现浇混凝土水池一般为薄壁的水工构筑物,是水上游乐设备工程施工控制的重点。大型水上游乐设备的水池滑道多为不规则曲面水池,对于混凝土结构外观质量和内在质量具有较高的要求,同时构造尺寸必须满足处理工艺与设备的精度要求,一般设计上有抗冻、抗渗、抗裂要求,因此在模板、钢筋、混凝土、止水带、施工缝等各个环节应采取有效质量控制措施以保证构造尺寸的准确,防止裂缝的产生,满足水工构筑物功能性试验要求。本文旨在研究和探讨与现浇混凝土曲面水池施工的相关内容,主要结合合肥万达主题乐园项目水上游乐项目秘境漂流水道的施工情况,分别从施工工艺、施工中控制要点等方面进行阐述,希望能够在阐述中为混凝土现浇不规则曲面水池施工提供可行性施工方案。
Cast-in-place concrete ponds are generally thin-walled hydraulic structures, water recreation equipment engineering construction control focus. Large water playground equipment pool slide mostly irregular curved pool, the appearance quality and intrinsic quality of concrete structures have high requirements, while the construction size must meet the accuracy requirements of processing technology and equipment, the general design of the antifreeze, anti Therefore, effective quality control measures should be taken in all aspects such as formwork, steel bar, concrete, water stop and construction joint so as to ensure the accurate structure size and prevent the occurrence of cracks and meet the functional test requirements of hydraulic structures. This paper aims to study and discuss with the construction of cast-in-situ concrete surface pool, mainly combined with the construction of Hefu Wanda Theme Park waterfront project secret drifting waterway, elaborated from the construction technology, construction control points, etc., hoping to In the elaboration, it provides a feasible construction plan for the construction of irregularly curved concrete pool surface pool.