摘 要:在城市化发展的进程中,为了满足新时期经济建设的基本要求,同时让人们的生产生活用电得到充分满足,需要提高对高压电缆工程的重视。在相关工程作业的开展过程中,需要合理选择科学的地基处理方法,使得软土地基得到有效处理,从而提高地基承载能力,让工程建设更加稳定。施工人员需要对施工现场的地质条件做好分析,同时结合环境状态,完成地基处理方案的制订,提升工程施工使用过程中的安全性。
关键词:高压电缆工程 地基处理 高压旋喷桩 软土地基
中图分类号:TM75 文献标识码:A文章编号:1672-3791(2021)09(a)-0022-03
Common Foundation Treatment Schemes for High-voltage Cable Engineering
YOU Huawu1 CHANG Long2
(1.Nari Power Design Co., Ltd., Fuzhou, Fujian Province, 350007 China; 2.Nari Power Design Co., Ltd., Nanjing, Jiangsu Province, 211100 China)
Abstract: In the process of urbanization, in order to meet the basic requirements of economic construction in the new era and fully meet people's production and living electricity, we need to pay more attention to high-voltage cable engineering. In the process of relevant engineering operations, it is necessary to rationally choose scientific foundation treatment methods to effectively treat the soft soil foundation, so as to improve the foundation bearing capacity and make the engineering construction more stable. The construction personnel need to analyze the geological conditions of the construction site, and at the same time, complete the formulation of the foundation treatment plan in combination with the environmental status, so as to improve the safety during the construction and use of the project.
Key Words: High-voltage cable engineering; Foundation treatment; High-pressure jet grouting pile; Soft soil foundation
对于高压电缆工程的质量保证而言,电缆沟有着重要影响和作用,良好的电缆沟结构能够为电力系统的稳定运行提供基础保障。施工人员需要提高自身的技术水平,同时根据实际情况编制合理的地基处理方案。
1 軟土工程具备的基本特点
1.1 含水量较高
软土地基与普通地基相比较而言,含水量较高,并且空隙较大。通常情况下,淤泥以及淤泥质土的天然含水量在50%~70%,软土的天然孔隙比约为1∶2,此种情况较液限而言较高。除此之外,软土地基的透水性能较差,如果在此种条件下承担一定的强载荷,会使得孔隙中的水压力升高,进而影响地基的压密固结性。
1.2 抗剪性能较低
软土地基具备较弱的抗剪强度,软土的流动性相对较强,一旦接受外部载荷的作用,会使其抗剪能力减弱,由于土层具备一定的排水功能,但是在外界压力逐渐增大的条件下,会使得排水出路发生固结。如果土层中的多余水分无法顺利排出,则会导致地基的强度不断下降。
2 基本处理原则分析
在地基处理的过程中,需要提高对基本原则的重视及加强落实,主要包括确保质量、技术先进以及安全可靠等,施工人员及技术人员需要针对施工现场的地质条件以及环境因素做好分析和调查,同时掌握结构物基本条件。首先,结合电缆管沟的实际功能以及地质特点,站在总体最优方向进行充分考虑,同时针对线路而言,可以允许其出现可控范围内的沉降量,实际目的是为了将线路间可能出现的不均匀沉降消除;其次,在编制地基处理方案的过程中,需要对上部载荷进行充分考虑,结合竖向变形程度,并认真分析后续施工过程中会出现的电缆管水平侧移问题[1-2]。
3 有效的处理方案
施工人员需要对相关原则进行明确及落实,结合实际情况,做好地基处理方案的编制工作。首先,针对紧邻道路的路基而言,如果经过高压旋喷桩进行加固处理,可以不用再做任何处理,对管沟做好明确设置,为加固道路的路基选择最佳位置;其次,针对局部位置存在淤泥质土,需要提高对换填技术的重视程度,利用良好级配的砂石进行换填,之后采取有效措施进行相应的分层碾压以及夯实处理;再次,如果存在跨河桥架的架设需求,施工人员应该对浇筑钢筋混凝土搅拌桩进行利用,同时做好夯实处理;最后,如果工程中有条状软弱地基,为了提高其整体的强度,需要对水泥搅拌桩进行合理利用,做好加固工作[3]。 4 高压电缆工程地基处理方法实例说明
4.1 工程基本情况分析
将某高压电缆工程为例进行分析,此工程为新建110 kV甲、乙线,以220 kV某村变电站为起点,将某拟建110 kV变电站作为终点。涉及的新建双回电缆总体长度为2×3.145 km。通过工作人员细致的地质勘察,明确地质表层为耕植土或者是人工填土,覆盖层的整体厚度范围在0.5~1.0 m之间,在覆盖层下方为淤泥层,实际厚度范围为0.9~9.3 m,而存在3.6~10.2 m厚度范围的黏土层。在以上土层下方为强风化泥质砂岩层,整體的埋藏深度不超过35 m。在此工程的地质剖面构成中,自下而上包含黏土、中密状含淤质砾砂卵石以及杂填土等,针对其中的含淤质砾砂卵石而言,总体的埋深约为4 m左右,通过比较分析,是相对来说最佳的持力层选择。
4.2 高压电缆工程软土地基处理方案
4.2.1 高压喷桩挡墙的实际应用
针对高压旋喷挡墙施工作业开展方案设计工作,首先,需要对高压旋喷桩桩径进行明确,具体值为500 mm,同时确定相邻桩的实际咬合尺寸为100 mm,并设定桩顶的标高为4 m,在以上条件的基础上,需要保证桩身能够到达稳定地层的位置,总体长度设定为10 m。在实际开展施工作业过程中,施工人员应该让注浆管深入到土层中,在实际深度达到要求标准后,对高压射流进行利用,使得地基土结构得到相应的破坏,并对压力做好控制,具体范围为20~40 MPa,向土层中注入适量的浆液之后,浆液会与土体发生混合,从而形成相应的旋喷桩,在桩体相互咬合的作用下,得到地下连续重力式挡墙,此类墙体具有较强的止水以及挡水作用。
4.2.2 高压旋喷桩复合地基的实际应用
对高压旋喷桩复合地基方案的利用,不仅可以让地基土自身的承载能力得到提高,还可以有效避免区域内地面以及电缆沟出现沉降问题。首先,将高压旋喷桩的桩径设定为500 mm,同时以梅花的形式进行旋喷桩的布置工作,并对两个相邻桩之间的距离做好合理控制,约为1 m左右,对桩顶标高进行明确,合理值为5.5 m,在开展施工作业过程中,施工人员应该对桩身进入地层时的平稳性进行有效保证。同时,通过对施工现场地质条件的分析,使得施工参数得到合理明确,通常情况下会将桩长控制在15 m左右,对原有的挡土墙结构进行保留,并根据设计图纸的要求和标准,针对电缆沟开展二次施工作业。
4.2.3 保证电缆沟的稳定性
为了让电缆沟的稳定性及可靠性得到保证,需要有针对性地做好架空处理,施工人员应该提高对施工中支架的重视,采取有效措施提高其稳固性,减少桩身变形以及倾倒等事故的发生。同时对小型施工机械进行有效利用,让工程整体的施工得到合理辅助,将原有的混凝土地面拆除,同时剔除掉原有的电缆沟,在此过程中需要注重对挡土墙以及电缆的保护。为了实现以上目标,需要施工人员开展针对素土的回填工作,并采取有效措施进行整平,在回填作业过程中,应将细砂或者粉质黏土作为主要的回填土,同时保证回填土中不含有任何其他杂质[4-5]。为了保证电缆沟的稳定性及安全性,可以对新型电缆沟结构的制作方法进行研究和利用,避免出现不均匀沉降。
5 施工注意事项
针对地基处理施工作业而言,在对高压旋喷桩进行利用时,需要有几个注意事项:首先,施工人员需要对钻机与高压注浆泵之前的距离做好合理控制和明确,一旦存在孔深不达标的情况,或者在勘察过程中发现钻孔地下存在障碍物等情况,需要将此类情况做好详实记录;其次,施工人员需要保证注浆管贯入土层时,严格按照设计方案对喷射注浆参数进行明确,并按照由上向下的顺序对注浆管做好匀速提升的操作,从而保证喷射注浆的均匀;最后,如果在以上操作过程中,出现异常情况,需要对具体原因进行合理明确,并采取有效措施做好相应处理[6]。
6 结语
针对电力线路的工程施工作业而言,需要对安全性及稳定性提高重视,同时在相关工作开展过程中需要面对很多困难和阻碍,施工人员应该充分发挥自身的专业性,选择合适的施工技术和方法。尤其对于软土地基而言,其具有含水量大以及承载能力低等特点,需要施工人员通过对实际情况的分析,对有效的地基处理方法进行明确,同时编制科学的施工方案,让地基变得更加可靠,为高压电缆的埋设及使用提供全面保障。
参考文献
[1] 吕鹏远.高压光电复合电缆载流量分析与工程应用研究[J].电子设计工程,2021,29(18):135-139,147.
[2] 余乾良.有效加强电力基建地基处理的措施分析[J].建筑与装饰,2018(3):139.
[3] 张敬敏.电力工程电气专业与土建施工配合的建议措施新探[J].科技创新与应用,2021,11(17):115-117.
[4] 徐瑞芃.输变电工程项目关键成功因素研究[D].郑州:郑州大学,2020.
[5] 李继攀.架空线路绝缘漆喷涂机器人的研制[D].长春:长春工业大学,2018.
[6] 霍伟珺.旋喷桩施工技术在重载铁路路基加固中的应用研究[D].石家庄:石家庄铁道大学,2018.
摘 要:在城市化发展的进程中,为了满足新时期经济建设的基本要求,同时让人们的生产生活用电得到充分满足,需要提高对高压电缆工程的重视。在相关工程作业的开展过程中,需要合理选择科学的地基处理方法,使得软土地基得到有效处理,从而提高地基承载能力,让工程建设更加稳定。施工人员需要对施工现场的地质条件做好分析,同时结合环境状态,完成地基处理方案的制订,提升工程施工使用过程中的安全性。
关键词:高压电缆工程 地基处理 高压旋喷桩 软土地基
中图分类号:TM75 文献标识码:A文章编号:1672-3791(2021)09(a)-0022-03
Common Foundation Treatment Schemes for High-voltage Cable Engineering
YOU Huawu1 CHANG Long2
(1.Nari Power Design Co., Ltd., Fuzhou, Fujian Province, 350007 China; 2.Nari Power Design Co., Ltd., Nanjing, Jiangsu Province, 211100 China)
Abstract: In the process of urbanization, in order to meet the basic requirements of economic construction in the new era and fully meet people's production and living electricity, we need to pay more attention to high-voltage cable engineering. In the process of relevant engineering operations, it is necessary to rationally choose scientific foundation treatment methods to effectively treat the soft soil foundation, so as to improve the foundation bearing capacity and make the engineering construction more stable. The construction personnel need to analyze the geological conditions of the construction site, and at the same time, complete the formulation of the foundation treatment plan in combination with the environmental status, so as to improve the safety during the construction and use of the project.
Key Words: High-voltage cable engineering; Foundation treatment; High-pressure jet grouting pile; Soft soil foundation
对于高压电缆工程的质量保证而言,电缆沟有着重要影响和作用,良好的电缆沟结构能够为电力系统的稳定运行提供基础保障。施工人员需要提高自身的技术水平,同时根据实际情况编制合理的地基处理方案。
1 軟土工程具备的基本特点
1.1 含水量较高
软土地基与普通地基相比较而言,含水量较高,并且空隙较大。通常情况下,淤泥以及淤泥质土的天然含水量在50%~70%,软土的天然孔隙比约为1∶2,此种情况较液限而言较高。除此之外,软土地基的透水性能较差,如果在此种条件下承担一定的强载荷,会使得孔隙中的水压力升高,进而影响地基的压密固结性。
1.2 抗剪性能较低
软土地基具备较弱的抗剪强度,软土的流动性相对较强,一旦接受外部载荷的作用,会使其抗剪能力减弱,由于土层具备一定的排水功能,但是在外界压力逐渐增大的条件下,会使得排水出路发生固结。如果土层中的多余水分无法顺利排出,则会导致地基的强度不断下降。
2 基本处理原则分析
在地基处理的过程中,需要提高对基本原则的重视及加强落实,主要包括确保质量、技术先进以及安全可靠等,施工人员及技术人员需要针对施工现场的地质条件以及环境因素做好分析和调查,同时掌握结构物基本条件。首先,结合电缆管沟的实际功能以及地质特点,站在总体最优方向进行充分考虑,同时针对线路而言,可以允许其出现可控范围内的沉降量,实际目的是为了将线路间可能出现的不均匀沉降消除;其次,在编制地基处理方案的过程中,需要对上部载荷进行充分考虑,结合竖向变形程度,并认真分析后续施工过程中会出现的电缆管水平侧移问题[1-2]。
3 有效的处理方案
施工人员需要对相关原则进行明确及落实,结合实际情况,做好地基处理方案的编制工作。首先,针对紧邻道路的路基而言,如果经过高压旋喷桩进行加固处理,可以不用再做任何处理,对管沟做好明确设置,为加固道路的路基选择最佳位置;其次,针对局部位置存在淤泥质土,需要提高对换填技术的重视程度,利用良好级配的砂石进行换填,之后采取有效措施进行相应的分层碾压以及夯实处理;再次,如果存在跨河桥架的架设需求,施工人员应该对浇筑钢筋混凝土搅拌桩进行利用,同时做好夯实处理;最后,如果工程中有条状软弱地基,为了提高其整体的强度,需要对水泥搅拌桩进行合理利用,做好加固工作[3]。 4 高压电缆工程地基处理方法实例说明
4.1 工程基本情况分析
将某高压电缆工程为例进行分析,此工程为新建110 kV甲、乙线,以220 kV某村变电站为起点,将某拟建110 kV变电站作为终点。涉及的新建双回电缆总体长度为2×3.145 km。通过工作人员细致的地质勘察,明确地质表层为耕植土或者是人工填土,覆盖层的整体厚度范围在0.5~1.0 m之间,在覆盖层下方为淤泥层,实际厚度范围为0.9~9.3 m,而存在3.6~10.2 m厚度范围的黏土层。在以上土层下方为强风化泥质砂岩层,整體的埋藏深度不超过35 m。在此工程的地质剖面构成中,自下而上包含黏土、中密状含淤质砾砂卵石以及杂填土等,针对其中的含淤质砾砂卵石而言,总体的埋深约为4 m左右,通过比较分析,是相对来说最佳的持力层选择。
4.2 高压电缆工程软土地基处理方案
4.2.1 高压喷桩挡墙的实际应用
针对高压旋喷挡墙施工作业开展方案设计工作,首先,需要对高压旋喷桩桩径进行明确,具体值为500 mm,同时确定相邻桩的实际咬合尺寸为100 mm,并设定桩顶的标高为4 m,在以上条件的基础上,需要保证桩身能够到达稳定地层的位置,总体长度设定为10 m。在实际开展施工作业过程中,施工人员应该让注浆管深入到土层中,在实际深度达到要求标准后,对高压射流进行利用,使得地基土结构得到相应的破坏,并对压力做好控制,具体范围为20~40 MPa,向土层中注入适量的浆液之后,浆液会与土体发生混合,从而形成相应的旋喷桩,在桩体相互咬合的作用下,得到地下连续重力式挡墙,此类墙体具有较强的止水以及挡水作用。
4.2.2 高压旋喷桩复合地基的实际应用
对高压旋喷桩复合地基方案的利用,不仅可以让地基土自身的承载能力得到提高,还可以有效避免区域内地面以及电缆沟出现沉降问题。首先,将高压旋喷桩的桩径设定为500 mm,同时以梅花的形式进行旋喷桩的布置工作,并对两个相邻桩之间的距离做好合理控制,约为1 m左右,对桩顶标高进行明确,合理值为5.5 m,在开展施工作业过程中,施工人员应该对桩身进入地层时的平稳性进行有效保证。同时,通过对施工现场地质条件的分析,使得施工参数得到合理明确,通常情况下会将桩长控制在15 m左右,对原有的挡土墙结构进行保留,并根据设计图纸的要求和标准,针对电缆沟开展二次施工作业。
4.2.3 保证电缆沟的稳定性
为了让电缆沟的稳定性及可靠性得到保证,需要有针对性地做好架空处理,施工人员应该提高对施工中支架的重视,采取有效措施提高其稳固性,减少桩身变形以及倾倒等事故的发生。同时对小型施工机械进行有效利用,让工程整体的施工得到合理辅助,将原有的混凝土地面拆除,同时剔除掉原有的电缆沟,在此过程中需要注重对挡土墙以及电缆的保护。为了实现以上目标,需要施工人员开展针对素土的回填工作,并采取有效措施进行整平,在回填作业过程中,应将细砂或者粉质黏土作为主要的回填土,同时保证回填土中不含有任何其他杂质[4-5]。为了保证电缆沟的稳定性及安全性,可以对新型电缆沟结构的制作方法进行研究和利用,避免出现不均匀沉降。
5 施工注意事项
针对地基处理施工作业而言,在对高压旋喷桩进行利用时,需要有几个注意事项:首先,施工人员需要对钻机与高压注浆泵之前的距离做好合理控制和明确,一旦存在孔深不达标的情况,或者在勘察过程中发现钻孔地下存在障碍物等情况,需要将此类情况做好详实记录;其次,施工人员需要保证注浆管贯入土层时,严格按照设计方案对喷射注浆参数进行明确,并按照由上向下的顺序对注浆管做好匀速提升的操作,从而保证喷射注浆的均匀;最后,如果在以上操作过程中,出现异常情况,需要对具体原因进行合理明确,并采取有效措施做好相应处理[6]。
6 结语
针对电力线路的工程施工作业而言,需要对安全性及稳定性提高重视,同时在相关工作开展过程中需要面对很多困难和阻碍,施工人员应该充分发挥自身的专业性,选择合适的施工技术和方法。尤其对于软土地基而言,其具有含水量大以及承载能力低等特点,需要施工人员通过对实际情况的分析,对有效的地基处理方法进行明确,同时编制科学的施工方案,让地基变得更加可靠,为高压电缆的埋设及使用提供全面保障。
参考文献
[1] 吕鹏远.高压光电复合电缆载流量分析与工程应用研究[J].电子设计工程,2021,29(18):135-139,147.
[2] 余乾良.有效加强电力基建地基处理的措施分析[J].建筑与装饰,2018(3):139.
[3] 张敬敏.电力工程电气专业与土建施工配合的建议措施新探[J].科技创新与应用,2021,11(17):115-117.
[4] 徐瑞芃.输变电工程项目关键成功因素研究[D].郑州:郑州大学,2020.
[5] 李继攀.架空线路绝缘漆喷涂机器人的研制[D].长春:长春工业大学,2018.
[6] 霍伟珺.旋喷桩施工技术在重载铁路路基加固中的应用研究[D].石家庄:石家庄铁道大学,2018.