【摘 要】插入式角钢斜柱基础是指基础主柱与铁塔主材坡度相一致,与铁塔主材的连接方式为预埋角钢的基础,具有保护环境、节省材料、减少工程造价、降低人工等优点。本文主要从插入式基础的角钢安装、各数据尺寸控制、施工经验总结等方面进行论证。
【关键词】插入式;角钢斜柱基础;施工要点
Plug-angle Inclined Column foundation construction techniques analysis
Wei Li-jun
(Hebei Huamao Construction Engineering Inspection Co.ltd Handan Hebei 056000)
【Abstract】Plug-angle oblique column refer to the basic foundation of the main column and Tower slope main material consistent with the connection of the main material for the embedded tower base angle, with the protection of the environment, saving materials, reducing construction costs, reducing labor and other advantages. This article from the plug-in base installation angle, the size of each data control, and other aspects of construction to demonstrate lessons learned.
【Key words】Plug-in;Angle Inclined Column foundation;Construction points
1. 前言
因插入式角钢斜柱基础具有受力稳定、保护环境、节省材料、降低人工、可全方位高低腿、与挖孔桩混合使用等优点,越来越广泛的应用于输电线路中。但由于插入式基础误差特别小、质量要求高,必须对尺寸进行精确计算和严格控制;否则,将直接影响工程的质量及工程评优。本文对角钢插入式基础相关数据的计算、施工方法及注意事项进行介绍,有助于在其他工程中借鉴和提高工艺水平。
图1
注:在放置插入式角钢时,基础顶面应与插入角钢棱交点处的标记“▲”相重合(该标记“▲”在角钢加工时已预留)。
2. 施工方法介绍
2.1 施工工序:角钢插入式基础的施工工序与普通基础型式的施工工序不同。普通基础型式的施工工序为:绑扎钢筋→制模→调整地脚螺栓→浇制。而插入式基础的施工工序必须要先调整好主角钢后才能进行下道工序,首先要定好基坑底部的位置(用于预埋插入式角钢的下部支撑点),放置并调好插入式主角钢后才能进行钢筋绑扎,再进行制模、浇制等施工工序。
2.2 角钢插入式基础施工的主要操作方法如下:当主角钢埋入长度不可到达基础底板时,可用废角钢加工“假脚”将插入式角钢下接至基坑底板,用以固定主角钢的下部位置, 下部要用混凝土浇制砼垫块, 规格为:150mm×150mm×150mm,中央固定一根螺栓(脚钉),用来控制主角钢的高程和在基础底部的位置,放置砼垫块时,要使其三分之一的高度嵌入基坑底部,高度不够时,须搅拌混凝土拥于垫块四周,以固定砼垫块。而角钢上部的操作方法如图所示,插入式主角钢的控制采用双拉杆三点固定法——双调节杆和砼垫块固定。调节杆由角钢(或钢管)、法兰螺丝、防扭螺栓、固定铁板组成,前端与主角钢用螺丝相连,后端与打入地下角铁桩,分别在横线路和顺线路的两个面控制主角钢的倾斜率;(见图1)。
图2
图3
2.3 基础根开计算(俗称基础下根开):
施工时应注意:在单主材基础面的基础的半根开与棱角到棱角的半根开不同。两者的关系为:
(1)当插入式角钢为单主材时:基础的半根开+重心线=棱角到棱角的半根开基础的对角半根开+ 2 重心线=棱角到棱角对角半根开(重心线尺寸对于各种塔型数据不同,可查插入式角钢加工数据表)。
(2)当插入式角钢为双主材时(如图3所示):基础的半根开=两条角钢的棱角到棱角的半根开(即基础主柱顶面的中心与插入式角钢的中心相重合)基础的对角半根开=棱角到棱角对角半根开。
2.4 角钢上顶根开计算:(俗称基础上根开,本文按照高低腿半根开进行介绍计算方法):
(1)基础正、侧面半根开,令正面半根开= 正A 、侧面半根开= 侧B ;
(2)主角钢基重心线至角钢背宽度,令重心线宽= K ;
(3)主角钢外露长度,令外露高= h ;
(4)主角钢正、侧面倾斜率,令正面倾斜率= a 、侧面倾斜率=b 。
(5)计算方法如下:
图4
以上3点的计算中,最主要是严格进行角钢上顶半对角尺寸的控制,只要将半对角尺寸控制好后,上顶两个半根开尺寸的控制也符合要求。
2.5 角钢加工误差对施工的影响:
(1)由于角钢加工是非标产品,加工制造时可能会出现或多或少的误差。例如:插入式角钢在加工制造过程中也会产生因下料长短不齐、切割长度不一、最上端第1个螺丝孔与顶棱之间的距离不规范(在云广直流线路工程中规定为40mm)为而产生的误差等,其中最上端第1个螺丝孔与顶棱之间的距离必须严格控制,因为它的误差将直接影响到与铁塔主材连接时的质量,也直接影响到各腿插入式角钢的高差是否符合设计要求。
【关键词】插入式;角钢斜柱基础;施工要点
Plug-angle Inclined Column foundation construction techniques analysis
Wei Li-jun
(Hebei Huamao Construction Engineering Inspection Co.ltd Handan Hebei 056000)
【Abstract】Plug-angle oblique column refer to the basic foundation of the main column and Tower slope main material consistent with the connection of the main material for the embedded tower base angle, with the protection of the environment, saving materials, reducing construction costs, reducing labor and other advantages. This article from the plug-in base installation angle, the size of each data control, and other aspects of construction to demonstrate lessons learned.
【Key words】Plug-in;Angle Inclined Column foundation;Construction points
1. 前言
因插入式角钢斜柱基础具有受力稳定、保护环境、节省材料、降低人工、可全方位高低腿、与挖孔桩混合使用等优点,越来越广泛的应用于输电线路中。但由于插入式基础误差特别小、质量要求高,必须对尺寸进行精确计算和严格控制;否则,将直接影响工程的质量及工程评优。本文对角钢插入式基础相关数据的计算、施工方法及注意事项进行介绍,有助于在其他工程中借鉴和提高工艺水平。
图1
注:在放置插入式角钢时,基础顶面应与插入角钢棱交点处的标记“▲”相重合(该标记“▲”在角钢加工时已预留)。
2. 施工方法介绍
2.1 施工工序:角钢插入式基础的施工工序与普通基础型式的施工工序不同。普通基础型式的施工工序为:绑扎钢筋→制模→调整地脚螺栓→浇制。而插入式基础的施工工序必须要先调整好主角钢后才能进行下道工序,首先要定好基坑底部的位置(用于预埋插入式角钢的下部支撑点),放置并调好插入式主角钢后才能进行钢筋绑扎,再进行制模、浇制等施工工序。
2.2 角钢插入式基础施工的主要操作方法如下:当主角钢埋入长度不可到达基础底板时,可用废角钢加工“假脚”将插入式角钢下接至基坑底板,用以固定主角钢的下部位置, 下部要用混凝土浇制砼垫块, 规格为:150mm×150mm×150mm,中央固定一根螺栓(脚钉),用来控制主角钢的高程和在基础底部的位置,放置砼垫块时,要使其三分之一的高度嵌入基坑底部,高度不够时,须搅拌混凝土拥于垫块四周,以固定砼垫块。而角钢上部的操作方法如图所示,插入式主角钢的控制采用双拉杆三点固定法——双调节杆和砼垫块固定。调节杆由角钢(或钢管)、法兰螺丝、防扭螺栓、固定铁板组成,前端与主角钢用螺丝相连,后端与打入地下角铁桩,分别在横线路和顺线路的两个面控制主角钢的倾斜率;(见图1)。
图2
图3
2.3 基础根开计算(俗称基础下根开):
施工时应注意:在单主材基础面的基础的半根开与棱角到棱角的半根开不同。两者的关系为:
(1)当插入式角钢为单主材时:基础的半根开+重心线=棱角到棱角的半根开基础的对角半根开+ 2 重心线=棱角到棱角对角半根开(重心线尺寸对于各种塔型数据不同,可查插入式角钢加工数据表)。
(2)当插入式角钢为双主材时(如图3所示):基础的半根开=两条角钢的棱角到棱角的半根开(即基础主柱顶面的中心与插入式角钢的中心相重合)基础的对角半根开=棱角到棱角对角半根开。
2.4 角钢上顶根开计算:(俗称基础上根开,本文按照高低腿半根开进行介绍计算方法):
(1)基础正、侧面半根开,令正面半根开= 正A 、侧面半根开= 侧B ;
(2)主角钢基重心线至角钢背宽度,令重心线宽= K ;
(3)主角钢外露长度,令外露高= h ;
(4)主角钢正、侧面倾斜率,令正面倾斜率= a 、侧面倾斜率=b 。
(5)计算方法如下:
图4
以上3点的计算中,最主要是严格进行角钢上顶半对角尺寸的控制,只要将半对角尺寸控制好后,上顶两个半根开尺寸的控制也符合要求。
2.5 角钢加工误差对施工的影响:
(1)由于角钢加工是非标产品,加工制造时可能会出现或多或少的误差。例如:插入式角钢在加工制造过程中也会产生因下料长短不齐、切割长度不一、最上端第1个螺丝孔与顶棱之间的距离不规范(在云广直流线路工程中规定为40mm)为而产生的误差等,其中最上端第1个螺丝孔与顶棱之间的距离必须严格控制,因为它的误差将直接影响到与铁塔主材连接时的质量,也直接影响到各腿插入式角钢的高差是否符合设计要求。