俄罗斯特罗伊茨克电厂1×660MW超临界机组工程设计240m烟囱钢内筒设计双筒悬挂式内衬钛合金复合板,直径8.1m全高240m。为了满足工期要求降低施工成本、降低施工安全风险缩短施工工期,创出载人电动吊篮与卷扬机联合进行烟囱钢平台整体组合吊装工法和采用小车分段平移运输组合钢内筒液压提升倒装法的施工工艺,在实践中取得了显著效果。
Design of 1 × 660MW Supercritical Unit in Troyk Power Plant in Russia Design of 240m Chimney Steel Inner Cylinder Design Double Cylinder Suspension Lined Titanium Alloy Composite Plate with Diameter of 8.1m and Height of 240m. In order to meet the requirements of the construction period to reduce construction costs, reduce construction safety risks and shorten the construction period, creating a combination of manned electric basket and hoist chimney steel platform combined lifting method and the use of the car section of the transposed parallel steel inner cylinder hydraulic lift flip The construction process has achieved remarkable results in practice.