【摘 要】根据降水设计,高层建筑群,建设规模大,投资大,合理确定基坑降水、停水时间,对投资核算及工程项目管理有着深刻的意义。
【关键词】高层建筑群,降水时间,停水时间
High-rise and ultra-high-rise buildings precipitation time cut off the water supply time
He Zhan-xu1,Wu Shao-jing1,Wu Shao-fei2,Zhang Yu2
(1.Henan Aero Geophysical Survey ang Remote Sensing Center Zhengzhou Henan 450053;
2.Henan Geological school employees Zhengzhou Henan 450000)
【Abstract】According toprecipitation design, high-rise and ultra-high-rise buildings, Size of the drive, capital intensive industry, reasonable certaindewatering, cut off the water supply time. investment check computations of object of construction production management have/possess Atticsalt.
【Key words】High-rise and ultra-high-rise buildings;Precipitation time;Cut off the water supply time
1. 前言
无氧铜材总厂金龙花园项目,高层建筑群拟建工程基坑降水方案结合工程地质条件及水位提出降水设计情况如下。
2. 工程概况:
本次拟建工程无氧铜材总厂金龙花园位于新乡市经济开发区,东台头村南部,西邻东干道,南邻二环路,场地地形比较平坦,建筑环境良好。占地面积125200m2 拟建 1栋楼高28层、2栋楼高24层、2栋楼高22层、8栋楼高18层、2栋楼高15层,共15栋高层住宅楼,幼儿园、会所、热力泵房及调压站(60套别野报告另出),等。15栋高层全部采用框剪结构,基础埋深为自然地面下4.5m,,基础埋深18~22层均带地下室一层为7m,15层不带地下室为4m;基底平均压力值620KN/m2,体型复杂,工程重要性等级为一级,抗震设防类别均为丙类。
3. 水文地质条件:
场区内地下水属于空隙潜水类型,受排水管道影响局部有上层滞水存在,补给来源以大气降水和侧向迳流为主,以蒸发和侧向迳流及人工开采为主要排泄途径,动态变化受季节性降水控制,依岩土及力学性质差异可分为上下两段:上段表层为耕植土,厚度0.4m,其下为黄河冲击形成的褐黄色、灰黄色粉质粘土及粉士,属新近沉积土,平均厚度7.8~11.0m。下段为埋深11.70~50m左右为细沙。静止水位在地面下3.8 m,水位年变幅为2.0m左右。
4. 工程地质条件:
地层地质岩性祥见无氧铜材总厂金龙花园岩土工程勘察报告。
5. 降水方案的选择:
人工降水地下水位,常用的方法有轻型井点、喷射井点、电渗井点管井,降水方案选择应根据土层岩性、渗透系数、降水深度和工程特点对各种方法进行综合对比确定,电渗井点主要在淤泥质软土中使用,喷射井点降水深度大,造价高,本工程基坑开挖较浅,可采用相对低廉的管井降水的方法。
6. 基坑降水方案
6.1 设计依据:
《无氧铜材总厂金龙花园岩土工程勘察报告》。
《无氧铜材总厂金龙花园基础平面图》。
《建筑与市政降水工程技术规范》JGJ111-98。
6.2 管井布置:
降水1#楼共布置5眼管井,2#楼共布置5眼管井,井深20m,井间距15~20m,管井成孔外径550mm,管井成井内径300mm,位置详见平面布置图。
7. 施工方法及工艺流程:
7.1 管井成井、管井正式抽水、基坑开挖、防水层施工、基坑回填、 管井封闭 、设备退场。
7.2 结合工程地质条件及水位提出降水设计情况,高层建筑群建设规模大,投资大,合理确定基坑降水停水时间对投资核算及工程项目管理有着深刻的意义。停水时间过早,可能造成过早,可能造成不均匀沉降等质量隐患,停水时间过晚,降水时间无谓延长,会造成建设资金不必要的浪费。要合理确定高层建筑群基坑降水停水时间,必须慎重考虑以下因素:
(1)根据地下水文资料及试验数据进行验算,确定上部建筑结构荷载大于地下水对基坑中基础结构的最大浮力,且基坑中基础结构均高于基坑降水前地下水静水位面,这就要求准确掌握降水前的地下地质水文资料,并且通过计算加以比较。
(2)地下防水工程结束且基坑回填完毕延续一段时间停水。由于高层建筑群面积大,基础开挖深,为了满足基础结构工程施工需要,基坑降水幅度往往较大,地下水形成较大落差,形成了地下水漏斗区,波及面大,影响范围广,动态变化极为复杂,在这个漏斗区内,由于各个建筑的基础形状、大小和构造各不相同,坐标位置不同,故每个基础甚至基础的不同部位受力大小和方向不同,为了避免突然停水对基础带来不利影响,基坑回填完毕后延续一段时间停水是必要的。
(3)在上述漏斗区内,各楼号停水要统筹安排,停水时间和水量控制要一致,否则因停水时间和水量控制不一致可能导致不均匀沉降。
(4)停水要分三个阶段进行,每阶段减少三分之一的抽水量,逐渐减少地下水的抽取,使地下水位缓慢回升,使建筑物逐步适应地下水的浮力,根据我们的工程实践经验,每阶段15~20天为宜,整个停水过程为45~60天。
8. 结论
通过以上几大因素的总结,要合理确定高层建筑群基坑降水停水时间,工程实践经验的总结认为每阶段15~20天为宜,整个停水过程为45~60天为最甲时间。
【关键词】高层建筑群,降水时间,停水时间
High-rise and ultra-high-rise buildings precipitation time cut off the water supply time
He Zhan-xu1,Wu Shao-jing1,Wu Shao-fei2,Zhang Yu2
(1.Henan Aero Geophysical Survey ang Remote Sensing Center Zhengzhou Henan 450053;
2.Henan Geological school employees Zhengzhou Henan 450000)
【Abstract】According toprecipitation design, high-rise and ultra-high-rise buildings, Size of the drive, capital intensive industry, reasonable certaindewatering, cut off the water supply time. investment check computations of object of construction production management have/possess Atticsalt.
【Key words】High-rise and ultra-high-rise buildings;Precipitation time;Cut off the water supply time
1. 前言
无氧铜材总厂金龙花园项目,高层建筑群拟建工程基坑降水方案结合工程地质条件及水位提出降水设计情况如下。
2. 工程概况:
本次拟建工程无氧铜材总厂金龙花园位于新乡市经济开发区,东台头村南部,西邻东干道,南邻二环路,场地地形比较平坦,建筑环境良好。占地面积125200m2 拟建 1栋楼高28层、2栋楼高24层、2栋楼高22层、8栋楼高18层、2栋楼高15层,共15栋高层住宅楼,幼儿园、会所、热力泵房及调压站(60套别野报告另出),等。15栋高层全部采用框剪结构,基础埋深为自然地面下4.5m,,基础埋深18~22层均带地下室一层为7m,15层不带地下室为4m;基底平均压力值620KN/m2,体型复杂,工程重要性等级为一级,抗震设防类别均为丙类。
3. 水文地质条件:
场区内地下水属于空隙潜水类型,受排水管道影响局部有上层滞水存在,补给来源以大气降水和侧向迳流为主,以蒸发和侧向迳流及人工开采为主要排泄途径,动态变化受季节性降水控制,依岩土及力学性质差异可分为上下两段:上段表层为耕植土,厚度0.4m,其下为黄河冲击形成的褐黄色、灰黄色粉质粘土及粉士,属新近沉积土,平均厚度7.8~11.0m。下段为埋深11.70~50m左右为细沙。静止水位在地面下3.8 m,水位年变幅为2.0m左右。
4. 工程地质条件:
地层地质岩性祥见无氧铜材总厂金龙花园岩土工程勘察报告。
5. 降水方案的选择:
人工降水地下水位,常用的方法有轻型井点、喷射井点、电渗井点管井,降水方案选择应根据土层岩性、渗透系数、降水深度和工程特点对各种方法进行综合对比确定,电渗井点主要在淤泥质软土中使用,喷射井点降水深度大,造价高,本工程基坑开挖较浅,可采用相对低廉的管井降水的方法。
6. 基坑降水方案
6.1 设计依据:
《无氧铜材总厂金龙花园岩土工程勘察报告》。
《无氧铜材总厂金龙花园基础平面图》。
《建筑与市政降水工程技术规范》JGJ111-98。
6.2 管井布置:
降水1#楼共布置5眼管井,2#楼共布置5眼管井,井深20m,井间距15~20m,管井成孔外径550mm,管井成井内径300mm,位置详见平面布置图。
7. 施工方法及工艺流程:
7.1 管井成井、管井正式抽水、基坑开挖、防水层施工、基坑回填、 管井封闭 、设备退场。
7.2 结合工程地质条件及水位提出降水设计情况,高层建筑群建设规模大,投资大,合理确定基坑降水停水时间对投资核算及工程项目管理有着深刻的意义。停水时间过早,可能造成过早,可能造成不均匀沉降等质量隐患,停水时间过晚,降水时间无谓延长,会造成建设资金不必要的浪费。要合理确定高层建筑群基坑降水停水时间,必须慎重考虑以下因素:
(1)根据地下水文资料及试验数据进行验算,确定上部建筑结构荷载大于地下水对基坑中基础结构的最大浮力,且基坑中基础结构均高于基坑降水前地下水静水位面,这就要求准确掌握降水前的地下地质水文资料,并且通过计算加以比较。
(2)地下防水工程结束且基坑回填完毕延续一段时间停水。由于高层建筑群面积大,基础开挖深,为了满足基础结构工程施工需要,基坑降水幅度往往较大,地下水形成较大落差,形成了地下水漏斗区,波及面大,影响范围广,动态变化极为复杂,在这个漏斗区内,由于各个建筑的基础形状、大小和构造各不相同,坐标位置不同,故每个基础甚至基础的不同部位受力大小和方向不同,为了避免突然停水对基础带来不利影响,基坑回填完毕后延续一段时间停水是必要的。
(3)在上述漏斗区内,各楼号停水要统筹安排,停水时间和水量控制要一致,否则因停水时间和水量控制不一致可能导致不均匀沉降。
(4)停水要分三个阶段进行,每阶段减少三分之一的抽水量,逐渐减少地下水的抽取,使地下水位缓慢回升,使建筑物逐步适应地下水的浮力,根据我们的工程实践经验,每阶段15~20天为宜,整个停水过程为45~60天。
8. 结论
通过以上几大因素的总结,要合理确定高层建筑群基坑降水停水时间,工程实践经验的总结认为每阶段15~20天为宜,整个停水过程为45~60天为最甲时间。