经过一年多的紧张建设,全国首批6大国家级中心渔港之一的吕四中心渔港主体工程已经完工。该港于2002年10月由农业部批准立项,中央预算内专项资金及省、市配套资金总投资4228.82万元。2003年2月,渔港设计方案获江苏省海鱼局评审专家审查认可。截至目前,港西征地80亩,总面积19852平方米的拆迁任务和老码头拆除已全部完成;总长1440米板桩码头已建成,平均拓宽15米。清淤总
After more than a year of intense construction, the main fishing port project of Lv Si Center, one of the first six major state-level fishing ports in the country, has been completed. The port was approved by the Ministry of Agriculture in October 2002 and the total investment in the central budget and the matching funds in the provinces and cities totaled 42.2882 million yuan. In February 2003, the fishing port design scheme was approved by Jiangsu Provincial Bureau of Ocean Fish Assessment. Up to now, 80 mu of land in Hong Kong and west of Hong Kong has been demolished and the dismantling of old wharfs has been completed. The total length of 1440 meters of piled piles has been completed and the average is 15 meters wide. Dredging total