浙江省余姚县克服了吊装设备不足的困难,修建了一座三孔跨径12.5米全长46.6米的钢筋混凝土装配式 T 梁桥,兹就其安装情况简介如下:桥面净宽为7米加人行道每边各1.5米,上部结构12.5米钢筋混凝土装配式 T 梁每孔7块,边梁每块重14.6吨,中梁每块重12.6吨。全部 T 梁在桥头预制后,拖拉上桥安装。1.施工布置。第一孔墩台砌筑时,就在桥头预制T 梁,在第二、三两孔墩台砌筑完成时,第一孔5根 T 梁就可拖拉上桥就位。这样,砌筑墩台、预制 T梁、安装等工序交错进行,既缩短了施工时间,又可充分利用场地,场地布置如图1。
Yuyao County, Zhejiang Province to overcome the lack of hoisting equipment difficulties, the construction of a three-hole span of 12.5 meters full-length 46.6 meters of reinforced concrete T-beam bridge assembly, it is installed on the profile is as follows: deck width of 7 meters plus Each side of the sidewalk 1.5 meters, 12.5 meters of the upper structure of reinforced concrete beam T-7 per hole, each weighing 14.6 tons of side beams, each weighing 12.6 tons of beams. After all the T-beams are prefabricated at the bridgehead, drag the bridge to install. 1. Construction layout. The first pier pier masonry, prefabricated T beam in the bridge, in the second and third holes Pier masonry completion, the first hole of 5 T beam can drag the bridge in place. In this way, masonry pier, prefabricated T beam, installation and other processes staggered, not only shorten the construction time, but also make full use of venues, venues layout shown in Figure 1.