读者:2007年10月,浙江某建设集团公司(下称总包单位)在总承包某体育馆工程后,将其中幕墙工程的设计、制作、安装分包给福建某幕墙公司上海分公司(下称分包单位)。当幕墙工程进行到尾声时,业主又临时增加了少量工程,此时分包单位向总包单位提出,应该再支付部分工程进度款。而总包单
Readers: In October 2007, Zhejiang Construction Group Company (hereinafter referred to as “EPC”) subcontracted the design, manufacture and installation of the curtain wall project to a curtain wall company in Shanghai (hereinafter referred to as the “Shanghai Branch” Subcontractor). When the curtain wall project comes to an end, the owner temporarily adds a small amount of work. At this time, the subcontractor submits the proposal to the general contractor and should pay part of the construction progress payment again. The total package