随着汽轮机安装技术的发展,越来越多机组采用水泥垫块代替传统的可调斜垫铁安装技术。汽轮机水泥垫块配制速度与质量直接影响汽轮机扣盖施工进度节点及汽轮机安全运行。在配制施工过程中,克服了多种不利因素,制定科学的施工工序,以最短的时间完成汽轮机水泥垫块配制工作,为后续的轴承座、汽缸就位提供条件,保证了汽轮机按时扣盖和机组安全移交。
With the development of steam turbine installation technology, more and more units use cement pad instead of the traditional adjustable tilting horn installation technology. Steam turbine cement block preparation speed and quality directly affect the steam turbine buckle construction node and steam turbine safety operation. In the preparation of the construction process, to overcome a variety of unfavorable factors, the development of scientific construction processes, in the shortest possible time to complete the preparation of steam turbine cement block for the follow-up bearing, cylinder in place to provide conditions to ensure that the steam turbine buckle on time and Unit safety transfer.