【美国《核子周刊》 1998年 11月 12日刊报道】 瑞典的奥斯卡港 1号机组在停堆维修和更换了一个堆芯围筒后于 1998年 11月 9日重新启动 ,比计划推迟了 4个月。这台 44 0 MW的 BWR已停役 6个多月。堆芯围筒的更换和其它维修工作都远比预期的要慢。由通用电气公司进行的堆芯围筒
[The US “Nuclear Weekly Journal” reported on November 12, 1998] The 1th unit of the Oscar Port in Sweden was restarted on November 9th, 1998 after the maintenance of the reactor was stopped and a core barrel was replaced. It was delayed by 4 more than planned. month. The 44 0 MW BWR has been suspended for more than six months. Replacement of core barrels and other maintenance work is much slower than expected. Core shroud made by General Electric Company