the first and second phases respectively in 1984 ~ 1988 and 1993 ~ 1996. The actual completion of the project is 1.883 million m 3 of excavation earthwork, 58,195.8 m of masonry revetment, 311,100 m 2 of demolished houses, 174.45 hm 2 of requisitioned land, pressure wasted