11月5日,宁波铁路枢纽新建北环线甬江左线特大桥钢混结合段最后一块风嘴单元的吊装胜利完工,这标志着全国首座铁路斜拉桥钢混结合段施工中研发的模块分体式制造技术取得圆满成功。该桥设计采用了新型钢混结合段构造连接技术,结合段采用阶梯状填充混凝土前后承压板式钢-混凝土接头,通过将结合段钢箱梁的顶板、底板、腹板与隔板和端承压板之间围封组成钢格室,并在其内填充混凝土,与混凝土箱梁顶
On November 5, the completion of the hoisting of the last tuyere unit of the steel-concrete combined section of the Yongjiang Left Line Super-Large Bridge on the Newly-built North Ring Road in Ningbo Railway Hub completed the hoisting of the modular unit of the first steel cable-stayed bridge construction in China Manufacturing technology has been a success. The bridge design uses a new type of steel-concrete combination of structural connection, combined with the use of stepped-filled concrete before and after the pressure plate steel-concrete joints, through the combination of steel box girder roof, floor, web and partitions and end bearing Compression between the platen composed of steel grid room, and in which the filling of concrete, and concrete box girder