一、概况常熟发电厂4×300MW机组一期工程于1990年9月开工。计划1992年第一台机组发电,1994年全部建成。原常熟发电厂初步设计中,没有设立施工码头,只设立重件码头。设立重件码头的原因是常熟发电厂无铁路专用线,靠公路运输设备重件,沿途的桥梁、涵洞无法承受,只有靠长江水路运输解决。初步设计中,没有考虑到在建设电厂期间,大量的黄砂、石料、水泥等建材及设备从长江水路运来,故没有设立一个以运输砂石料为主,并运输其它建材的砂石码头。1989年初,在江苏省电力工业局组织下,对西
I. Overview Changshu Power Plant 4 × 300MW unit a project started in September 1990. The first unit in 1992 planned to generate electricity, completed in 1994. In the original design of Changshu Power Plant, there was no construction wharf and only heavy wharf. The reason for the establishment of the heavy wharf is that Changshu Power Plant has no special railway lines and can not afford the heavy bridges and culverts along the road due to the heavy parts of road transport equipment. It can only be settled by the Yangtze River waterway transportation. In the preliminary design, no consideration was given to the fact that a large amount of construction materials and equipment such as yellow sand, stone, cement and the like were transported from the Yangtze River during the construction of the power plant. Therefore, a sand and gravel wharf was mainly set up to transport gravel and transport other building materials. In early 1989, under the organization of Jiangsu Provincial Electric Power Industry Bureau, to the west