阿联酋阿布扎比谢赫.扎耶德桥是前往阿布扎比岛的主要通道,主桥长840m,主拱跨径234m,2幅主梁采用预应力混凝土箱形结构,用大截面横梁连接,由粗大吊杆支承;3组不对称拱(寓指流动的沙丘)和墩身组成长600m的整体连续结构。4个水中主墩承台采用双壁钢板桩围堰法施工;墩身采用传统的支架法和翻模法施工;主梁采用重型临时支架系统分2个阶段现浇;钢构件运输到施工现场后,通过旋转架从侧卧位置旋转为立式位置,采用1台新式大型提升站(顶部带有旋转转盘)提升。该桥施工用的临时钢结构总计超过20 000t,临时工程中混凝土的用量达80kg/m3,工程造价约3亿美元,于2010年11月22日通车。
Sheikh Zayed Bridge, Abu Dhabi, United Arab Emirates Sheik Zayed Bridge is the main access to Abu Dhabi Island, the main bridge length 840m, the main arch span 234m, two girders using prestressed concrete box-shaped structure, with a large cross-beam connection, Supported by a thick boom; 3 sets of asymmetrical arches (dune with flowing fingers) and pier body make up an overall continuous structure with a length of 600m. The four water main pier caps are constructed by double-wall steel sheet pile cofferdam. The pier body is constructed by the traditional support method and the turn-over method. The main beam is cast in two stages by a heavy duty temporary support system. The steel members are transported to the construction site After the rotary frame from the lateral position to the vertical position, using a large new large elevators (top with a rotating turntable) to enhance. The temporary steel structure for the bridge construction totaled more than 20,000 tons, the amount of concrete used in the temporary works reached 80 kg / m3, and the construction cost was about 300 million U.S. dollars. It opened to traffic on November 22, 2010.