一、工程概况波塘水电站位于广西壮族自治区梧州地区的黄华河上,第一期工程装机两台共5,000千瓦(2×2500),j。机组已于1981年10月发电投产。一期工程结束后,为了使其早日发挥效益,增加水电站电能,在坝顶安装高2米的临时简易闸门,将原设计水头抬高2米。放于1982年冬季开始,进行了第二期工程的施工。第二期工程的特点是在需使电站不降低水头、保证1~#机
First, the project profile Bo Tang Hydropower Station is located in Wuzhou, Guangxi Zhuang Autonomous Region on the Huanghe River, the first phase of the installation of two total 5,000 kilowatts (2 × 2500), j. The unit was put into operation in October 1981. After the first phase of the project, in order to make it effective as soon as possible to increase the hydropower station energy, installation of 2 meters high temporary temporary gate at the crest, the original design head elevation of 2 meters. Put in the beginning of the winter of 1982, carried out the second phase of construction. The second phase of the project is characterized by the need to reduce the power plant head, to ensure 1 ~ # machine