论文部分内容阅读
高温气冷堆核电站示范工程是世界首座模块式高温气冷堆核电站示范工程,其核岛厂房结构形式复杂多变,各厂房层高及房间尺寸无统一模数,给施工过程中模板的选型和施工带来了很大的施工难度。经过充分的对比论证,最终选用了组装灵活、形式多变、自重轻便的木工字梁组拼式大模板体系,大大降低了安全风险,减少了施工成本,非常有利于结构施工的质量控制和进度控制。
High temperature gas-cooled reactor nuclear power plant demonstration project is the world’s first modular high temperature gas-cooled reactor nuclear power station demonstration project, its nuclear island plant complex and changeable form, the plant height and room dimensions without uniform modulus, to the construction process template selection And construction has brought a lot of construction difficulty. After a full comparison and demonstration, the final selection of flexible assembly, changing the form, weight lightweight carpentry beam formwork big template system, greatly reducing the safety risk, reducing construction costs, is very conducive to the quality control of construction and progress control.