Abstract: mine construction entered the second period before construction, safe and reliable ventilation problems become construction a bottleneck. With local fan ventilation group do not conform to national relevant provision, to bring production safety hazard. Use the permanent main fan ventilation in the car are the major status, economy is not viable, and the state advocates for energy conservation and emission reduction in personality. By installing the fan can meet the safety in production, accord with national regulations, can achieve more energy saving effect.
Keywords: mine of the second phase of the project, ventilation safety, fan installation, energy conservation and emission reduction
中图分类号: TD72 文献标识码: A 文章编号:
1 羊东工程施工概况
羊东工程的施工进度,关系到羊东矿井的水平接替,羊东副井井底早一天进入二期施工,羊东矿的生产就早主动一天。但由于施工场地制约,永久抽风机房施工滞后,如何解决风井与副井贯通后的通风问题,成为开拓-850水平井巷工程的关键问题。
2 羊东安设前期风机的必要性
根据施工工期安排2011年1月份羊东将具备井底车场施工条件。2011年3月东副井与风井贯通,具备四组队伍同时施工的条件。因此,在2011年3月9日前形成安全可靠的通风系统,可使多组施工队伍同时施工。按国家煤矿安全监察局发改能源(2010)709号文第七条规定:“高瓦斯、煤(岩)与瓦斯(二氧化碳)突出矿井,进入二期工程前,必须形成由地面主要通风机供风的全风压通风系统”。根据相关规定要求如果不进行前期风机安装,只能在7月份才能开始多组队伍进行施工,既影响施工进度,又不利于安全生产。因此,安装前期风机是十分必要的。另外,预计从矿井一期到矿井二期前半程施工期间,若直接采用永久风机,则会出现风机大马拉小车的的状况,经济不合算,综上所述安装前期风机是完全必要的也是经济合理的。
3机械设备选型
3.1选型依据
矿井通风风量:50.4m3/s
矿井通风负压:300Pa(通风容易期)360Pa(通风困难期)
3.2设备选型
必需的风量和负压为: Qb=1.05×50.4=52.92m3/s
容易期负压:H= h易+⊿h+hz =300+200+400=900Pa
困难期负压:H= h难+⊿h+hz =360+200+400=960Pa
式中h易—容易期有效负压 Pa
h难—困难期有效负压 Pa
⊿h—通风设备压力损失,取200 Pa
hZ—自然风压,取400 Pa
根据需求选用两台FBCDZ-8-№18B型对旋式风机,一台工作,一台备用,配备电动机功率75×2kW。风量30m3/s~68m3/s。风压506-1913Pa,风机转速n=740r/min,风机采用反转返风的方式。随机定购蝶式阀以作风道闸门用。
3.3供电电源
两路电源从矿井利用现有地面6KV变电所,低压380V不同母线段馈出,两路电源进线采用YJV22-0.6/1KV-3×240+1×120mm²电力电缆,地埋敷设。两路电源均为专线,以满足通风机供电电源要求。前期通风机附设风机房配电室,配电室又分为低压配电室和风机房控制室;其中低压配电室设5台TJJ-1型低压配电柜,分别为2台进线柜,2台风机及低压辅助设备配电柜,为两台2×75kW对旋式轴流通风机提供供电电源,电机采用软启动。风机房控制室可以实现对风机进行在线监测和控制。
为保证矿井安全生產和通风机正常工作,设计选用煤矿主扇风机计算机监控、监视及无线网络通讯系统KS-TF/I型一套,该系统可快速准确地测量温度、压力、流量及振动等参数,通过通讯、信号测量和在线监测技术手段,可满足风机运行和计量的要求,永久风机投运后可改造使用。
4节能减排,减少投资资金
4.1尽量延长前期风机的使用时间,延缓大型风机的投运时间,避免从矿井二期到矿井三期前半程施工期间出现风机大马拉小车的的状况。前期风机电机功率2×75kw,永久风机电机功率1000kw。前期风机预计最少使用12个月。粗略估算下节省电费:(1000-150)kw×24小时/天×365天×0.9元kw/时=670万元,而前期通风工程总投资概算为272.87万元。
4.2前期风机风道利用风井安全通道,风道断面为3m×3m,中间加两道相反方向风门,在风道尽头加两道风门做为安全出口及风量观测,不用再建风道,减少土建工程量。
4.3由于前期风机供电系统利用现有地面配电室,不用在单独建立高压、低压配电室,订购高压设备及变压器,节约了资金。
羊东-850水平南翼回风与52回风贯通后,永久风机启动,前期风机停止运行。前期风机投入运行符合了相关规定要求,保证了生产顺利进行,在施工的过度期间发挥了作用,减少了能源浪费,节约了成本,为以后集团公司其它矿井延深提供了宝贵经验。
注:文章内所有公式及图表请以PDF形式查看。
关键词:矿井二期工程、通风安全、风机安装、节能减排
Abstract: mine construction entered the second period before construction, safe and reliable ventilation problems become construction a bottleneck. With local fan ventilation group do not conform to national relevant provision, to bring production safety hazard. Use the permanent main fan ventilation in the car are the major status, economy is not viable, and the state advocates for energy conservation and emission reduction in personality. By installing the fan can meet the safety in production, accord with national regulations, can achieve more energy saving effect.
Keywords: mine of the second phase of the project, ventilation safety, fan installation, energy conservation and emission reduction
中图分类号: TD72 文献标识码: A 文章编号:
1 羊东工程施工概况
羊东工程的施工进度,关系到羊东矿井的水平接替,羊东副井井底早一天进入二期施工,羊东矿的生产就早主动一天。但由于施工场地制约,永久抽风机房施工滞后,如何解决风井与副井贯通后的通风问题,成为开拓-850水平井巷工程的关键问题。
2 羊东安设前期风机的必要性
根据施工工期安排2011年1月份羊东将具备井底车场施工条件。2011年3月东副井与风井贯通,具备四组队伍同时施工的条件。因此,在2011年3月9日前形成安全可靠的通风系统,可使多组施工队伍同时施工。按国家煤矿安全监察局发改能源(2010)709号文第七条规定:“高瓦斯、煤(岩)与瓦斯(二氧化碳)突出矿井,进入二期工程前,必须形成由地面主要通风机供风的全风压通风系统”。根据相关规定要求如果不进行前期风机安装,只能在7月份才能开始多组队伍进行施工,既影响施工进度,又不利于安全生产。因此,安装前期风机是十分必要的。另外,预计从矿井一期到矿井二期前半程施工期间,若直接采用永久风机,则会出现风机大马拉小车的的状况,经济不合算,综上所述安装前期风机是完全必要的也是经济合理的。
3机械设备选型
3.1选型依据
矿井通风风量:50.4m3/s
矿井通风负压:300Pa(通风容易期)360Pa(通风困难期)
3.2设备选型
必需的风量和负压为: Qb=1.05×50.4=52.92m3/s
容易期负压:H= h易+⊿h+hz =300+200+400=900Pa
困难期负压:H= h难+⊿h+hz =360+200+400=960Pa
式中h易—容易期有效负压 Pa
h难—困难期有效负压 Pa
⊿h—通风设备压力损失,取200 Pa
hZ—自然风压,取400 Pa
根据需求选用两台FBCDZ-8-№18B型对旋式风机,一台工作,一台备用,配备电动机功率75×2kW。风量30m3/s~68m3/s。风压506-1913Pa,风机转速n=740r/min,风机采用反转返风的方式。随机定购蝶式阀以作风道闸门用。
3.3供电电源
两路电源从矿井利用现有地面6KV变电所,低压380V不同母线段馈出,两路电源进线采用YJV22-0.6/1KV-3×240+1×120mm²电力电缆,地埋敷设。两路电源均为专线,以满足通风机供电电源要求。前期通风机附设风机房配电室,配电室又分为低压配电室和风机房控制室;其中低压配电室设5台TJJ-1型低压配电柜,分别为2台进线柜,2台风机及低压辅助设备配电柜,为两台2×75kW对旋式轴流通风机提供供电电源,电机采用软启动。风机房控制室可以实现对风机进行在线监测和控制。
为保证矿井安全生產和通风机正常工作,设计选用煤矿主扇风机计算机监控、监视及无线网络通讯系统KS-TF/I型一套,该系统可快速准确地测量温度、压力、流量及振动等参数,通过通讯、信号测量和在线监测技术手段,可满足风机运行和计量的要求,永久风机投运后可改造使用。
4节能减排,减少投资资金
4.1尽量延长前期风机的使用时间,延缓大型风机的投运时间,避免从矿井二期到矿井三期前半程施工期间出现风机大马拉小车的的状况。前期风机电机功率2×75kw,永久风机电机功率1000kw。前期风机预计最少使用12个月。粗略估算下节省电费:(1000-150)kw×24小时/天×365天×0.9元kw/时=670万元,而前期通风工程总投资概算为272.87万元。
4.2前期风机风道利用风井安全通道,风道断面为3m×3m,中间加两道相反方向风门,在风道尽头加两道风门做为安全出口及风量观测,不用再建风道,减少土建工程量。
4.3由于前期风机供电系统利用现有地面配电室,不用在单独建立高压、低压配电室,订购高压设备及变压器,节约了资金。
羊东-850水平南翼回风与52回风贯通后,永久风机启动,前期风机停止运行。前期风机投入运行符合了相关规定要求,保证了生产顺利进行,在施工的过度期间发挥了作用,减少了能源浪费,节约了成本,为以后集团公司其它矿井延深提供了宝贵经验。