在特立尼达和多巴哥西班牙港国家艺术中心室外雨水系统的设计中,根据当地排水部门的要求,项目建成前后的基地雨水排放不能增加市政排放系统的流量,为此根据当地暴雨强度公式,对比了项目建成前后的雨水排放量,通过设置雨水调节池的方式调蓄了洪峰径流量,并就如何确定调节池的容积进行了探讨。
In the design of the outdoor rainwater system of the National Art Center of Port of Spain in Port of Trinidad and Tobago, the drainage of the base before and after the completion of the project can not increase the discharge of the municipal discharge system according to the requirements of the local drainage department. Therefore, according to the local storm intensity formula , Compared the discharge of rainwater before and after the completion of the project, set up the stormwater runoff by setting the rainwater regulation pool, and discussed how to determine the volume of the regulation pond.