论文部分内容阅读
田径场位于奥林匹克体育中心,占地五万多平方米,建筑面积30653平方米,东西看台和绕场一周的环形高架平台可容纳两万名观众。由北京市建筑设计院设计,北京第三城市建设工程公司施工,该工程于1989年12月16日竣工。环形高架平台上层是观众出入场疏散通道,下层是各种车辆的通道。看台和高架平台均必须做防水处理,保证不渗漏。原设计准备做胶乳沥清防水,但在数量达25000多平方米的看台、高架平台上做涂
The track and field stadium is located in the Olympic Sports Center, covering an area of more than 50,000 square meters, with a building area of 30,653 square meters. The ring-shaped elevated platform of the East-West stand and a week-long round can accommodate 20,000 spectators. Designed by Beijing Architectural Design Institute, Beijing Third City Construction Engineering Co., Ltd. was completed on December 16, 1989. The upper part of the ring elevated platform is the evacuation channel for the audience to enter and exit, and the lower level is the passage for various vehicles. Stands and elevated platforms must be waterproofed to ensure no leakage. The original design is ready for latex waterproofing, but it is painted on stands and elevated platforms with a total number of more than 25,000 square meters.