摘 要:为解决尼龙化工精己二酸技术改造项目硝酸吸收塔基础工程地脚螺栓预埋精度问题,采取了大型螺栓组预埋技术,经检测,项目预埋48根M56不锈钢螺栓全部一次合格,不但节约了成本.而且大型螺栓组预埋施工技术解决了目前钢结构工程中地脚螺栓组预埋精度问题,避免了钢结构柱脚扩孔现象,缩短了工期.
关键词:大型螺栓组预埋精度 复核混凝土
Pick to: in order to solve the nylon chemical essence of adipic acid nitric acid absorber technological transformation project based engineering anchor bolt embedded accuracy problem, took a large bolt group of embedded technology, after the examination, 48 root M56 project embedded stainless steel bolts all qualified, not only save the cost. And a large bolt group embedded in solving the present steel structure project construction technology of anchor bolt group buries the accuracy problems, avoid the phenomenon of steel column foot reaming, shortens the time limit for a project.
Keywords: embedded accuracy check concrete large bolt group
中图分类号:TH文献标识码:A
工程概况:某尼龙化工精己二酸技术改造项目硝酸吸收塔基础工程,需要预埋48根M56不锈钢螺栓。上部高度为53米、重达220吨的吸收塔由这48根螺栓直接固定基础上。螺栓每根长度为2.2米,重为40公斤。螺栓总重量为2035公斤,需要沿跨中均布安放。传统的施工方法用钢筋通过焊接把螺栓与立壁钢筋网片相连,由于螺栓重量大,钢筋网片刚度小易变形,后期受砼浇筑的影响大,质量难以保证,目前国内没有成熟的施工工艺可以拿来直接应用。因此根据工程实践,浅谈一下大型螺栓组的施工工艺。
一、施工工艺:
(一)施工原理:把定位环板作为固定系统,脚手架作为支撑系统。定位环板,由上下两部分组成,形状为圆环形,在其上钻与螺栓直径相配套的孔,孔中心距与螺栓间距相同。上部环板由螺栓钢套管与2块环形钢板组成,钢套管把上下两块板连接成一个整体,套管长度依据螺栓露头长度定,其主要作用是确保螺栓的间距和垂直度;下部环板主要是锚固作用。把脚手架作为支撑系统,脚手架的强度、刚度和稳定性较好,在其底部设拖撑来调节环板高度和水平度。
施工工艺:
二、施工方法:
彈线:在垫层上根据施工图和坐标点用经纬仪和钢尺找出基础的定位线及圆心,在圆周上标出不少于2个螺栓的位置。
搭设脚手架:脚手架的搭设在基础垫层施工时根据立杆位置埋设Φ25钢筋,钢筋露头300,以便与立杆焊接。脚手架搭根据基础大小、定位板的尺寸以及螺栓的位置来确定每步架的高度、杆件的位置。每层平面为十字形,如下图所示。立杆在环板内安放4根,平杆应避开螺栓位置。为了方便安装螺栓,支撑下环板的平面杆件比环板设计位置低200处。上环板底杆件位置在设计标高处。搭设完成后用水准仪检查支撑上环板的点标高,高差控制在2mm。
制作定位环板:定位环板制作要进行1:1放样,在大样上标识出十字线、圆心和每个螺栓的位置与大小。钢板厚度选用12mm厚的Q235钢板,把钢板加工成比螺栓组直径大200的板3块。根据大样内容在钢板上逐一划出。然后进行机械制孔,孔径比螺栓直径大2mm。再按线加工成宽度为200的环形。这样下定位板就做成了。上定位板加工需要先截取比螺栓露头长度小180钢套管,钢套管内径大于螺栓直径2mm,厚度不小于3.5mm。现把上定位板的其中一个安放水平,然后把钢套管逐个焊接在该块板上,用水平尺逐一检查套管的垂直度,要求不大于1mm。最后再把另一块板与钢套管连接。上部定位环板几何尺寸大,为了增加刚度,在圆环内加焊∠75*6角钢制成的十字撑。定位环板也可委托工厂加工。
安装定位环板:下部锚板先就位,用扣件进行临时固定。然后安放支撑上部环板的平面杆件。安装前,用水准仪检查支撑杆件是否在同一水平面上并通过调整拖撑或其它手段进行调平。安放环板后通过在环板上拉十字线找出中心并复核是否与垫层上标识的圆心在同一条铅垂线上;用经纬仪检查轴线位置。检查符合要求后,在上环板四周用扣件固定在杆件上。
螺栓安装:需逐条对称安放螺栓,通过调整丝扣控制露头长度。最后再通过下部螺栓与锚板相连,如下图所示。
复核:螺栓全部安放完成后,用水准仪、钢尺等复核标高和平整度;通过经纬仪和拉线的方法检查位置。见下图:
加固脚手架:复核无误后加固架体。加固架体包括在支撑环板的纵横杆位置处增加不少于2根斜拉杆件,杆件搭设与剪刀撑相似;还包括在基坑周围设抛撑与架体相连等方法。
隐蔽:经监理或厂家代表验收并签字后,方可进行隐蔽。
砼浇筑:浇筑前,在螺栓丝扣处先涂抹黄油,然后用塑料薄膜密封,防止受到砼污染。浇筑时分层对称进行,每层厚度500-800高。施工过程中随时检查每层浇筑厚度,避免因为过厚砼流动使架体位移超过规范要求。
验收:砼施工完成后,建设单位、监理单位、设计单位和设备厂家等进行联合验收,并履行签字手续。
质量要求:
1、 加工的定位环板,要确保孔距、几何尺寸、强度满足要求。
2、脚手架搭应考虑上部荷载,根据构造要求和螺栓位置等进行搭设,荷载特别大的,应进行验算。
3、安装的允许偏差和检验:
项
结束语:通过在尼龙化工公司的应用中,螺栓组验收一次通过,在后续设备安装时,螺栓位置与设备高度吻合,大型螺栓组的预埋,提高了螺栓安装的精度。在工业建筑,尤其是化工、风电和核电等行业,有许多设备需要安放螺栓组。大型螺栓组施工质量是大型设备安装的必要条件。因此找到一个确保施工质量的施工工艺,也是我们长期探讨的一个话题。
参考文献:大型高强螺栓组群节点施工技术《建筑科技情报》
王海涛2010年第四期
青岛扶桑JFH项目地脚螺栓组预埋施工技术 《青岛理工大学学报》吴安农 李中山 2006年第6期
横向载荷下普通螺栓组连接设计方法的讨论 《中国集体经济》 席本强2007.07
关键词:大型螺栓组预埋精度 复核混凝土
Pick to: in order to solve the nylon chemical essence of adipic acid nitric acid absorber technological transformation project based engineering anchor bolt embedded accuracy problem, took a large bolt group of embedded technology, after the examination, 48 root M56 project embedded stainless steel bolts all qualified, not only save the cost. And a large bolt group embedded in solving the present steel structure project construction technology of anchor bolt group buries the accuracy problems, avoid the phenomenon of steel column foot reaming, shortens the time limit for a project.
Keywords: embedded accuracy check concrete large bolt group
中图分类号:TH文献标识码:A
工程概况:某尼龙化工精己二酸技术改造项目硝酸吸收塔基础工程,需要预埋48根M56不锈钢螺栓。上部高度为53米、重达220吨的吸收塔由这48根螺栓直接固定基础上。螺栓每根长度为2.2米,重为40公斤。螺栓总重量为2035公斤,需要沿跨中均布安放。传统的施工方法用钢筋通过焊接把螺栓与立壁钢筋网片相连,由于螺栓重量大,钢筋网片刚度小易变形,后期受砼浇筑的影响大,质量难以保证,目前国内没有成熟的施工工艺可以拿来直接应用。因此根据工程实践,浅谈一下大型螺栓组的施工工艺。
一、施工工艺:
(一)施工原理:把定位环板作为固定系统,脚手架作为支撑系统。定位环板,由上下两部分组成,形状为圆环形,在其上钻与螺栓直径相配套的孔,孔中心距与螺栓间距相同。上部环板由螺栓钢套管与2块环形钢板组成,钢套管把上下两块板连接成一个整体,套管长度依据螺栓露头长度定,其主要作用是确保螺栓的间距和垂直度;下部环板主要是锚固作用。把脚手架作为支撑系统,脚手架的强度、刚度和稳定性较好,在其底部设拖撑来调节环板高度和水平度。
施工工艺:
二、施工方法:
彈线:在垫层上根据施工图和坐标点用经纬仪和钢尺找出基础的定位线及圆心,在圆周上标出不少于2个螺栓的位置。
搭设脚手架:脚手架的搭设在基础垫层施工时根据立杆位置埋设Φ25钢筋,钢筋露头300,以便与立杆焊接。脚手架搭根据基础大小、定位板的尺寸以及螺栓的位置来确定每步架的高度、杆件的位置。每层平面为十字形,如下图所示。立杆在环板内安放4根,平杆应避开螺栓位置。为了方便安装螺栓,支撑下环板的平面杆件比环板设计位置低200处。上环板底杆件位置在设计标高处。搭设完成后用水准仪检查支撑上环板的点标高,高差控制在2mm。
制作定位环板:定位环板制作要进行1:1放样,在大样上标识出十字线、圆心和每个螺栓的位置与大小。钢板厚度选用12mm厚的Q235钢板,把钢板加工成比螺栓组直径大200的板3块。根据大样内容在钢板上逐一划出。然后进行机械制孔,孔径比螺栓直径大2mm。再按线加工成宽度为200的环形。这样下定位板就做成了。上定位板加工需要先截取比螺栓露头长度小180钢套管,钢套管内径大于螺栓直径2mm,厚度不小于3.5mm。现把上定位板的其中一个安放水平,然后把钢套管逐个焊接在该块板上,用水平尺逐一检查套管的垂直度,要求不大于1mm。最后再把另一块板与钢套管连接。上部定位环板几何尺寸大,为了增加刚度,在圆环内加焊∠75*6角钢制成的十字撑。定位环板也可委托工厂加工。
安装定位环板:下部锚板先就位,用扣件进行临时固定。然后安放支撑上部环板的平面杆件。安装前,用水准仪检查支撑杆件是否在同一水平面上并通过调整拖撑或其它手段进行调平。安放环板后通过在环板上拉十字线找出中心并复核是否与垫层上标识的圆心在同一条铅垂线上;用经纬仪检查轴线位置。检查符合要求后,在上环板四周用扣件固定在杆件上。
螺栓安装:需逐条对称安放螺栓,通过调整丝扣控制露头长度。最后再通过下部螺栓与锚板相连,如下图所示。
复核:螺栓全部安放完成后,用水准仪、钢尺等复核标高和平整度;通过经纬仪和拉线的方法检查位置。见下图:
加固脚手架:复核无误后加固架体。加固架体包括在支撑环板的纵横杆位置处增加不少于2根斜拉杆件,杆件搭设与剪刀撑相似;还包括在基坑周围设抛撑与架体相连等方法。
隐蔽:经监理或厂家代表验收并签字后,方可进行隐蔽。
砼浇筑:浇筑前,在螺栓丝扣处先涂抹黄油,然后用塑料薄膜密封,防止受到砼污染。浇筑时分层对称进行,每层厚度500-800高。施工过程中随时检查每层浇筑厚度,避免因为过厚砼流动使架体位移超过规范要求。
验收:砼施工完成后,建设单位、监理单位、设计单位和设备厂家等进行联合验收,并履行签字手续。
质量要求:
1、 加工的定位环板,要确保孔距、几何尺寸、强度满足要求。
2、脚手架搭应考虑上部荷载,根据构造要求和螺栓位置等进行搭设,荷载特别大的,应进行验算。
3、安装的允许偏差和检验:
项
结束语:通过在尼龙化工公司的应用中,螺栓组验收一次通过,在后续设备安装时,螺栓位置与设备高度吻合,大型螺栓组的预埋,提高了螺栓安装的精度。在工业建筑,尤其是化工、风电和核电等行业,有许多设备需要安放螺栓组。大型螺栓组施工质量是大型设备安装的必要条件。因此找到一个确保施工质量的施工工艺,也是我们长期探讨的一个话题。
参考文献:大型高强螺栓组群节点施工技术《建筑科技情报》
王海涛2010年第四期
青岛扶桑JFH项目地脚螺栓组预埋施工技术 《青岛理工大学学报》吴安农 李中山 2006年第6期
横向载荷下普通螺栓组连接设计方法的讨论 《中国集体经济》 席本强2007.07