8月4日零时,随着年150万吨常减压蒸馏装置开始降量,呼和浩特石化公司一期工程常减压蒸馏和催化裂化等装置完成19年历史使命,与重整和加氢装置全部关停,比原计划提前11天。一年来,呼石化坚持一期工程安全平稳生产和500万吨/年工程建设“两线作战”。随着500万吨/年工程有序推进,一期工程装置关停后,呼石化将把全部精力转向工程建设。预计2012年5月30日生产
At 0:00 on the August 4, with the annual 1.5 million tons of atmospheric and vacuum distillation unit began to drop, the first phase of Hohhot Petrochemical Company atmospheric and vacuum distillation and catalytic cracking and other devices to complete the 19-year historical mission, and the reforming and hydrogenation unit All shut down, 11 days earlier than originally planned. In the past year, Huhua Petrochemical Company adhered to the safe and stable production of the first phase of its project and the construction of 5 million tons / year of “two-line operation.” With 5000000 tons / year project in an orderly manner, a shut down the installation of equipment, Huhua will turn all the energy to construction. Expected on May 30, 2012 production