济钢2~#1 750 m~3高炉按照计划进行降料面停炉。通过停炉前保持稳定的炉况顺行基础,停炉过程中控制好风量和配合合理的打水量,严格控制炉顶温度和煤气中氢氧的含量,合理组织炉前出铁等措施,停炉过程安全顺利,共用时10 h55 min,达到了停炉低碳低消耗的目的。
Jigang 2 ~ # 1 750 m ~ 3 blast furnace in accordance with the planned surface down furnace shutdown. By stopping the furnace before the steady state of the furnace to go along the line, the process of stopping the process of controlling the amount of air flow and with a reasonable amount of water, the roof temperature and gas strictly control the content of hydrogen and oxygen, the rational organization of the furnace front iron and other measures, shutdown process Safe and smooth, when shared 10 h55 min, reached the purpose of stopping low-carbon consumption.