论文部分内容阅读
深圳北站大桥拱肋吊装正值台风季节 ,为保证施工安全及铁路正常作业 ,施工时采取了一系列抗风措施 ,经历 3次台风检验 ,大桥均安全无恙。本文就该桥施工的抗风设计和经历 990 8号台风采取的措施情况作一介绍
In order to ensure construction safety and normal railway operation, a series of anti-wind measures were taken during the construction of the arch rib of Shenzhen North Station Bridge. During the typhoon inspection, the bridges were safe and sound. This paper introduces the wind-resistant design of the bridge construction and the measures taken by typhoon No. 990-8