摘要:目前,国内许多高层住宅、公共建筑及超长结构的现浇整体钢筋混凝土结构中都采用后浇带的施工,后浇带是指现浇整体式钢筋混凝土结构施工期间,为了克服因温度、收缩、沉降而可能产生有害裂缝而设置的变形缝,起到消化沉降收缩变形的作用。长期以来,后浇带的设计与施工也不断发展,但是还存在不足之处。
关键词:混凝土;后浇带;设计;施工技术
Abstract: At present, the construction of the late poured band whole cast-in-situ reinforced concrete structure at home many high-rise residential, public buildings and super long structure, post-pouring belt refers to a whole cast-in-situ reinforced concrete structure during construction, in order to overcome and may be due to temperature, shrinkage, settlement and setting deformation joint of harmful cracks, to digest the settlement shrinkage deformation. Long-term since, after the design and construction of the pouring belt is also developing, but there are still shortcomings.
Keywords: concrete;post-pouring belt;design;construction technology
中图分类号: TV331 文献标识码:A 文章编号:2095-2104(2012)
一、混凝土结构后浇带按其作用可分为3种
1、为解决高层建筑主楼与裙房的沉降差而设置的后浇施工带称为沉降后浇带。
2、为防止混凝土凝结收缩开裂而设置的后浇施工带称为收缩后浇带。
3、为防止混凝土因温度变化拉裂而设置的后浇施工带称为温度后浇带。
二、根据情况确定后浇带的类型
设计采用何种类型的后浇带必须根据工程类型、工程部位、现场施工情况和结构受力情况而具体确定。
1、后浇带的缝宽与墙、板厚度有关。对底板厚度超过100厘米以上的,可根据后浇带处的接槎形式、钢筋搭接、施工难易程度等灵活掌握,当施工较困难时,后浇带缝宽可适当增加。
2、后浇带接缝處的断面形式,当墙、板厚度小于30厘米时,可做成平直缝;当厚度大于30厘米小于60厘米时,可做成阶梯形或上下对称坡口形;当墙板厚度大于60厘米时可做成企口缝。
3、后浇带的钢筋断开或贯通,在于后浇带缝的类型。对沉降后浇带而言,钢筋贯通为好;对收缩后浇带而言,钢筋断开为好;梁反结构的板筋断开,梁筋贯通,如果钢筋不断开,钢筋附近的混凝土收缩将受到约束,产生拉力导致开裂,从而降低结构抵抗温度变化的能力。
4、对于后浇带内的后浇混凝土,应使用无收缩混凝土,防止新老混凝土接缝收缩开裂。无收缩混凝土可在混凝土掺加微膨胀剂,也可直接采用膨胀水泥配制,如矿渣水泥。配制的混凝土强度等级应比先浇混凝土高一个强度等级。
5、后浇带后浇部分混凝土的浇灌时间,不同类型后浇带的浇灌时间是不同的。伸缩后浇带应根据先浇混凝土的收缩完成情况而定,不同水泥、水灰比、养护条件的混凝土,一般应控制在施工后60天进行。如工期非常紧迫,也应在2周以上。沉降后浇带宜在建筑物基本完成沉降后,再浇注后浇带。
三、混凝土结构中后浇带设计及施工中常见的问题
混凝土结构中后浇带的设计问题
高层楼主与低层裙房的连接是否设后浇带,要根据上部结构及建筑场地地基持力层情
况而定。设后浇带有其适用条件,并非凡高层主楼与低层裙房连接处均可设后浇带。有的工程应设永久性沉降缝的却设后浇带,等于未设永久性沉降缝,有的工程可能完全不设后浇带却设了,使设计复杂,施工困难。
后浇带的位置选择问题。普遍认为应选在结构内力较小处。
基础、墙、梁、板后浇带的断面形式交代不明。从规范的角度来看,设计图纸应有明
确交代,并绘制详图。
后浇带的钢筋断开与否难确定。为防止在同一截而钢筋焊接接头过多选择离开,但是
不宜直接通过一个开间。有的工程设计为后浇带,但施工单位却先建主楼,待高层主体完成后,再施工裙房,不留后浇缝,而是预留出钢筋,低层施工时再焊接,这虽是后浇缝的一种变通形式,但施工时未按设计要求做,易带来一些问题。
后浇带的后浇混凝土,有普通混凝土提高一级强度等级、采用同等级或提高一级的无
收缩混凝土等规定。
混凝土结构中后浇带施工常见得问题
后浇带的两侧宜采用钢筋支架铝丝网或单层钢板网隔断,并按规定做成企口式,但有
的工程采用木模隔断做法,由于钢筋不断,木模缝隙较大,浇筑混凝土不易保证质量。对楼板的后浇带两侧,有的不支模,留成自然槎,更不易保证质量。
钢筋的保护措施不到位。后浇带一般预留800mm宽,钢筋应保证准确位置而连续不断,
施工中由于对钢筋的保护措施不利,有些板的钢筋被踩弯或压弯,虽然相对数量不多,但若不采取补救措施就浇筑混凝土,则会对板结构受力不利。
后浇带未按照设计图纸要求施工。设计要求留企口缝,实际留直槎,板的后浇带处不
支模板,留成斜坡槎,虽然在浇筑混凝土前经清刷、凿毛,但不认真,疏松混凝土未彻底凿除,使混凝土补齐后连接较差。
其他原因。后浇带的封闭时间的控不当,后浇带的施工顺序,对后浇带的养护不重视
等等。
四、后浇带施工中应注意问题
后浇带的施工应严格按照施工规范和设计要求进行,处理不当极易造成质量事故,轻则开裂渗漏,重则危及结构安全,所以在施工中应给予高度重视。
1、后浇带接缝形式必须严格按施工图施工,施工时应用堵头板,根据接口形式在堵头板上装凸条。有些施工单位不按图施工,接口处不支模,留成自然斜坡槎,使施工缝处混凝土浇捣困难,造成混凝土不密实,达不到设计强度等级。如果是地下室底板还易产生渗水现象。
2、后浇带先浇混凝土完成后应进行防护,局部应覆盖,四周用临时栏杆围护,防止施工过程中钢筋污梁,保证钢筋不被踩踏。有些工地后浇带不设围护,致使钢筋被严重踩弯、钢筋杂乱、建筑垃圾较多,不易清理。
3、在后浇带浇注混凝土前必须将整个截面按照施工缝的要求进行处理,清除杂物,水泥薄膜、表面松动的砂石和软弱混凝土层,并将两侧混凝土凿毛,用水冲洗干净,充分保持两侧混凝土湿润,一般不少于24小时。在表面涂刷水泥净浆或混凝土界面处理剂后,及时浇筑混凝土。有些施工单位两侧混凝土不凿毛就浇注后浇带内混凝土,使新老混凝土的粘结强度难以保证,处理不好会在后浇带两侧造成两条贯空裂缝,极易渗水。
4、后浇带后浇混凝土一定要用无收缩混凝土,掺用微膨胀剂,精心振捣密实,注意浇水养护。有些单位施工不按设计要求使用无收缩混凝土,用普通混凝土应付;还有一些施工单位由于后浇混凝土用量较少,在后浇带旁人工拌制混凝土,随拌随浇,严重影响了工程质量。
5、后浇带跨内的梁反在后浇带混凝土浇注前,两侧结构长期处于悬臂受力状态,在施工期间,本跨内的模板和支撑不能拆除,必须待后浇混凝土强度达到设计强度值的75%以上后,方可按由上向下顺序拆除。有些施工单位,施工期间模板准备不足,或考虑资金等因素,提前拆除后浇带跨内的模板和支撑,造成板边开裂,使结构承载能力下降。
此外,后浇带的混凝土因一次浇筑量小,因而通常采用现场搅拌混凝土的方法,且后浇带应用强度等级提高一级、早强、补偿收缩的混凝土浇筑,所以应单独申请混凝土配合比。施工中应提前做好水泥、砂、石和外加剂及掺合料的进场检验和试验工作,及时申请混凝土配合比。浇筑时认真计量,在混凝土浇筑时按规定留置标准养护试件和同条件养试件,用以检验和证明后浇带混凝土的强度。混凝土浇筑后应重视其养护工作,及时的养护可使混凝土在潮湿的环境中硬化,水泥水化生成物堵塞毛细孔隙,提高混凝土的密实度和抗渗性。
后浇带可以有效地减少收缩应力,在施工后期,把后浇带砼浇上,使工程变成整体,以利用“后浇带”办法控制裂缝并达到不设置永久伸缩缝的目的。通过设计单位、施工单位认真设计、精心施工,一定能在工程实践中收到较好的效果。
结束语
总之,混凝土结构后浇带的设计和施工直接影响到结构的安全性与经济性,设计单位也应要根据不同的工程结构性质、特点、作用认真设计。在施工过程中,要严格控制后浇带混凝土的施工质量,控制裂缝并达到不设置永久伸缩缝的目的,保证每个工程的整体性、完美性和使用性,才能达到提高工程质量的真正目的。
参考文献
[1]姚延龄. 混凝土质量问题的预防控制[N]. 建筑时报,2010 .
[2]王福元. 浅谈混凝土结构中后浇带的施工[J] .山西建筑,2011,33(18)
关键词:混凝土;后浇带;设计;施工技术
Abstract: At present, the construction of the late poured band whole cast-in-situ reinforced concrete structure at home many high-rise residential, public buildings and super long structure, post-pouring belt refers to a whole cast-in-situ reinforced concrete structure during construction, in order to overcome and may be due to temperature, shrinkage, settlement and setting deformation joint of harmful cracks, to digest the settlement shrinkage deformation. Long-term since, after the design and construction of the pouring belt is also developing, but there are still shortcomings.
Keywords: concrete;post-pouring belt;design;construction technology
中图分类号: TV331 文献标识码:A 文章编号:2095-2104(2012)
一、混凝土结构后浇带按其作用可分为3种
1、为解决高层建筑主楼与裙房的沉降差而设置的后浇施工带称为沉降后浇带。
2、为防止混凝土凝结收缩开裂而设置的后浇施工带称为收缩后浇带。
3、为防止混凝土因温度变化拉裂而设置的后浇施工带称为温度后浇带。
二、根据情况确定后浇带的类型
设计采用何种类型的后浇带必须根据工程类型、工程部位、现场施工情况和结构受力情况而具体确定。
1、后浇带的缝宽与墙、板厚度有关。对底板厚度超过100厘米以上的,可根据后浇带处的接槎形式、钢筋搭接、施工难易程度等灵活掌握,当施工较困难时,后浇带缝宽可适当增加。
2、后浇带接缝處的断面形式,当墙、板厚度小于30厘米时,可做成平直缝;当厚度大于30厘米小于60厘米时,可做成阶梯形或上下对称坡口形;当墙板厚度大于60厘米时可做成企口缝。
3、后浇带的钢筋断开或贯通,在于后浇带缝的类型。对沉降后浇带而言,钢筋贯通为好;对收缩后浇带而言,钢筋断开为好;梁反结构的板筋断开,梁筋贯通,如果钢筋不断开,钢筋附近的混凝土收缩将受到约束,产生拉力导致开裂,从而降低结构抵抗温度变化的能力。
4、对于后浇带内的后浇混凝土,应使用无收缩混凝土,防止新老混凝土接缝收缩开裂。无收缩混凝土可在混凝土掺加微膨胀剂,也可直接采用膨胀水泥配制,如矿渣水泥。配制的混凝土强度等级应比先浇混凝土高一个强度等级。
5、后浇带后浇部分混凝土的浇灌时间,不同类型后浇带的浇灌时间是不同的。伸缩后浇带应根据先浇混凝土的收缩完成情况而定,不同水泥、水灰比、养护条件的混凝土,一般应控制在施工后60天进行。如工期非常紧迫,也应在2周以上。沉降后浇带宜在建筑物基本完成沉降后,再浇注后浇带。
三、混凝土结构中后浇带设计及施工中常见的问题
混凝土结构中后浇带的设计问题
高层楼主与低层裙房的连接是否设后浇带,要根据上部结构及建筑场地地基持力层情
况而定。设后浇带有其适用条件,并非凡高层主楼与低层裙房连接处均可设后浇带。有的工程应设永久性沉降缝的却设后浇带,等于未设永久性沉降缝,有的工程可能完全不设后浇带却设了,使设计复杂,施工困难。
后浇带的位置选择问题。普遍认为应选在结构内力较小处。
基础、墙、梁、板后浇带的断面形式交代不明。从规范的角度来看,设计图纸应有明
确交代,并绘制详图。
后浇带的钢筋断开与否难确定。为防止在同一截而钢筋焊接接头过多选择离开,但是
不宜直接通过一个开间。有的工程设计为后浇带,但施工单位却先建主楼,待高层主体完成后,再施工裙房,不留后浇缝,而是预留出钢筋,低层施工时再焊接,这虽是后浇缝的一种变通形式,但施工时未按设计要求做,易带来一些问题。
后浇带的后浇混凝土,有普通混凝土提高一级强度等级、采用同等级或提高一级的无
收缩混凝土等规定。
混凝土结构中后浇带施工常见得问题
后浇带的两侧宜采用钢筋支架铝丝网或单层钢板网隔断,并按规定做成企口式,但有
的工程采用木模隔断做法,由于钢筋不断,木模缝隙较大,浇筑混凝土不易保证质量。对楼板的后浇带两侧,有的不支模,留成自然槎,更不易保证质量。
钢筋的保护措施不到位。后浇带一般预留800mm宽,钢筋应保证准确位置而连续不断,
施工中由于对钢筋的保护措施不利,有些板的钢筋被踩弯或压弯,虽然相对数量不多,但若不采取补救措施就浇筑混凝土,则会对板结构受力不利。
后浇带未按照设计图纸要求施工。设计要求留企口缝,实际留直槎,板的后浇带处不
支模板,留成斜坡槎,虽然在浇筑混凝土前经清刷、凿毛,但不认真,疏松混凝土未彻底凿除,使混凝土补齐后连接较差。
其他原因。后浇带的封闭时间的控不当,后浇带的施工顺序,对后浇带的养护不重视
等等。
四、后浇带施工中应注意问题
后浇带的施工应严格按照施工规范和设计要求进行,处理不当极易造成质量事故,轻则开裂渗漏,重则危及结构安全,所以在施工中应给予高度重视。
1、后浇带接缝形式必须严格按施工图施工,施工时应用堵头板,根据接口形式在堵头板上装凸条。有些施工单位不按图施工,接口处不支模,留成自然斜坡槎,使施工缝处混凝土浇捣困难,造成混凝土不密实,达不到设计强度等级。如果是地下室底板还易产生渗水现象。
2、后浇带先浇混凝土完成后应进行防护,局部应覆盖,四周用临时栏杆围护,防止施工过程中钢筋污梁,保证钢筋不被踩踏。有些工地后浇带不设围护,致使钢筋被严重踩弯、钢筋杂乱、建筑垃圾较多,不易清理。
3、在后浇带浇注混凝土前必须将整个截面按照施工缝的要求进行处理,清除杂物,水泥薄膜、表面松动的砂石和软弱混凝土层,并将两侧混凝土凿毛,用水冲洗干净,充分保持两侧混凝土湿润,一般不少于24小时。在表面涂刷水泥净浆或混凝土界面处理剂后,及时浇筑混凝土。有些施工单位两侧混凝土不凿毛就浇注后浇带内混凝土,使新老混凝土的粘结强度难以保证,处理不好会在后浇带两侧造成两条贯空裂缝,极易渗水。
4、后浇带后浇混凝土一定要用无收缩混凝土,掺用微膨胀剂,精心振捣密实,注意浇水养护。有些单位施工不按设计要求使用无收缩混凝土,用普通混凝土应付;还有一些施工单位由于后浇混凝土用量较少,在后浇带旁人工拌制混凝土,随拌随浇,严重影响了工程质量。
5、后浇带跨内的梁反在后浇带混凝土浇注前,两侧结构长期处于悬臂受力状态,在施工期间,本跨内的模板和支撑不能拆除,必须待后浇混凝土强度达到设计强度值的75%以上后,方可按由上向下顺序拆除。有些施工单位,施工期间模板准备不足,或考虑资金等因素,提前拆除后浇带跨内的模板和支撑,造成板边开裂,使结构承载能力下降。
此外,后浇带的混凝土因一次浇筑量小,因而通常采用现场搅拌混凝土的方法,且后浇带应用强度等级提高一级、早强、补偿收缩的混凝土浇筑,所以应单独申请混凝土配合比。施工中应提前做好水泥、砂、石和外加剂及掺合料的进场检验和试验工作,及时申请混凝土配合比。浇筑时认真计量,在混凝土浇筑时按规定留置标准养护试件和同条件养试件,用以检验和证明后浇带混凝土的强度。混凝土浇筑后应重视其养护工作,及时的养护可使混凝土在潮湿的环境中硬化,水泥水化生成物堵塞毛细孔隙,提高混凝土的密实度和抗渗性。
后浇带可以有效地减少收缩应力,在施工后期,把后浇带砼浇上,使工程变成整体,以利用“后浇带”办法控制裂缝并达到不设置永久伸缩缝的目的。通过设计单位、施工单位认真设计、精心施工,一定能在工程实践中收到较好的效果。
结束语
总之,混凝土结构后浇带的设计和施工直接影响到结构的安全性与经济性,设计单位也应要根据不同的工程结构性质、特点、作用认真设计。在施工过程中,要严格控制后浇带混凝土的施工质量,控制裂缝并达到不设置永久伸缩缝的目的,保证每个工程的整体性、完美性和使用性,才能达到提高工程质量的真正目的。