在1999年发表关于“国家点火装置”建造费用超支和管理不善后,能源部被迫修改项目。在其2000财年拨款方案中,国会要求提出“国家点火装置”的新费用和进度估算。2000年6月1日,能源部长BillRichardson送交国会一份修订费用和进度基线的中间检验证明报告。根据此份中间评估的?
After making a statement about the cost overruns and mismanagement of the construction of a “national ignition” in 1999, the Department of Energy was forced to modify the project. In its 2000 fiscal year appropriation program, Congress requested new costs and progress estimates for “national ignition devices.” On June 1, 2000, Bill Richardson, Minister of Energy, sent a copy of the Intermediate Inspection Certificate to the National Assembly to amend the fee and schedule baseline. According to this intermediate assessment?