论文部分内容阅读
泉州市公路局在南昌大桥引道项目工程施工中,对填土路堤的施工质量采取了一些措施,有效地控制了填土路堤的工后沉降和局部沉陷,取得了较好的成效。经过三年的运行,路堤未发现任何变形,水泥混凝土路面完好,行车平稳,受到建设单位的好评。现将该工程在施工过程中采取的质量管理措施总结如下。南昌大桥引道项目工程是南昌至九江汽车专用公路中的一个合同段,全长2100米。该工程总填方量为50
In the construction of Nanchang Bridge Approach Project, Quanzhou Highway Bureau took some measures to the construction quality of fill embankment, effectively controlled the post-construction settlement and partial settlement of fill embankment, and achieved good results. After three years of operation, the embankment did not find any deformation, cement concrete road surface intact, smooth driving, praised by the construction unit. Now the project in the construction process to take the quality management measures are summarized below. Nanchang Bridge Approach Project is Nanchang to Jiujiang motor vehicle highway in a contract section, a total length of 2100 meters. The total project fill volume is 50