论文部分内容阅读
【摘 要】.采用水泥灌浆技术处理杂填土地基,在安阳市地区尚属首次,本文通过水泥灌浆法处理杂填土地基的工程实际情况,详细总结了水泥灌浆处理杂填土地基的技术问题,实践证明,该方法在理论、实践上可行,费用较低,能达到设计要求,完全可以达到地基的承载力和确保地基不出现不均匀沉馅,可以作为建筑行业地基处理的一种参考方式。.
【关键词】.基础;处理
Miscellaneous fill foundation treatment of
Xin Yang1,Zhao Yun-bin2
(1.Water Survey and Design Institute of Henan Province, in northern Henan Anyang Henan 455000;.
2.Anyang City Zhangwu Reservoir Administration in the South China Sea Anyang Henan 455000)
【Abstract】.Fill foundation with cement grouting technology processing, the first time in Anyang City area, this article through the cement grouting Treatment Fill foundation engineering, detailed summary of the the cement grouting handling miscellaneous fill foundation, provedthe method is feasible in theory, practice, lower cost, and can meet the design requirements can be achieved bearing capacity of the foundation and to ensure that the foundation is not uneven Shen stuffing can be used as a reference to the way of the construction industry ground treatment..
【Key words】.Foundation;Processing
1. 工程概况.
安阳市河道管理处办公楼位于河南省豫北棉纺织厂对面,老107国道南侧安阳河左岸,呈椭圆形建筑,占地面积约40×17m2,二层,最大高度7m,采用钢筋混凝土基础,砖混结构。
地基为近期回填、堆积起来的以建筑垃圾为主的杂填土,回填时间五年左右,建筑垃圾的厚度为2.6~10.3m,强度低且不均一,其fK值仅为60KPa,设计要求fK值为100KPa,作为基础,必须做基础处理。.
2. 基础处理方案.
根据地基的情况,我们在原设计基础底标高继续下挖0.9m、将原设计基础向外扩宽0.6m,然后用3:7灰土分层夯实至设计标高,在灰土以下的地基采用水泥灌浆法加固处理。.
3. 基础处理.
(1)水泥灌浆法的加固原理。
该方法是采用机械造孔,利用灌浆泵或泥浆泵将按比例配制的水泥浆液,通过一定压力,灌注到预加固地层,冲填土体空间、空隙,经过脱水凝固作用,将松散的土体凝固成为一个整体,从而达到加固地基、增加地基强度、减少地基不均匀沉馅和透水性以及增大抗滑稳定性。
(2)钻孔布置。
在基础范围内共布置钻孔80个,总进尺428.4m,孔距1.5~4.55m,孔深3.0~9.2m,其中:灌浆孔38个,孔深3.0~9.2m,进尺254.4m;加强孔33个,孔深4.0m,进尺132.0m;检查孔9个,孔深4.0~8.0m,进尺42.0m。
(3)钻孔次序。
该工程的钻孔灌浆工作按照先外排后内排,同排间隔钻灌的原则进行。即按照灌浆孔、加强孔、检查孔序次的顺序钻灌,孔深以钻入杂填土为准。按钻孔——下止浆塞——灌浆(自下而上)的工序进行。在遇到塌孔不能成深孔时,则采用先上段后下段的灌浆工艺,灌浆与下段成孔间隔时间不小于24小时。
(4)浆液浓度。
根据《水工建筑物水泥灌浆施工技术规范》,结合本工程实际,我们采用灌浆的水灰比分为3:1、2:1、1:1、0.8:1、0.6:1五个比级,开灌浆液水灰比为3:1,特殊情况下可用2:1或1:1,依次逐级价浓,当某一比级的浆液单位吸浆量大于10L/min且灌入量大于200L时,则加浓一级。当单位吸浆量大于20L/min且灌入量大于400L时,则越级加浓。在低压力、高浓度灌浆单位吸浆量大于20L/min时,则增加速凝剂或其它配料如砂等。
灌注浆液的水灰比一般为2:1~1:1。对于吸浆量很大(单位吸浆量对于20L/min,连续灌入量对于500L)的孔段,采用低压力(自重)、高浓度(0.8~0.6:1)混合浆,间歇式的方法灌注。
(5)灌浆压力。
灌浆压力原则上按照上部荷重和侧壁厚度确定,对外排原则上采取浆柱自重灌浆,但是,当吸浆量很小(小于5L/min)时,则采用0.5Kg/cm2的压力灌浆。对于内排孔,一般采用0.5Kg/cm2的压力。
(6)灌浆结束标准。
当灌浆压力达到设计压力(0.5Kg/cm2),单位吸浆量小于0.4L/min时,则终止本段灌浆。
(7)封孔。
用1:2水泥砂浆逐次回填捣实的方法封至孔口平为止。
(8)质量检查。
钻灌结束后,采用钻孔注浆法进行质量检查,即向孔内注入水灰比1:2的浆液,在规定的压力下,初始10min内注入不超过10L即为合格。
共设检查孔9个,采用钻孔注浆法进行检查,结果表明灌浆全部合格。.
4. 处理后的效果.
基础处理完成7d以后,使用武汉岩海公司生产的RS-JYB全自动桩基静载荷测试分析系统测试,根据规范GBJ7-89和GBJ79-91,将现场测试的三组试验点的原始記录经微机处理后绘制出每组复合地基试验点的Q~s曲线、s~LgQ曲线和s~Lgt曲线。
当Q~s曲线上有明显比例极限时,取该比例极限所对应的荷载为该组地基荷载的标准值。
当极限荷载能确定,而其值又小于对应比例极限荷载值的1.5倍时,取极限荷载的一半为该组地基荷载的标准值。
经过对测试数据进行计算整理,结合场地工程地质勘探资料及水泥灌浆加固地基的特点,根据Q~s、s~LgQ、s~Lgt曲线分析对比,参考本地区实践经验,确定三组复合地基承载力结果分别为143KPa、147KPa、152KPa;三组复合地基承载力平均值为147KPa,极差为3.40%,小于30%,因此,该场地复合地基承载力标准值为147KPa,满足设计要求。.
5. 结论.
采用水泥灌浆技术处理杂填土地基,在安阳市地区尚属首次,本次水泥灌浆法处理杂填土地基,达到了设计要求,实践证明,该方法在理论、实践上可行,费用较低,完全可以达到地基的承载力的要求和确保不出现不均匀沉馅,可以作为建筑行业地基处理的一种参考方式。
[文章编号].1619-2737(2012)07-31-691
【关键词】.基础;处理
Miscellaneous fill foundation treatment of
Xin Yang1,Zhao Yun-bin2
(1.Water Survey and Design Institute of Henan Province, in northern Henan Anyang Henan 455000;.
2.Anyang City Zhangwu Reservoir Administration in the South China Sea Anyang Henan 455000)
【Abstract】.Fill foundation with cement grouting technology processing, the first time in Anyang City area, this article through the cement grouting Treatment Fill foundation engineering, detailed summary of the the cement grouting handling miscellaneous fill foundation, provedthe method is feasible in theory, practice, lower cost, and can meet the design requirements can be achieved bearing capacity of the foundation and to ensure that the foundation is not uneven Shen stuffing can be used as a reference to the way of the construction industry ground treatment..
【Key words】.Foundation;Processing
1. 工程概况.
安阳市河道管理处办公楼位于河南省豫北棉纺织厂对面,老107国道南侧安阳河左岸,呈椭圆形建筑,占地面积约40×17m2,二层,最大高度7m,采用钢筋混凝土基础,砖混结构。
地基为近期回填、堆积起来的以建筑垃圾为主的杂填土,回填时间五年左右,建筑垃圾的厚度为2.6~10.3m,强度低且不均一,其fK值仅为60KPa,设计要求fK值为100KPa,作为基础,必须做基础处理。.
2. 基础处理方案.
根据地基的情况,我们在原设计基础底标高继续下挖0.9m、将原设计基础向外扩宽0.6m,然后用3:7灰土分层夯实至设计标高,在灰土以下的地基采用水泥灌浆法加固处理。.
3. 基础处理.
(1)水泥灌浆法的加固原理。
该方法是采用机械造孔,利用灌浆泵或泥浆泵将按比例配制的水泥浆液,通过一定压力,灌注到预加固地层,冲填土体空间、空隙,经过脱水凝固作用,将松散的土体凝固成为一个整体,从而达到加固地基、增加地基强度、减少地基不均匀沉馅和透水性以及增大抗滑稳定性。
(2)钻孔布置。
在基础范围内共布置钻孔80个,总进尺428.4m,孔距1.5~4.55m,孔深3.0~9.2m,其中:灌浆孔38个,孔深3.0~9.2m,进尺254.4m;加强孔33个,孔深4.0m,进尺132.0m;检查孔9个,孔深4.0~8.0m,进尺42.0m。
(3)钻孔次序。
该工程的钻孔灌浆工作按照先外排后内排,同排间隔钻灌的原则进行。即按照灌浆孔、加强孔、检查孔序次的顺序钻灌,孔深以钻入杂填土为准。按钻孔——下止浆塞——灌浆(自下而上)的工序进行。在遇到塌孔不能成深孔时,则采用先上段后下段的灌浆工艺,灌浆与下段成孔间隔时间不小于24小时。
(4)浆液浓度。
根据《水工建筑物水泥灌浆施工技术规范》,结合本工程实际,我们采用灌浆的水灰比分为3:1、2:1、1:1、0.8:1、0.6:1五个比级,开灌浆液水灰比为3:1,特殊情况下可用2:1或1:1,依次逐级价浓,当某一比级的浆液单位吸浆量大于10L/min且灌入量大于200L时,则加浓一级。当单位吸浆量大于20L/min且灌入量大于400L时,则越级加浓。在低压力、高浓度灌浆单位吸浆量大于20L/min时,则增加速凝剂或其它配料如砂等。
灌注浆液的水灰比一般为2:1~1:1。对于吸浆量很大(单位吸浆量对于20L/min,连续灌入量对于500L)的孔段,采用低压力(自重)、高浓度(0.8~0.6:1)混合浆,间歇式的方法灌注。
(5)灌浆压力。
灌浆压力原则上按照上部荷重和侧壁厚度确定,对外排原则上采取浆柱自重灌浆,但是,当吸浆量很小(小于5L/min)时,则采用0.5Kg/cm2的压力灌浆。对于内排孔,一般采用0.5Kg/cm2的压力。
(6)灌浆结束标准。
当灌浆压力达到设计压力(0.5Kg/cm2),单位吸浆量小于0.4L/min时,则终止本段灌浆。
(7)封孔。
用1:2水泥砂浆逐次回填捣实的方法封至孔口平为止。
(8)质量检查。
钻灌结束后,采用钻孔注浆法进行质量检查,即向孔内注入水灰比1:2的浆液,在规定的压力下,初始10min内注入不超过10L即为合格。
共设检查孔9个,采用钻孔注浆法进行检查,结果表明灌浆全部合格。.
4. 处理后的效果.
基础处理完成7d以后,使用武汉岩海公司生产的RS-JYB全自动桩基静载荷测试分析系统测试,根据规范GBJ7-89和GBJ79-91,将现场测试的三组试验点的原始記录经微机处理后绘制出每组复合地基试验点的Q~s曲线、s~LgQ曲线和s~Lgt曲线。
当Q~s曲线上有明显比例极限时,取该比例极限所对应的荷载为该组地基荷载的标准值。
当极限荷载能确定,而其值又小于对应比例极限荷载值的1.5倍时,取极限荷载的一半为该组地基荷载的标准值。
经过对测试数据进行计算整理,结合场地工程地质勘探资料及水泥灌浆加固地基的特点,根据Q~s、s~LgQ、s~Lgt曲线分析对比,参考本地区实践经验,确定三组复合地基承载力结果分别为143KPa、147KPa、152KPa;三组复合地基承载力平均值为147KPa,极差为3.40%,小于30%,因此,该场地复合地基承载力标准值为147KPa,满足设计要求。.
5. 结论.
采用水泥灌浆技术处理杂填土地基,在安阳市地区尚属首次,本次水泥灌浆法处理杂填土地基,达到了设计要求,实践证明,该方法在理论、实践上可行,费用较低,完全可以达到地基的承载力的要求和确保不出现不均匀沉馅,可以作为建筑行业地基处理的一种参考方式。
[文章编号].1619-2737(2012)07-31-691