根据现行的《水利水电工程设计工程量计算规定》(以下简称《规定》)工程量是根据建筑物或工程的设计几何轮廓尺寸进行计算的。施工中超挖、超填部分已计入概算定额,不再包括在设计所提出的工程量中。《规定》把超挖、超填的客观事实写清楚了,也把超填、挖问题通过概算定额解决了,但笔者认为在实际运用中,这样的处理方法尚有不足之处,有待于在
According to the current “Provisions for Calculation of Engineering Quantity of Water Conservancy and Hydropower Projects” (hereinafter referred to as “Provisions”), the quantities of works are calculated based on the geometric dimensions of buildings or works. Over-excavation and over-filling in construction have been included in the estimated quota and are no longer included in the volume of works proposed in the design. The Provisions stipulate the objective facts of over-excavation and over-filling, and also solve the problem of over-filling and digging through budget estimates. However, in the actual application, the author thinks there are still some deficiencies in this method of treatment.