摘要:鹤山市沙坪联围泵站更新改造工程总工期为18个月,工期目标为:2012年4月12日前沙坪泵站全部机组具备运行条件,能够承担排涝任务。现因主厂房电机层以下为流道、异形复杂结构、埋件多、工程量大、施工难度大、设计变更多,导致工期延误45天。为使工程建设项目按时完工,尽快发挥经济效益,需加快施工进度,追回已延误的工期。而进度与质量是统一的矛盾体,加快进度会因材料供应紧张,施工条件的改变,可能会影响到工程质量。
关键字:进度;质量;工期;施工
Abstract: ShaPing united around the pumping station yinhe rebuilding project total duration for 18 months, time limit for target: in April 2012 ShaPing pump station before 12 all units have operating conditions, can undertake draining task. Now for the following main workshop of motor for port, abnormity complex structure, and built-in parts, bill, more difficult construction, design change much, time delay in 45 days. For the engineering construction project on time, play as soon as possible economic benefit, need to speed up the construction progress and recover has delayed time limit. And progress and quality is unified encompasses, will speed up the process by material supplies are tight, construction of the changed conditions, may affect the quality of the project.
Key word: progress; Quality; Time limit; construction
中图分类号:TV523 文献标识码:A 文章编号:
鹤山市沙坪联围泵站更新改造工程总工期为18个月,现因各种原因导致工期延误45天,为追回已延误的工期,需采取必要的赶工措施。天车梁结构施工是桥机安装调试的紧前工作,桥机安装调试是机组设备安装的紧前工作,所以为按期完成施工任务的关键结点在于加快天车梁结构的施工。
为了追回已延误的工期,根据劳动力强度,适度均衡地加快施工进度,不仅可以使计划工期得到合理的提前,而且还可以保证施工质量。严格控制质量,可以避免返工,进度则会加快;提高了承包商的施工效益,减少建设项目的经常性维护费用,延长工程使用年限,从而降低了投资成本,提高了施工单位的经济效益;反之则会因返工,造成工期延后,施工成本增加。
进度控制和质量控制在施工中的作用与关系
工程施工中最重要的是进度和质量,施工进度按最佳工期施工,可以在合理的时间内使施工企业产生更大的经济效益,使建设工程投资按计划工期交付使用,在预定的期限内尽早地收回投资。质量好可以减少工程施工返工;减少施工单位成本投入;减少建设单位的经常性维修;延长建设工程的使用年限,保证建设工程的稳定长效运营,提高投资效益,降低维护成本。因此必须掌握好进度控制和质量控制工作的要点,才能使工作做的有效、准确,发挥更好的经济效益。
而单方面地追求工期又会产生质量问题,会造成返工,会降低施工企业经济效益,影响到建设单位投资效益的尽快发挥。为了保证施工质量,偏面地精做细干又会使工期延后,成本增加。因此进度控制和质量控制规划设计,在施工中的关系是紧密的,只有认真地完成进度控制和质量控制规划设计的工作任务,才能保证在合理的时间内完成优良的建筑产品。
如何加快天车梁施工进度
合理的进度计划应体現资源的合理使用,工作面的合理安排,有序的进度计划有利于提高建设质量,有利于文明施工,有利于合理地缩短建设周期。而施工方案对工程进度有直接影响,在决策其适用时,不仅应分析技术的先进性和经济合理性,还应考虑其对进度的影响。尤其在工程进度滞后时,应分析是否存在施工技术、方法、环境、机械等方面的影响因素。
本工程项目主厂房有6跨12根天车梁,安装间有3跨6根天车梁,共18根天车梁,单根梁最长6150mm,最短5150mm,梁高900mm,每根重约6.0t,天车梁离电机层楼面高度为14.1m。原天车梁施工方案为现浇,为在关键线路工期上节省现浇混凝土龄期(28天),加快桥机安装及运行,为机组设备安装提供必要条件,故将天车梁现浇方案改为预制。
从主厂房空间考虑,天车梁预制免去了承重排架的搭设,可节省工期及节约成本,同时也能加快主厂房其他主体结构及砖砌体施工,避免装修工程与机组设备安装之间的交叉作业,从而加快了总工期的施工进度,对实现总工期提供了有力保证。
预制天车梁为低空作业,受不确定因素影响较小,场地容易布置,工作面容易开展,能够有效地组织人员、机械、材料形成流水作业,进行有序施工。天车梁共18根,集中主要材料、施工力量每天预制6根,3天即可完成。牛腿柱、天车梁强度都达到设计要求后,用50t履带吊将天车梁吊到牛腿柱上,履带吊需就两次位,就能完成全部吊装工作。
如何控制天车梁质量
建设工程质量不仅关系到建设工程的适用性、安全性、耐久性和建设项目的投资效益,同时也关系到人民群众生命和财产安全。所以应对建设工程质量实施有效控制,保证工程质量达到预期目标。
施工质量控制是整个建设工程项目质量控制的关键,施工是形成工程建设项目实体的阶段也是形成最终产品质量的重要阶段。所以,施工阶段的质量控制是工程建设项目质量控制的重点也是施工阶段要合理完成的重要因素。要控制好天车梁质量,需做到以下三点:
周密计划,要做到事前控制,在施工前,应认真审核设计图纸,做好技术资料准备工作,做好对钢筋、模板原材料的检查和控制工作。天车梁截面型式为梯形,所用主筋为Φ25,箍筋为¢10@100。在施工之前,应对模板的组装方法,每种钢筋的下料长度,布置间距向施工班组详细交底。还应努力做到对施工中可能发生的问题有一个预见性措施,才能在事前就把施工中的质量问题解决好,避免因没有做好事前控制造成建设工程施工质量返工的问题。
事中控制指在施工质量形成过程中,对影响施工质量的各种因素进行全面的动态控制。每一道工序,从天车梁模板支立到混凝土浇筑都有专业技术人员现场跟踪。事中控制的关键是坚持质量标准,控制的重点是工序质量、工作质量和质量控制点的控制。严格执行工序间的交接检查,认真执行“三检”制,即自检、互检、专检,对天车梁预埋件重要工程部位,项目总工应亲自进行技术复核,并进行实时监控。
事后控制即事后质量把关,以使不合格的工序或最终产品不得流入下道工序,控制的重点是发现施工质量方面的缺陷,并通过分析提出施工质量改进措施,保证质量处于受控状态。
现场检查质量的方法主要有目测法、实测法。
通过目测法,即通过感官对天车梁质量进行检查,其方法可概括为“看、摸、敲、照”。看、就是通过质量标准,对天车梁混凝土外观进行检查,看混凝土是否存在蜂窝麻面及露筋;摸、就是通过触摸手感进行检查,鉴别天车梁表面的光滑度;敲、就是应用敲击工具进行音感检查,用小锤敲击天车梁混凝土可判断混凝土是否密实;照、就是通过人工光源或反射光照射,检查天车梁翼缘处的细微部位。
通过实测法,即通过“靠、量、吊、套”取得实测数据与施工规范、质量标准要求的允许偏差值进行对照,以此判断质量是否符合要求。靠、就是用直尺、塞尺检查天车梁混凝土的平整度;量、就是用测量工具检查天车梁的结构尺寸,轴线、标高等的偏差;吊、就是用托线板以及线锤吊线检查天车梁的垂直度;套、就是方尺套方、辅以塞尺检查天车梁阴阳角的方正。
落实进度控制与质量控制对建设工程的作用
合格的建筑产品是在施工组织设计中对进度控制和质量控制进行科学合理的计算与规划,工程施工中进行有效的控制和管理。所以,进度控制和质量控制的合理规划,对施工工期,对施工质量,对施工经济效益,对建设工程投资都会产生很大的影响。
施工质量控制和进度控制的匀衡、协调是保证建设工程能如期,保质的最有效手段。在施工中无序地追求施工工期,不做科学的工期计算,就会在规划工期内以非正常施工速度赶工期,使工人劳动强度加大,质量目标难以操控,产生各类工程施工质量问題,严重的还会造成返工和不能返工的问题(原因工程施工一次性特点)。在施工中没有一个合理的施工工期规划,就无法保证在合理的时间内完成合格的建筑工程产品。
经过以上文字的阐述我们可以发现,只要合理安排工序,采取有效的赶工措施,严格控制施工质量,完全可以追回已延误的工期。
参考文献:
[1] 黄国红.浅谈施工项目中的进度与质量控制[J].经营管理者.2009(06).
[2] 高大伟. 建筑施工中进度与质量控制的作用与关系[J].科技创新导报.
2008(26).
[3] 骆汉宾.基于知识库的建筑工程施工质量控制点设置[J].施工技术.2006(06).
[4] 赖陈生.论建筑工程房屋施工质量管理及控制[J].建材与装饰(下旬刊). 2007(9).
[5] 周祥春. 探索建筑管理的项目控制措施[J]. 科技致富向导.2011(15).
[6] 周义,张菊. 浅谈建筑施工现场进度与质量[J]. 科技风. 2010(10).
关键字:进度;质量;工期;施工
Abstract: ShaPing united around the pumping station yinhe rebuilding project total duration for 18 months, time limit for target: in April 2012 ShaPing pump station before 12 all units have operating conditions, can undertake draining task. Now for the following main workshop of motor for port, abnormity complex structure, and built-in parts, bill, more difficult construction, design change much, time delay in 45 days. For the engineering construction project on time, play as soon as possible economic benefit, need to speed up the construction progress and recover has delayed time limit. And progress and quality is unified encompasses, will speed up the process by material supplies are tight, construction of the changed conditions, may affect the quality of the project.
Key word: progress; Quality; Time limit; construction
中图分类号:TV523 文献标识码:A 文章编号:
鹤山市沙坪联围泵站更新改造工程总工期为18个月,现因各种原因导致工期延误45天,为追回已延误的工期,需采取必要的赶工措施。天车梁结构施工是桥机安装调试的紧前工作,桥机安装调试是机组设备安装的紧前工作,所以为按期完成施工任务的关键结点在于加快天车梁结构的施工。
为了追回已延误的工期,根据劳动力强度,适度均衡地加快施工进度,不仅可以使计划工期得到合理的提前,而且还可以保证施工质量。严格控制质量,可以避免返工,进度则会加快;提高了承包商的施工效益,减少建设项目的经常性维护费用,延长工程使用年限,从而降低了投资成本,提高了施工单位的经济效益;反之则会因返工,造成工期延后,施工成本增加。
进度控制和质量控制在施工中的作用与关系
工程施工中最重要的是进度和质量,施工进度按最佳工期施工,可以在合理的时间内使施工企业产生更大的经济效益,使建设工程投资按计划工期交付使用,在预定的期限内尽早地收回投资。质量好可以减少工程施工返工;减少施工单位成本投入;减少建设单位的经常性维修;延长建设工程的使用年限,保证建设工程的稳定长效运营,提高投资效益,降低维护成本。因此必须掌握好进度控制和质量控制工作的要点,才能使工作做的有效、准确,发挥更好的经济效益。
而单方面地追求工期又会产生质量问题,会造成返工,会降低施工企业经济效益,影响到建设单位投资效益的尽快发挥。为了保证施工质量,偏面地精做细干又会使工期延后,成本增加。因此进度控制和质量控制规划设计,在施工中的关系是紧密的,只有认真地完成进度控制和质量控制规划设计的工作任务,才能保证在合理的时间内完成优良的建筑产品。
如何加快天车梁施工进度
合理的进度计划应体現资源的合理使用,工作面的合理安排,有序的进度计划有利于提高建设质量,有利于文明施工,有利于合理地缩短建设周期。而施工方案对工程进度有直接影响,在决策其适用时,不仅应分析技术的先进性和经济合理性,还应考虑其对进度的影响。尤其在工程进度滞后时,应分析是否存在施工技术、方法、环境、机械等方面的影响因素。
本工程项目主厂房有6跨12根天车梁,安装间有3跨6根天车梁,共18根天车梁,单根梁最长6150mm,最短5150mm,梁高900mm,每根重约6.0t,天车梁离电机层楼面高度为14.1m。原天车梁施工方案为现浇,为在关键线路工期上节省现浇混凝土龄期(28天),加快桥机安装及运行,为机组设备安装提供必要条件,故将天车梁现浇方案改为预制。
从主厂房空间考虑,天车梁预制免去了承重排架的搭设,可节省工期及节约成本,同时也能加快主厂房其他主体结构及砖砌体施工,避免装修工程与机组设备安装之间的交叉作业,从而加快了总工期的施工进度,对实现总工期提供了有力保证。
预制天车梁为低空作业,受不确定因素影响较小,场地容易布置,工作面容易开展,能够有效地组织人员、机械、材料形成流水作业,进行有序施工。天车梁共18根,集中主要材料、施工力量每天预制6根,3天即可完成。牛腿柱、天车梁强度都达到设计要求后,用50t履带吊将天车梁吊到牛腿柱上,履带吊需就两次位,就能完成全部吊装工作。
如何控制天车梁质量
建设工程质量不仅关系到建设工程的适用性、安全性、耐久性和建设项目的投资效益,同时也关系到人民群众生命和财产安全。所以应对建设工程质量实施有效控制,保证工程质量达到预期目标。
施工质量控制是整个建设工程项目质量控制的关键,施工是形成工程建设项目实体的阶段也是形成最终产品质量的重要阶段。所以,施工阶段的质量控制是工程建设项目质量控制的重点也是施工阶段要合理完成的重要因素。要控制好天车梁质量,需做到以下三点:
周密计划,要做到事前控制,在施工前,应认真审核设计图纸,做好技术资料准备工作,做好对钢筋、模板原材料的检查和控制工作。天车梁截面型式为梯形,所用主筋为Φ25,箍筋为¢10@100。在施工之前,应对模板的组装方法,每种钢筋的下料长度,布置间距向施工班组详细交底。还应努力做到对施工中可能发生的问题有一个预见性措施,才能在事前就把施工中的质量问题解决好,避免因没有做好事前控制造成建设工程施工质量返工的问题。
事中控制指在施工质量形成过程中,对影响施工质量的各种因素进行全面的动态控制。每一道工序,从天车梁模板支立到混凝土浇筑都有专业技术人员现场跟踪。事中控制的关键是坚持质量标准,控制的重点是工序质量、工作质量和质量控制点的控制。严格执行工序间的交接检查,认真执行“三检”制,即自检、互检、专检,对天车梁预埋件重要工程部位,项目总工应亲自进行技术复核,并进行实时监控。
事后控制即事后质量把关,以使不合格的工序或最终产品不得流入下道工序,控制的重点是发现施工质量方面的缺陷,并通过分析提出施工质量改进措施,保证质量处于受控状态。
现场检查质量的方法主要有目测法、实测法。
通过目测法,即通过感官对天车梁质量进行检查,其方法可概括为“看、摸、敲、照”。看、就是通过质量标准,对天车梁混凝土外观进行检查,看混凝土是否存在蜂窝麻面及露筋;摸、就是通过触摸手感进行检查,鉴别天车梁表面的光滑度;敲、就是应用敲击工具进行音感检查,用小锤敲击天车梁混凝土可判断混凝土是否密实;照、就是通过人工光源或反射光照射,检查天车梁翼缘处的细微部位。
通过实测法,即通过“靠、量、吊、套”取得实测数据与施工规范、质量标准要求的允许偏差值进行对照,以此判断质量是否符合要求。靠、就是用直尺、塞尺检查天车梁混凝土的平整度;量、就是用测量工具检查天车梁的结构尺寸,轴线、标高等的偏差;吊、就是用托线板以及线锤吊线检查天车梁的垂直度;套、就是方尺套方、辅以塞尺检查天车梁阴阳角的方正。
落实进度控制与质量控制对建设工程的作用
合格的建筑产品是在施工组织设计中对进度控制和质量控制进行科学合理的计算与规划,工程施工中进行有效的控制和管理。所以,进度控制和质量控制的合理规划,对施工工期,对施工质量,对施工经济效益,对建设工程投资都会产生很大的影响。
施工质量控制和进度控制的匀衡、协调是保证建设工程能如期,保质的最有效手段。在施工中无序地追求施工工期,不做科学的工期计算,就会在规划工期内以非正常施工速度赶工期,使工人劳动强度加大,质量目标难以操控,产生各类工程施工质量问題,严重的还会造成返工和不能返工的问题(原因工程施工一次性特点)。在施工中没有一个合理的施工工期规划,就无法保证在合理的时间内完成合格的建筑工程产品。
经过以上文字的阐述我们可以发现,只要合理安排工序,采取有效的赶工措施,严格控制施工质量,完全可以追回已延误的工期。
参考文献:
[1] 黄国红.浅谈施工项目中的进度与质量控制[J].经营管理者.2009(06).
[2] 高大伟. 建筑施工中进度与质量控制的作用与关系[J].科技创新导报.
2008(26).
[3] 骆汉宾.基于知识库的建筑工程施工质量控制点设置[J].施工技术.2006(06).
[4] 赖陈生.论建筑工程房屋施工质量管理及控制[J].建材与装饰(下旬刊). 2007(9).
[5] 周祥春. 探索建筑管理的项目控制措施[J]. 科技致富向导.2011(15).
[6] 周义,张菊. 浅谈建筑施工现场进度与质量[J]. 科技风. 2010(10).