广东岭澳核电站,是国家在“九五”期间安排的4个核电建设项目之一。自一号核岛于1997年5月浇灌第一罐混凝土以来,工程建设进展顺利,前期工程全面完成,四通一平工程均按期达标。 1997年5月15日,岭澳核电站主体工程正式开工,李鹏总理发来贺信,吴邦国副总理亲自出席开工仪式并发表讲话。9月15日,一号常规岛按期浇灌第一罐混凝土;11月28日,二号核岛较原计划提前47天浇灌了第一罐混凝土;1998年4月,土石方工程全部完工。截止今年7月底,1号机组反应堆厂房第七圈钢衬里已安装就位,标高达到25.9米;安注罐等9个罐吊装就位,硼注罐于6
Guangdong Lingao Nuclear Power Station is one of the four nuclear power construction projects arranged by the state during the “Ninth Five-Year Plan” period. Since the construction of the first tank concrete from No. 1 nuclear island in May 1997, the project construction has progressed smoothly. The pre-projects have been fully completed, and the four-pass and one-level project have met the standards on schedule. On May 15, 1997, the main project of Ling Ao Nuclear Power Plant officially started. Premier Li Peng sent a letter of congratulation and Vice Premier Wu Bangguo attended the opening ceremony and delivered a speech. On September 15th, No. 1 conventional island was poured with concrete from the first tank on schedule; on the 28th of November, No. 2 nuclear island was poured into the first concrete tank 47 days earlier than originally planned; in April 1998, the earth and rock works were all completed. By the end of July this year, the steel lining of the No. 1 unit reactor plant was installed in place on the seventh lap, and the elevation reached 25.9 meters; 9 tanks such as An injection cans were hoisted in place, and the boron injection tanks were at 6