论文部分内容阅读
【摘要】井点降水法是在实际开挖地下水位埋藏较浅,基础埋设较深,土内含水接近饱和状态,沿基坑四周每隔一定间距布设井点管,井点管底部设置滤水管插入透水层,上部接软管与集水总管进行连接,集水总管为钢管,周身设置与井点管间距相同的吸水管口,然后通过真空吸水泵将集水管内水抽出,从而达到降低基坑四周地下水位的效果,保证了基底的干燥无水。
【关键词】深基础;井点降水;施工工艺;分析
【Abstract】Well point dewatering method is in the actual excavation of underground water buried depth is shallow and deep foundation embedment, Tsuchinai Mizu close to saturation state, along a tube around the pit every certain distance layout of well point, well point pipe at the bottom of the filter pipe set into permeable layer, connected with the upper part of the hose and the water collecting duct are connected, collecting duct for the steel, Zhoushen setting and well point pipe suction nozzle of the same distance, then through a vacuum suction pump will set the internal water pipe out, so as to achieve the effect of lowering the groundwater level around the pit, to ensure that the basal dry.
【Key words】Deep foundation;Well point dewatering;Construction technology;Analysis
1. 概述
某县公路局新办公楼选址处于弥河东岸1000米,根据现场实际开挖发现地下水位埋藏较浅,-0.8m米处见地下水。房建基础埋设较深,自然地面向下4.0m为基础标高,土内含水接近饱和状态,这种施工条件给基础施工带来很大的困难。基础开挖后随时有塌方的危险,基础开挖后如果塌方,可能会造成重大安全事故,后果不堪设想,存在极大的安全隐患。因此根据实际情况采用井点降水。为了满足文明施工的要求,确保安全生产和工程质量,施工单位采取轻型井点降水的措施,井点降水所排出的水必须按要求排放到指定的排水井,并做好排水的过滤工作,这些降水、排水工作都要持续到房建基础工程完毕回填后才能停止,以保证房建基础等在无水条件下施工。
2. 施工准备
根据工程的结构、特点、进度要求及现场实际情况,投入足够的施工人员,机械设备按种类和数量组织进场。合理规划摆放位置,暂时未用的设备应维修完好待命。现场测量人员用白灰、木桩等标识出井点降水下管的中心位置。
3. 施工技术措施
3.1降水形式。基础两侧采用双排井点降水,井点管间距1.0m,降水深度为6m;或采用基础环型井点降水,井点管间距0.8米,降水深度6米。
3.2抽水泵采用YB180M-ZW型水泵,吸口直径为108mm,集水管根据现场实际确定长度。集水管两端用肓板封死后接48管,用软胶管将总管和井点管连接成总管系统,集水总管系统与集水箱吸入口连接。
3.3井点管用48钢管制成,每根6m,一端制成锥型封闭,下部1.5m长为滤管,设间距30mm一个12圆孔,用18#铁线绑扎后,外用70目尼龙网包两层,用22#铁线绑牢,井点管每50根用一套设备。
3.4打井管用57钢管制成长8m,一端制成锥型锯齿形状,用水带与高压水泵连接。
3.5采用冲沉法布管,由于当时施工工期紧,开工时处于春节刚过,冻土未融化,打井管无法插入地下,所以必须先将自然地面向下0.5m深的冻土挖除,由打井管向地下注入高压水,将打井管对准点位垂直插入井点孔,边冲边拔边旋转并保持打井管垂直,调整水压和沉入速度,保证冲孔直径达到要求,冲水压力可逐渐加压,待冲沉至设计底标高下0.5m时,打井管停止冲沉,再冲洗片刻将底部泥浆随水冲出,切断水源后,迅速垂直拨出打井管,随即将井点管对准井孔中心垂直插入,当井点管达到设计高程后,将井点管固定并将井点管管顶临时封堵。在井点管四周均匀分层填灌粗砂,填至地下水位以上0.5m处,改填普通土捣实。
3.6当井点管封堵完成后,将管顶临时封堵打开,向井点管内灌水,当清水灌入后,迅速下沉,证明井点成孔合格。
3.7检试完成后,将井点管和集水干管连接,组装水泵机组,进行井点试运行。
3.8降水周期为以基础安装完毕,土方夯填完成后为井点结束。施工完毕终止抽水后,拨出井点管,所留孔洞应立即用砂填实。
4. 安全技术措施
吸水泵严禁无水空转,系统运行前必须先注满清水; 经常检查井点系统的管路连接是否严密,有无渗水,漏气现象,在施工排水过程中不得间断排水(一旦排水间断半小时,前面降水一周的辛苦就白费了,所以必须备好发电机组),并对排水系统经常维护; 对集水管内泥砂应及时、彻底的清理; 系统运行时要设专人看护,并设立领导带班制度,24小时不定期巡视; 系统水泵、水箱固定牢固,不得移位; 现场用的电闸箱应一机一闸一保护,用规定的保险丝接保险,严禁用铝线、铜线代替,一旦发现严肃处理。 临时用电必须符合规范要求。采用三相五线制,电源线架空敷设。所有用电设备均实行一机一箱一闸一保护。对电器在设备,重复接地和漏电保护器应定时检测。发现问题及时处理,严禁带病运行。
5. 结语
该工程采用井点降水法施工工艺,比大开挖基坑抽水施工工艺缩短工期60天,节省工程款200余万元,更为关键的是保证了房建基础施工工作人员安全,把“安全生产、预防为主”、“不安全不生产”等口号落到实处。
【关键词】深基础;井点降水;施工工艺;分析
【Abstract】Well point dewatering method is in the actual excavation of underground water buried depth is shallow and deep foundation embedment, Tsuchinai Mizu close to saturation state, along a tube around the pit every certain distance layout of well point, well point pipe at the bottom of the filter pipe set into permeable layer, connected with the upper part of the hose and the water collecting duct are connected, collecting duct for the steel, Zhoushen setting and well point pipe suction nozzle of the same distance, then through a vacuum suction pump will set the internal water pipe out, so as to achieve the effect of lowering the groundwater level around the pit, to ensure that the basal dry.
【Key words】Deep foundation;Well point dewatering;Construction technology;Analysis
1. 概述
某县公路局新办公楼选址处于弥河东岸1000米,根据现场实际开挖发现地下水位埋藏较浅,-0.8m米处见地下水。房建基础埋设较深,自然地面向下4.0m为基础标高,土内含水接近饱和状态,这种施工条件给基础施工带来很大的困难。基础开挖后随时有塌方的危险,基础开挖后如果塌方,可能会造成重大安全事故,后果不堪设想,存在极大的安全隐患。因此根据实际情况采用井点降水。为了满足文明施工的要求,确保安全生产和工程质量,施工单位采取轻型井点降水的措施,井点降水所排出的水必须按要求排放到指定的排水井,并做好排水的过滤工作,这些降水、排水工作都要持续到房建基础工程完毕回填后才能停止,以保证房建基础等在无水条件下施工。
2. 施工准备
根据工程的结构、特点、进度要求及现场实际情况,投入足够的施工人员,机械设备按种类和数量组织进场。合理规划摆放位置,暂时未用的设备应维修完好待命。现场测量人员用白灰、木桩等标识出井点降水下管的中心位置。
3. 施工技术措施
3.1降水形式。基础两侧采用双排井点降水,井点管间距1.0m,降水深度为6m;或采用基础环型井点降水,井点管间距0.8米,降水深度6米。
3.2抽水泵采用YB180M-ZW型水泵,吸口直径为108mm,集水管根据现场实际确定长度。集水管两端用肓板封死后接48管,用软胶管将总管和井点管连接成总管系统,集水总管系统与集水箱吸入口连接。
3.3井点管用48钢管制成,每根6m,一端制成锥型封闭,下部1.5m长为滤管,设间距30mm一个12圆孔,用18#铁线绑扎后,外用70目尼龙网包两层,用22#铁线绑牢,井点管每50根用一套设备。
3.4打井管用57钢管制成长8m,一端制成锥型锯齿形状,用水带与高压水泵连接。
3.5采用冲沉法布管,由于当时施工工期紧,开工时处于春节刚过,冻土未融化,打井管无法插入地下,所以必须先将自然地面向下0.5m深的冻土挖除,由打井管向地下注入高压水,将打井管对准点位垂直插入井点孔,边冲边拔边旋转并保持打井管垂直,调整水压和沉入速度,保证冲孔直径达到要求,冲水压力可逐渐加压,待冲沉至设计底标高下0.5m时,打井管停止冲沉,再冲洗片刻将底部泥浆随水冲出,切断水源后,迅速垂直拨出打井管,随即将井点管对准井孔中心垂直插入,当井点管达到设计高程后,将井点管固定并将井点管管顶临时封堵。在井点管四周均匀分层填灌粗砂,填至地下水位以上0.5m处,改填普通土捣实。
3.6当井点管封堵完成后,将管顶临时封堵打开,向井点管内灌水,当清水灌入后,迅速下沉,证明井点成孔合格。
3.7检试完成后,将井点管和集水干管连接,组装水泵机组,进行井点试运行。
3.8降水周期为以基础安装完毕,土方夯填完成后为井点结束。施工完毕终止抽水后,拨出井点管,所留孔洞应立即用砂填实。
4. 安全技术措施
吸水泵严禁无水空转,系统运行前必须先注满清水; 经常检查井点系统的管路连接是否严密,有无渗水,漏气现象,在施工排水过程中不得间断排水(一旦排水间断半小时,前面降水一周的辛苦就白费了,所以必须备好发电机组),并对排水系统经常维护; 对集水管内泥砂应及时、彻底的清理; 系统运行时要设专人看护,并设立领导带班制度,24小时不定期巡视; 系统水泵、水箱固定牢固,不得移位; 现场用的电闸箱应一机一闸一保护,用规定的保险丝接保险,严禁用铝线、铜线代替,一旦发现严肃处理。 临时用电必须符合规范要求。采用三相五线制,电源线架空敷设。所有用电设备均实行一机一箱一闸一保护。对电器在设备,重复接地和漏电保护器应定时检测。发现问题及时处理,严禁带病运行。
5. 结语
该工程采用井点降水法施工工艺,比大开挖基坑抽水施工工艺缩短工期60天,节省工程款200余万元,更为关键的是保证了房建基础施工工作人员安全,把“安全生产、预防为主”、“不安全不生产”等口号落到实处。