广西黎塘水泥厂,经过几年的努力,厂区的主要土建工程已基本完成,目前正进入全面设备安装阶段。从1978年4月破土动工至今年7月底,累计完成投资额5191万元,占总概算投资的63.5%。计划今年底实现单体试机,明年上半年建成投产。今年初,黎塘水泥厂被列为广西和全国的重点工程项目之一,采取了有效措施,加快了建设步伐。全厂职工同心同德,施工单位和有关部门互相协作,进展顺利。到目前为止,石灰石矿山工程已完成18000多石方,石灰石破碎输送道廊、熟料输送道、两座回转窑、水泥磨、原料磨和铁路专用线等主要基建工程,基本完成,并交付安装。
After several years of efforts, the Guangxi Litang Cement Plant has basically completed the main civil works of the plant and is currently entering the stage of full equipment installation. From groundbreaking in April 1978 to the end of July this year, the accumulated investment amount was 51.91 million yuan, accounting for 63.5% of the total estimated investment. It is planned to implement a monomer testing machine at the end of this year and it will be completed and put into production in the first half of next year. Earlier this year, Litang Cement Plant was listed as one of the key projects in Guangxi and the country, and effective measures were taken to accelerate the pace of construction. The employees of the whole company are united with one another, and the construction unit and related departments are working together to make progress. So far, the limestone mining project has completed more than 18,000 stone, the main infrastructure projects such as limestone crushing and conveying corridor, clinker conveyor road, two rotary kiln, cement mill, raw material mill, and railway special line, and is basically completed and delivered and installed. .