论文部分内容阅读
我公司在部和公司党委的正确领导下,胜利地完成了一九六五年的建设任务。在工程质量方面,由于我们突出政治,加强了政治思想工作,坚持了“好字当头,质量第一”的方针,大力开展了以“三高、三清、三过硬、一包到底”为内容,以质量为中心的创样板活动,进一步加强了技术管理工作,从而使工程质量得到进一步的提高。全年交工验收的96项单位工程质量,全部合格,其中优良的94项,占97.92%。分部分项工程质量优良率达93.23%。样板工程越来
Under the correct leadership of the ministry and the company’s party committee, our company successfully completed the construction tasks of 1965. In terms of project quality, due to our outstanding politics, strengthened political and ideological work, and adhered to the principle of “Quality First, Quality First”, we vigorously carried out the “three highs, three clearings, three outstanding ones, and one package” in the end. "For the content, quality-centered model creation activities, and further strengthen the technical management work, so that the project quality has been further improved. The quality of the 96 project units that passed inspection and acceptance in the whole year were all qualified, of which 94 were excellent, accounting for 97.92%. The quality of the sub-projects was 93.23%. Model project is coming