嘉绍大桥主航道桥为六塔独柱四索面分体钢箱梁斜拉桥,钢箱梁左右幅梁段间隔采用箱形横梁、工字形横梁和无横梁形式,梁体宽度达到55.6m。首先分析了采用传统左右幅钢箱梁整体吊装方案的可行性,为降低施工风险,提出左右幅梁段独立吊装的施工方案。为满足施工过程结构受力的需要,提高中间横梁施工工效,采用长度可调节的临时横梁辅助受力,并对横梁的工地连接构造形式进行优化,提出的分体钢箱梁独立吊装技术施工速度快、安全性高,可为类似工程提供很好的借鉴。
The main waterway bridge of Jiashao Bridge is a six-tower single-column four-cable split steel box girder cable-stayed bridge. The left and right girder sections of steel box girders are box-beam, I-beam and beamless. The width of the girder is 55.6m . Firstly, the feasibility of adopting the traditional hoisting scheme of the steel box girder with the traditional left and right webs is analyzed. In order to reduce the construction risk, the construction scheme of independently hoisting the left and right web beams is proposed. In order to meet the needs of the construction process of the force, improve the efficiency of the middle beam construction, the use of temporary length adjustable beam to assist the force, and to connect the beam site construction optimization, proposed separate steel box girder independent lifting technology construction speed Fast, safe, can provide a good reference for similar projects.