论文部分内容阅读
【摘 要】南京市大观天地MALL项目基坑支护工程设计采用的是1997年从日本引进的先进设备和技术。SMW工法桩是利用专门的多轴搅拌机,就地钻进切削土体,同时在钻头端将水泥浆液注入土体,充分搅拌混合后,再将H型钢插入搅拌桩内,形成地下连续墙,利用该墙作为挡土和止水结构,特别适合城市的深基坑工程,体现了基坑支护形式的多样性。
【关键词】SMW工法;H型钢;水泥搅拌墙;三轴搅拌桩;基坑支护形式的多样性
Great view-Foundation ditch of world MALL protects design and construction(part 2)
Xu Li-yuan
(Nanjing North Pole survey and mapping Nanjing research institute Nanjing Jiangsu 210000)
【Abstract】Nanjing City great view world MALL project foundation ditch protect an engineering design to adopt of is advanced equipments and technique that ushers in from Japan in 1997. The SMW work method stake makes use of many specialized stalk mixers and right on the spot drill into slice to pare a soil body, carry to strach cement the liquid infusion soil body in the auger in the meantime, after well mixing blend mixture, again insert the H type steel into the agitation stake, become an underground continuous wall, use that wall as to block soil and water structure, specially suit a city of deep foundation ditch engineering, body now foundation ditch is diverse that protect a form.
【Key words】SMW work method; H type steel; Cement mix blend wall; Three stalk agitation stake; Foundation ditch diverse that protect form
7. SMW工法的主要特点
(1)施工中不扰动邻近土体,不会产生邻近地面下沉、房屋倾斜、道路裂损及地下设施移位等危害。此类搅拌桩不存在挤土作用,对周围建筑物和管线的安全极为有利。
(2)钻杆具有螺旋推进翼与搅拌翼相间设置的特点,随着钻掘和搅拌的反复进行,可使水泥系强化剂与土得到充分搅拌,而且墙体全长无接缝,从而使它可比传统连续墙具有更可靠的止水性,其渗透系数K可达10~7cm/s。
(3)它可在粘性土、砂土、粉土、砂砾土、100以上卵石及单轴抗压强度60MPa以下的岩层应用。
(4)可成墙厚度550~1300mm,常用厚度600~850mm,成墙最大深度目前为65米,视地质条件尚可施工至更深。
(5)所需工期较其他工法为短,同钻孔灌注桩比较工期可以短2/3在一般地质条件下,每一台班可成墙70~80m2,造价明显降低约18.8%工程成本。
(6)废土外运量远比其他工法少,实践证明南京大观天地MALL工程,采用SMW工法桩施工是可行的,由于四周可不作防护,H型钢又可回收,造价明显降低,加快了施工进度,取得了良好的经济和社会效益。
2008年4月30日召开有市建委韩云桥总工参加的专家论证会,结论意见:
(1)根据支护结构变形和应力监测报告资料分析,该支护结构体系是安全的;
(2)由于填土层较厚,土质差,支护结构变形等原因,纵向沉降差异造成围墙裂缝较多,但根据裂缝宽度、分布特征,发展速率判断,静海寺房屋和连廊是安全的。
(3)根据复算,局部超挖300mm,采用措施后是安全的;
(4)基本同意对围墙、连廊采用压密注浆加固方案,并建议如下:
a.控制注浆压力在1MPa左右;
b.注浆深度根据填土厚度确定,宜穿过填土层;
c.注浆时加强对地面及围墙、连廊、房屋以及支护结构的监测,如出现异常,应立即停止注浆。
(5)加快靠近静海寺一侧的底板施工速度。
(6)尽量减少地面堆载。
8. 施工工况
靠近静海寺侧采用水钻孔灌注桩,冲击钻共24根,桩长27~29.1m,止水采用双轴深搅,桩长15.9m,岩面浅用二重管压密注浆,靠建宁路、热河路、郑河路采用SMW工法桩,插二跳一型,共452幅,插24mH型钢628根。
9. 监理工作
严格审查施工单位的施工组织设计,把好材料计量关,并按设计及规范进行检测,随机取样,按照工序申报合格后才能进入下道工序,监理作为高智能服务,为开发公司提供技术支持,对SMW工法设计理论提出以整体滑移稳定控制,桩长由26.5m减为24m,节省材料费用,加快施工工期,对南部约1万m2的车库加深50cm进行复算,提出不增加第四道支撑也可节省40万元费用,施工也可以加快,对基坑测试方案,提出能保证基坑安全的符合实际的方案,减少不必要的测点,监理精心组织,精心设计,多做计算分析,为工程创优夺杯献出我们的力量,得到开发公司的认同,由监理执笔和开发公司、施工单位撰写了多篇论文,在市、省、国家杂志发表。
(1)简支格构柱用冲击钻,到已施工的桩头不需加撑;
(2)桁架因无水平力作用,可不设米字拉杆;
(3)基坑工法桩经多方咨询专家,并经计算应该是整体滑移稳定起控制作用,桩长可减少,由26.5m减到21~24m,节约钢材费用,加快施工;(4)南面建宁路侧由于增加车库面积7000m2,需要继续挖深50cm,监理经过计算整体滑移稳定能够满足要求,故不需要增加第四道钢支撑和围檩,不但节省了费用,而且减少了施工难度,使施工进度加快。
10. SMW工法与钻孔灌注止水的经济价值分析
10.1 结构形式比较,见表1。
10.2 结构经济价值分析(按每10米长进行测算)
(1)钻孔灌注桩,桩径1000mm,砼标号为C30,桩长24米,每根桩主筋为2125,加强筋为16@200,螺旋筋为8@200,桩距1000mm,双轴止水桩为700,桩中心距为1000mm,桩体纵横搭接200mm,采用普通硅酸盐水泥,掺入量为16%,水灰比0.45~0.55,采用四搅二喷施工,参照省建筑与装饰工程价表,其造价是216438.11元。
(2)SMW工法根据招标文件中规定:H型钢在120天施工的施工期间所有的插入、拔出,涂减磨剂等所有费用均在报价中,当超过120天时,型钢按每吨每天7元计算租金,直到拔出为止。在《南京地铁工程计价表》子目2-69中,没有规定工期时间,只是说明了型钢按四次摊销,从我们了解的其他城市情况,一般按6~8次摊销,为此我们结合实际情况分别计算了了其造价,见表2。(注:地铁计价表中的工资标准已换算成建筑与装饰计价表中的工资标准。)
(3) 结论:该工程使用的是插二跳一,现以此为例,工期120天内按四次摊销,比钻孔灌注桩造价节省造价19.734%,按八次摊销,节省造价34.998%,工期每增加30天分别比钻孔灌注桩造价节省12.625%(四次摊销)和27.897%(八次摊销)。根据这样推算,工期超过120+90天,使用SMW工法(按四次摊销)比灌注桩增加1.6139%,考虑到使用钻孔灌注桩一次性投入有银行贷款利息,工期120天外加3个月就基本持平,工期越长工法桩就越不经济,详细地价值比较见表3、表4、表5。
[文章编号]1006-7619(2008)10-29-614
【关键词】SMW工法;H型钢;水泥搅拌墙;三轴搅拌桩;基坑支护形式的多样性
Great view-Foundation ditch of world MALL protects design and construction(part 2)
Xu Li-yuan
(Nanjing North Pole survey and mapping Nanjing research institute Nanjing Jiangsu 210000)
【Abstract】Nanjing City great view world MALL project foundation ditch protect an engineering design to adopt of is advanced equipments and technique that ushers in from Japan in 1997. The SMW work method stake makes use of many specialized stalk mixers and right on the spot drill into slice to pare a soil body, carry to strach cement the liquid infusion soil body in the auger in the meantime, after well mixing blend mixture, again insert the H type steel into the agitation stake, become an underground continuous wall, use that wall as to block soil and water structure, specially suit a city of deep foundation ditch engineering, body now foundation ditch is diverse that protect a form.
【Key words】SMW work method; H type steel; Cement mix blend wall; Three stalk agitation stake; Foundation ditch diverse that protect form
7. SMW工法的主要特点
(1)施工中不扰动邻近土体,不会产生邻近地面下沉、房屋倾斜、道路裂损及地下设施移位等危害。此类搅拌桩不存在挤土作用,对周围建筑物和管线的安全极为有利。
(2)钻杆具有螺旋推进翼与搅拌翼相间设置的特点,随着钻掘和搅拌的反复进行,可使水泥系强化剂与土得到充分搅拌,而且墙体全长无接缝,从而使它可比传统连续墙具有更可靠的止水性,其渗透系数K可达10~7cm/s。
(3)它可在粘性土、砂土、粉土、砂砾土、100以上卵石及单轴抗压强度60MPa以下的岩层应用。
(4)可成墙厚度550~1300mm,常用厚度600~850mm,成墙最大深度目前为65米,视地质条件尚可施工至更深。
(5)所需工期较其他工法为短,同钻孔灌注桩比较工期可以短2/3在一般地质条件下,每一台班可成墙70~80m2,造价明显降低约18.8%工程成本。
(6)废土外运量远比其他工法少,实践证明南京大观天地MALL工程,采用SMW工法桩施工是可行的,由于四周可不作防护,H型钢又可回收,造价明显降低,加快了施工进度,取得了良好的经济和社会效益。
2008年4月30日召开有市建委韩云桥总工参加的专家论证会,结论意见:
(1)根据支护结构变形和应力监测报告资料分析,该支护结构体系是安全的;
(2)由于填土层较厚,土质差,支护结构变形等原因,纵向沉降差异造成围墙裂缝较多,但根据裂缝宽度、分布特征,发展速率判断,静海寺房屋和连廊是安全的。
(3)根据复算,局部超挖300mm,采用措施后是安全的;
(4)基本同意对围墙、连廊采用压密注浆加固方案,并建议如下:
a.控制注浆压力在1MPa左右;
b.注浆深度根据填土厚度确定,宜穿过填土层;
c.注浆时加强对地面及围墙、连廊、房屋以及支护结构的监测,如出现异常,应立即停止注浆。
(5)加快靠近静海寺一侧的底板施工速度。
(6)尽量减少地面堆载。
8. 施工工况
靠近静海寺侧采用水钻孔灌注桩,冲击钻共24根,桩长27~29.1m,止水采用双轴深搅,桩长15.9m,岩面浅用二重管压密注浆,靠建宁路、热河路、郑河路采用SMW工法桩,插二跳一型,共452幅,插24mH型钢628根。
9. 监理工作
严格审查施工单位的施工组织设计,把好材料计量关,并按设计及规范进行检测,随机取样,按照工序申报合格后才能进入下道工序,监理作为高智能服务,为开发公司提供技术支持,对SMW工法设计理论提出以整体滑移稳定控制,桩长由26.5m减为24m,节省材料费用,加快施工工期,对南部约1万m2的车库加深50cm进行复算,提出不增加第四道支撑也可节省40万元费用,施工也可以加快,对基坑测试方案,提出能保证基坑安全的符合实际的方案,减少不必要的测点,监理精心组织,精心设计,多做计算分析,为工程创优夺杯献出我们的力量,得到开发公司的认同,由监理执笔和开发公司、施工单位撰写了多篇论文,在市、省、国家杂志发表。
(1)简支格构柱用冲击钻,到已施工的桩头不需加撑;
(2)桁架因无水平力作用,可不设米字拉杆;
(3)基坑工法桩经多方咨询专家,并经计算应该是整体滑移稳定起控制作用,桩长可减少,由26.5m减到21~24m,节约钢材费用,加快施工;(4)南面建宁路侧由于增加车库面积7000m2,需要继续挖深50cm,监理经过计算整体滑移稳定能够满足要求,故不需要增加第四道钢支撑和围檩,不但节省了费用,而且减少了施工难度,使施工进度加快。
10. SMW工法与钻孔灌注止水的经济价值分析
10.1 结构形式比较,见表1。
10.2 结构经济价值分析(按每10米长进行测算)
(1)钻孔灌注桩,桩径1000mm,砼标号为C30,桩长24米,每根桩主筋为2125,加强筋为16@200,螺旋筋为8@200,桩距1000mm,双轴止水桩为700,桩中心距为1000mm,桩体纵横搭接200mm,采用普通硅酸盐水泥,掺入量为16%,水灰比0.45~0.55,采用四搅二喷施工,参照省建筑与装饰工程价表,其造价是216438.11元。
(2)SMW工法根据招标文件中规定:H型钢在120天施工的施工期间所有的插入、拔出,涂减磨剂等所有费用均在报价中,当超过120天时,型钢按每吨每天7元计算租金,直到拔出为止。在《南京地铁工程计价表》子目2-69中,没有规定工期时间,只是说明了型钢按四次摊销,从我们了解的其他城市情况,一般按6~8次摊销,为此我们结合实际情况分别计算了了其造价,见表2。(注:地铁计价表中的工资标准已换算成建筑与装饰计价表中的工资标准。)
(3) 结论:该工程使用的是插二跳一,现以此为例,工期120天内按四次摊销,比钻孔灌注桩造价节省造价19.734%,按八次摊销,节省造价34.998%,工期每增加30天分别比钻孔灌注桩造价节省12.625%(四次摊销)和27.897%(八次摊销)。根据这样推算,工期超过120+90天,使用SMW工法(按四次摊销)比灌注桩增加1.6139%,考虑到使用钻孔灌注桩一次性投入有银行贷款利息,工期120天外加3个月就基本持平,工期越长工法桩就越不经济,详细地价值比较见表3、表4、表5。
[文章编号]1006-7619(2008)10-29-614