南洞庭(胜天)特大桥主桥承台为27.8m×44.8m×7m倒矩形结构,单个承台混凝土总方量为8 184.5m~3,单次最大浇筑方量为2 338m~3,为大体积混凝土。其水化热大,绝热温升高,温度裂纹预防及控制难度大。施工时,通过优化配合比设计、减薄浇筑分层、加强散热效率、降低混凝土的入模温度、全蓄水的保温养生等一系列措施及方法,有效地消除了温度裂纹的产生。
The main dam cap of the South Dongting (Shengtian) Super Bridge is 27.8m × 44.8m × 7m inverted rectangular structure. The total concrete mass of a single cap platform is 8 184.5m 3 and the maximum single pouring square is 2 338m 3. For mass concrete. Its hydration heat, adiabatic temperature rise, temperature crack prevention and control difficult. During construction, a series of measures and methods such as optimizing the mix design, thinning and pouring delamination, strengthening the heat dissipation efficiency, lowering the temperature of the mold for molding, keeping warm and keeping in full water, effectively eliminated the temperature crack.