摘要:井筒是矿井提升的咽喉,它承担着矿井提升升降人员、提升矸石、下放材料等任务。井筒涌水是大多数矿井都存在的问题,井筒涌水得不到合理的治理,必将给矿井生产带来巨大的影响。首山一矿副井井筒直径7.0米,井筒深度700.5米。副井井筒在-223米-322米位置穿过平顶山砂岩等富有含水层,且裂隙比较发育,井筒涌水量比较大,井筒涌水基本保持稳定在25m3/h左右。这给矿井生产带来很大的不便。
经过对副井涌水情况的分析,制定出了治理方案。同时,形成了井筒截导防治水新颖的施工工法。由于在防治水方面效果明显,技术先进,故有明显的社会效益和经济效益。
关键词:立井井筒;防治水; 研究与实施
Abstract: the mine shaft is ascending throat, it bear the mine and personnel, improve ascension gangue, lowering materials task. Wellbore is most water gushing all mine, the existing problems of the borehole water gushing not reasonable management, will give the mine production bring tremendous influence. First mountain a ore mine shaft 7.0 meters in diameter and 700.5 meters deep borehole. Mine shaft in-223 m-322-m position through pingdingshan sandstone rich aquifer, and fracture more development, wellbore bigger yield, water gushing basic stable wellbore in 25 m3 / h or so. The mine production to bring a lot of inconvenience.
Based on the analysis of mine water gushing, made a management plan. At the same time, form the shaft cut guide the construction methods preventing water novel. Due to the prevention and control of water in the obvious effects, advanced technology, it is obvious social benefits and economic benefits.
Keywords: vertical shaft; Preventing water; Research and implementation
中图分类号:TU74文献标识码:A 文章编号:
1、工程概况
平煤集团平宝公司首山一矿副井防水设施安装工程,是首山一矿确保安全生产的重要工程,由于副井井筒在-223米~-322米位置穿过平顶山砂岩等富含水层,且裂隙比较发育,井筒涌水量比较大,井筒涌水基本保持稳定在25m3/h左右。这给矿井生产带来很大的不。经过对副井涌水情况的分析,制定出了治理方案。从副井井筒-223米~-700.5米敷设一趟Φ118x9mm的无缝钢管做为疏水主管,在副井井筒-258米、-298米、-313米、-322米处位置安装四套截水槽,所有截水槽的水流出口均以软连接的方式与疏水主管连通。同时对-223米~-298米和-298米~-322米位置的个别出水点采用安装接水管和局部安装截水槽的形式进行处理,以保证副井涌水治理的质量。
2、工程特点
(1)、安装技术难度大,施工工序复杂。
(2)、工期要求特别紧。
(3)、立体、交叉作业,施工配合要求高。
(4)、安装精度要求高,确保罐笼与井避的最小间隙控制在150mm.
3、安装工艺
○1、敷设方法:
首山一矿副井井筒内敷设的管、线较多,管路4趟:其中Φ377mm主排水管道2趟、Φ273mm压风管道1趟,Φ159mm供水管道1趟;10kv高压电缆四趟,通讯、泄露电缆6趟。
综合考虑管路固定和便于入井、敷设几个方面,将管路敷设在供水管道的一侧,即副井井筒东北角。利用现有的供水管道的梁用管道卡子每隔6米对疏水管道进行固定。为承接和分散疏水管道的重量。
○2、管道敷设工艺:
1)管座梁安装:首先将弯管座和支管座裝到罐笼内,下放到井底。在井底东北侧井壁上按照设计尺寸号线,窝子中心线距井筒东西中心线2.36米,然后照线扣窝子,窝子深度800mm。窝子扣好后,将支管座梁按照图纸设计安装,并操平找正,支好盒子板进行灌灰。
2)管道安装:
根据安装情况及甲方要求,管道加工采用自由长度,井筒两管子连接采用套袖连接方式,其余管身不允许有焊接出现。井筒内电缆、管道众多,综合考虑,管道下料时采用矿方下道轨的方式下放。
首先将管道运送至井口出车侧,利用井口西南侧矿方的JD—11.4调度绞车在上井口把管道装进东罐笼(穿罐帽),施工人员站在罐笼顶上,系好安全带,以2米/秒的速度下放至吊装位置。施工人员利用井筒东侧的梯子间,将需要安装的第一根管道用完好的钢丝绳扣锁在井筒内管道上,确保安全后利用无线对讲机联络罐笼下落将管道抽出,再利用双导链及绳扣将管道导至梯子间大梁内测安装位置,进行找正和固定,施工人员站在事先安装好的折页板上利用管道卡子把管道与管道梁固定好。按照此工序依次进行,管道安装完毕后,再对管道接头位置套袖统一焊接。
○3、截水槽安装:
根据副井出水点的分布情况,在副井井筒-258米、-298米、-313米、-322米位置安装四套截水槽,所有截水槽的水流出口均以软连接的方式与疏水主管连通。
截水槽安装采用分段组装的方法,截水槽与井壁固定用M20*350mm的树脂锚杆固定。施工人员利用罐笼顶部的折页板及梯子间作为施工平台,在安装截水槽位置的井壁上每隔500mm钻一个400深的孔,然后安装树脂锚杆。将加工好的截水槽按照设计位置安装,利用树脂锚杆与井壁固定并贴紧,然后利用焊接方式将截水槽与井筒内罐道托架及梯子间梁托架固定。为保证截水槽与井壁的紧密结合,截水槽与井壁间隙用树脂锚固剂进行加固。最后进行导水管的打眼安装工作。
打眼所用风源利用已敷设安装好的疏水管做为风管,从副底液压站处取。
4、标高水平度和安全距离的控制
在正常提升的井筒内施工确定标高,依据已安装好的梯间大梁,从井底往上返标高,也可根据提升机房井筒深度指示器进行校合。水平度的控制利用井筒进入水槽水的流向进行控制,确保同一水槽的水分两边流向疏水管道即可。
安全距离的控制是确保安全提升的关键。目前大部分井筒在注浆过程中都存在凹凸不平的现象,给安装带来诸多不便,根据这一情况,我们采用现场测量放线,在罐角处加工特殊水槽的做法,确保提升容器与井壁距离在150mm以上。
5、方法总结及应用前景
目前,大部分已投入使用的井筒都存在比较严重的涌水现象,直接影响着矿井的安全生产,而建井单位一贯采用重复灌浆的方式进行涌堵。根据水的特性,只能采用疏导的方式进行治理,将井筒内大量的水收集起来利用专用疏水管直接进入井下水仓,解决了冬季天轮结冰和井底泵窝水量大的难题,确保井筒提升的安全性。同时采用已安装好的疏水管道做为临时风管用,解决了井筒深难以取风的难题。
附图
注:文章内所有公式及图表请用PDF形式查看。
经过对副井涌水情况的分析,制定出了治理方案。同时,形成了井筒截导防治水新颖的施工工法。由于在防治水方面效果明显,技术先进,故有明显的社会效益和经济效益。
关键词:立井井筒;防治水; 研究与实施
Abstract: the mine shaft is ascending throat, it bear the mine and personnel, improve ascension gangue, lowering materials task. Wellbore is most water gushing all mine, the existing problems of the borehole water gushing not reasonable management, will give the mine production bring tremendous influence. First mountain a ore mine shaft 7.0 meters in diameter and 700.5 meters deep borehole. Mine shaft in-223 m-322-m position through pingdingshan sandstone rich aquifer, and fracture more development, wellbore bigger yield, water gushing basic stable wellbore in 25 m3 / h or so. The mine production to bring a lot of inconvenience.
Based on the analysis of mine water gushing, made a management plan. At the same time, form the shaft cut guide the construction methods preventing water novel. Due to the prevention and control of water in the obvious effects, advanced technology, it is obvious social benefits and economic benefits.
Keywords: vertical shaft; Preventing water; Research and implementation
中图分类号:TU74文献标识码:A 文章编号:
1、工程概况
平煤集团平宝公司首山一矿副井防水设施安装工程,是首山一矿确保安全生产的重要工程,由于副井井筒在-223米~-322米位置穿过平顶山砂岩等富含水层,且裂隙比较发育,井筒涌水量比较大,井筒涌水基本保持稳定在25m3/h左右。这给矿井生产带来很大的不。经过对副井涌水情况的分析,制定出了治理方案。从副井井筒-223米~-700.5米敷设一趟Φ118x9mm的无缝钢管做为疏水主管,在副井井筒-258米、-298米、-313米、-322米处位置安装四套截水槽,所有截水槽的水流出口均以软连接的方式与疏水主管连通。同时对-223米~-298米和-298米~-322米位置的个别出水点采用安装接水管和局部安装截水槽的形式进行处理,以保证副井涌水治理的质量。
2、工程特点
(1)、安装技术难度大,施工工序复杂。
(2)、工期要求特别紧。
(3)、立体、交叉作业,施工配合要求高。
(4)、安装精度要求高,确保罐笼与井避的最小间隙控制在150mm.
3、安装工艺
○1、敷设方法:
首山一矿副井井筒内敷设的管、线较多,管路4趟:其中Φ377mm主排水管道2趟、Φ273mm压风管道1趟,Φ159mm供水管道1趟;10kv高压电缆四趟,通讯、泄露电缆6趟。
综合考虑管路固定和便于入井、敷设几个方面,将管路敷设在供水管道的一侧,即副井井筒东北角。利用现有的供水管道的梁用管道卡子每隔6米对疏水管道进行固定。为承接和分散疏水管道的重量。
○2、管道敷设工艺:
1)管座梁安装:首先将弯管座和支管座裝到罐笼内,下放到井底。在井底东北侧井壁上按照设计尺寸号线,窝子中心线距井筒东西中心线2.36米,然后照线扣窝子,窝子深度800mm。窝子扣好后,将支管座梁按照图纸设计安装,并操平找正,支好盒子板进行灌灰。
2)管道安装:
根据安装情况及甲方要求,管道加工采用自由长度,井筒两管子连接采用套袖连接方式,其余管身不允许有焊接出现。井筒内电缆、管道众多,综合考虑,管道下料时采用矿方下道轨的方式下放。
首先将管道运送至井口出车侧,利用井口西南侧矿方的JD—11.4调度绞车在上井口把管道装进东罐笼(穿罐帽),施工人员站在罐笼顶上,系好安全带,以2米/秒的速度下放至吊装位置。施工人员利用井筒东侧的梯子间,将需要安装的第一根管道用完好的钢丝绳扣锁在井筒内管道上,确保安全后利用无线对讲机联络罐笼下落将管道抽出,再利用双导链及绳扣将管道导至梯子间大梁内测安装位置,进行找正和固定,施工人员站在事先安装好的折页板上利用管道卡子把管道与管道梁固定好。按照此工序依次进行,管道安装完毕后,再对管道接头位置套袖统一焊接。
○3、截水槽安装:
根据副井出水点的分布情况,在副井井筒-258米、-298米、-313米、-322米位置安装四套截水槽,所有截水槽的水流出口均以软连接的方式与疏水主管连通。
截水槽安装采用分段组装的方法,截水槽与井壁固定用M20*350mm的树脂锚杆固定。施工人员利用罐笼顶部的折页板及梯子间作为施工平台,在安装截水槽位置的井壁上每隔500mm钻一个400深的孔,然后安装树脂锚杆。将加工好的截水槽按照设计位置安装,利用树脂锚杆与井壁固定并贴紧,然后利用焊接方式将截水槽与井筒内罐道托架及梯子间梁托架固定。为保证截水槽与井壁的紧密结合,截水槽与井壁间隙用树脂锚固剂进行加固。最后进行导水管的打眼安装工作。
打眼所用风源利用已敷设安装好的疏水管做为风管,从副底液压站处取。
4、标高水平度和安全距离的控制
在正常提升的井筒内施工确定标高,依据已安装好的梯间大梁,从井底往上返标高,也可根据提升机房井筒深度指示器进行校合。水平度的控制利用井筒进入水槽水的流向进行控制,确保同一水槽的水分两边流向疏水管道即可。
安全距离的控制是确保安全提升的关键。目前大部分井筒在注浆过程中都存在凹凸不平的现象,给安装带来诸多不便,根据这一情况,我们采用现场测量放线,在罐角处加工特殊水槽的做法,确保提升容器与井壁距离在150mm以上。
5、方法总结及应用前景
目前,大部分已投入使用的井筒都存在比较严重的涌水现象,直接影响着矿井的安全生产,而建井单位一贯采用重复灌浆的方式进行涌堵。根据水的特性,只能采用疏导的方式进行治理,将井筒内大量的水收集起来利用专用疏水管直接进入井下水仓,解决了冬季天轮结冰和井底泵窝水量大的难题,确保井筒提升的安全性。同时采用已安装好的疏水管道做为临时风管用,解决了井筒深难以取风的难题。