鲁布革水电站压力钢管工程是国际招标项目C_1合同的一部分,由日本川崎重工与水电部第十四工程局安装公司合作施工。工程的施工方案、技术措施、工艺规程以川崎重工为主编制。技术规范和质量标准均达到了国际上同类工程的水平。工程自1986年1月13日开工准备,至1987年9月25日提前竣工,历时约20个月。其使用劳动力2500人·月。各项技术经济指标都取得了较好的结果,工程质量得到国内外专家的
The Ruipeng Hydropower Station pressure pipe project is part of the C_1 contract of the international bidding project. The Kawasaki Heavy Industries Co., Ltd. and the installation company of the Fourteenth Engineering Bureau of the Ministry of Water Resources jointly set up the project. Construction program, technical measures, process planning to Kawasaki heavy industry-based system. Technical specifications and quality standards have reached the level of similar projects in the world. The project started construction on January 13, 1986 and was completed ahead of schedule on September 25, 1987, which lasted for about 20 months. Its use of labor force 2,500 people month. The technical and economic indicators have achieved good results, the quality of the project by domestic and foreign experts