一、概况北京重型电机厂汽轮机重型总装车间为“六五”技改项目之一,厂房位于已建成投产的汽轮机车间与辅机车间之间的空地上。新车间建成后,将已建成的两车间联成一体,成为一个联合车间组,为工厂产品上等级和提高产量创造了有利条件。两个老车间之间为一狭长空地,净宽(外墙面之间距离)38.20m,老车间柱距皆为6m,柱基底为亚粘土层,落深为-1.600m至-3.000m不等。杯型基础底板外边缘距外墙面1.500m左右,故两个老车间基础之间的净空仅35.20m,使新厂房的跨度受到更大限制。工艺要求总装车间需设置一台250t和两台75t
I. Overview The heavy-duty assembly plant of the heavy-duty motor plant of Beijing Heavy Industries is one of the “sixth five-year” technological transformation projects. The plant is located on the open space between the steam turbine workshop and the auxiliary engine workshop that have been completed and put into production. After the completion of the new workshop, the two completed workshops will be integrated into a united workshop group, which will create favorable conditions for the production of grades and increase of production. Between the two old workshops is a narrow open space, the net width (distance between the outer wall) is 38.20m, the old workshop is 6m, the column base is sub-clay layer, and the drop depth is -1.600m to -3.000m. Wait. The outer edge of the cup-shaped base plate is about 1.500m from the outer wall, so the clearance between the two old workshop foundations is only 35.20m, which makes the span of the new plant more limited. Process requirements The assembly shop needs to set up a 250t and two 75t