论文部分内容阅读
【摘 要】近几年,全国许多地区都采用和逐渐推广了人工挖孔桩,其特有的大承载力优势得到了许多设计、施工单位的认可,确实是一种在软弱地基上经济适用的基础形式,但在施工中还存在着一些问题,我们在通过对采用人工挖孔桩基础的工程实践中,积累了一些经验,处理了一些特殊的问题。
【关键词】桩;基础;施工
Treatment of some special problems in hand-dug pile construction technology
Yan Cheng-jin
(1.Yanbian Huatong Road and Bridge Maintenance Engineering Co., Ltd Yanji Jilin 133000;
2.With highway in the dragon City management segmen Helongt Jilin 133500)
【Abstract】In recent years, many parts of the country and gradually extend the use of hand-dug piles, large carrying capacity of its unique advantages in a number of design and construction unit of recognition is really a weak foundation on the basis of affordable form, but in the construction there are still some problems, we dug through the pile of the artificial foundation engineering practice, has accumulated some experience dealing with some special problems.
【Key words】Pile; Basis; Construction
1. 工程概况
省道松老公路和龙至龙井段一级公路建设项目,起点位于吉林省和龙市北出口广场处,终点接龙井至延吉一级公路起点,其中05合同段海兰江大桥,桥梁中心桩号K29+487,与水流交交50°,汇水面积337.7km2,设计流量为457.7m3/s,设计流速3.63m/s,设计水位294.13m桥梁全长330.56m,桥宽31.6m,上不结构采用10孔30m预应力T型组合梁,下部结构采用柱式桥墩,肋板式桥台,基础均为挖孔桩基础。
2. 地下水
地下水是深基础施工中最常见的问题,它给人工挖孔桩施工带来许多困难。含水层中的水在开挖时破坏了其平衡状态,使周围的静态水充入桩孔内,从而影响了人工挖孔桩的正常施工,如果遇到动态水压土层施工,不仅开挖困难,连护壁混凝土也易被水压冲刷穿透,发生桩身质量问题。如遇到了细砂、粉砂土层,在压力水的作用下,也极易发生流砂和井漏现象。
2.1 地下水量不大时。
可选用潜水泵抽水,边抽水边开挖,成孔后及时浇筑相应段的混凝土护壁,然后继续下一段的施工。
2.2 水量较大时。
当用施工孔自身水泵抽水,也不易开挖时,应从施工顺序考虑,采取对周围桩孔同时抽水,以减少开挖孔内的涌水量,并采取交替循环施工的方法,组织安排合理,能达到很好的效果。
2.3 对不太深的挖孔桩。
可在场地四周合理布置统一的轻型管井降水分流,对基础平面占地较大时,也可增加降水管井的排数,一般即可解决。
2.4 抽水时环境影响。
有时施工周围环境特殊,一是抽出地下水进出时周围环境,基础设施等影响较多,不允许无限制抽水;二是周围有江沙、湖泊、沼泽等,不可能无限制达到抽水目的。因此在抽水前均要采取可靠的措施。处理这类问题最有效的方法是截断水源,封闭水路。桩孔较浅时,可用板桩封闭;桩孔较深时,用钻孔压力灌浆形成帷幕挡水,以保证在正常抽水时,达到正常开挖。
3. 流砂
人工挖孔在开挖时,如遇细砂,粉砂层地质时,再加上地下水的作用,极易形成流砂,严重时会发生井漏,造成质量事故,因此要采取有效可靠的措施。
3.1 流砂情况较轻时。
有效的方法是缩短这一循环的开挖深度,将正常的1m左右一段,缩短为0.5m以减少挖层孔壁的暴漏时间,及时进行护壁混凝土灌注。当孔壁塌落,有泥砂流入而不能形成桩孔时,可用纺织袋逐渐堆堵,形成桩孔的外壁,并控制保证内壁满足设计要求。
3.2 流砂情况较严重时。
常用的办法是下钢套筒,钢套筒与护壁用的钢模板相似,以孔外径为直径,可分成4~6段圆弧,再加上适当的助条,相互用螺栓或钢筋环扣链接,在开挖0.5左右,即可分片将套筒装入,深入孔底不少于0.2m,插入上部混凝土护壁外侧不小于0.5m,装后即支模浇注护壁混凝土,若放入套筒后流砂仍上涌,可采取突出挖出后即用混凝土封闭孔底的方法,待混凝土凝结后,将孔心部位的混凝土清凿以形成桩孔。也可用此种方法,应用到已完成的混凝土护壁的最下段钻大,使孔位倾斜至下层护壁以外,打入浆管,压力浇注水泥浆,使下部土壤硬些,提高周围及土壤的不透水性,以解决流砂现象。
4. 淤泥质土层
在遇到淤泥质土层等软弱土层时,一般可用木方、木板模板等支挡,并要缩短这一段的开挖深度,并及时浇注混凝土护壁,这次支挡的木方模板要沿周边打入底部不少于0.2m深,上部嵌入上段已浇好的混凝土护壁后面,可斜向放置,双排布置互相反向交叉,能达到很好的支挡效果。
5. 桩身混凝土的浇筑
5.1 消除水的影响。
5.1.1 孔底积水。
浇筑桩身混凝土主要应保证其符合设计强度,要保证混凝土的均匀性,密实性。因此要防止孔内积水影响混凝土的配合比和密实性。
浇筑前要抽干孔内积水,抽水的潜水泵要装设逆流阀,保证提出水泵时,不致使抽水管中残留水又流入桩孔内。如果孔内的水抽不干,提出水泵后,可用部分干拌混凝土混合料或干水泥铺入孔底,然后再浇筑混凝土。
如果孔底水量大,确实无法采取抽水的方法解决,桩身混凝土的施工应当采取水下浇筑施工工艺了。
5.1.2 保证桩身混凝土的密实性。
对孔壁渗水不容忽视,因桩柱混凝土浇筑时间较长,如果渗水过多,将影响混凝土质量,可在桩身混凝土浇筑前采用防水材料封闭渗漏部位。对于出水量较大的孔可用木楔打入,周围再用防水材料封闭,或在集中漏水部分嵌入泄水管,装上阀门,在施工桩孔时打开阀门让水流出,浇筑桩身混凝土时,再关闭,这样也可解决其影响桩身混凝土质量的问题。
5.2 保证桩身混凝土密实性。
桩身混凝土的密实性,是保证混凝土达到设计强度的必要条件,为保证桩身混凝土浇筑的密实性,一般采用串流筒下料及分层振捣浇筑的方法,其中的浇筑速度是关键,即力求在最短时间内完成一个桩身混凝土的浇筑,特别是在有地下水情况时,要求集中足够的混凝土短时间浇入,以便领先混凝土自身重量压住水流的渗入。
对于深度大于10m的桩身下部,可依靠混凝土自身的落差形成的冲击力及混凝土自身的重量的压力面使其密实,这部分混凝土即可不用振捣,经验证明,桩身混凝土能满足均匀性和密实性。而速度优于采用串流筒施工,对于桩身上部混凝土浇筑要采取正常的施工方法,因为一般上部很少有地下水影响,浇筑速度不必很快,也不能采用自由下落的特殊施工方法。
6. 合理安排施工顺序
合理安排人工挖孔桩的施工顺序,对减少施工难度起到重要作用,在施工方案中要认真统筹,根据实际情况合理安排。
在可能的条件下,先施工比较浅的桩孔,后施工深一些的桩孔。因为一般桩孔愈深,难度相对愈大,较浅的桩孔施工后,对上部土层的稳定起到加固的作用,也减少了深孔施工时的压力。在含水层或有动水压力的土层中施工,应先施工外围(或迎水部位)的桩孔,这部分桩孔混凝土护壁完成后,可保留少量桩孔先不浇筑桩身混凝土,而做為排水井,以方便其它孔位的施工。保证了桩孔的施工速度和成孔质量。
7. 实现效果
经过对人工挖孔桩实施上述的技术控制,使其达到了预期的效果,在对44跟成桩进行的静载(堆载)试验证明,人工挖孔桩满足设计要求,达到了质量检验评定标准的优良等级。
[文章编号]1006-7619(2011)01-10-012
【关键词】桩;基础;施工
Treatment of some special problems in hand-dug pile construction technology
Yan Cheng-jin
(1.Yanbian Huatong Road and Bridge Maintenance Engineering Co., Ltd Yanji Jilin 133000;
2.With highway in the dragon City management segmen Helongt Jilin 133500)
【Abstract】In recent years, many parts of the country and gradually extend the use of hand-dug piles, large carrying capacity of its unique advantages in a number of design and construction unit of recognition is really a weak foundation on the basis of affordable form, but in the construction there are still some problems, we dug through the pile of the artificial foundation engineering practice, has accumulated some experience dealing with some special problems.
【Key words】Pile; Basis; Construction
1. 工程概况
省道松老公路和龙至龙井段一级公路建设项目,起点位于吉林省和龙市北出口广场处,终点接龙井至延吉一级公路起点,其中05合同段海兰江大桥,桥梁中心桩号K29+487,与水流交交50°,汇水面积337.7km2,设计流量为457.7m3/s,设计流速3.63m/s,设计水位294.13m桥梁全长330.56m,桥宽31.6m,上不结构采用10孔30m预应力T型组合梁,下部结构采用柱式桥墩,肋板式桥台,基础均为挖孔桩基础。
2. 地下水
地下水是深基础施工中最常见的问题,它给人工挖孔桩施工带来许多困难。含水层中的水在开挖时破坏了其平衡状态,使周围的静态水充入桩孔内,从而影响了人工挖孔桩的正常施工,如果遇到动态水压土层施工,不仅开挖困难,连护壁混凝土也易被水压冲刷穿透,发生桩身质量问题。如遇到了细砂、粉砂土层,在压力水的作用下,也极易发生流砂和井漏现象。
2.1 地下水量不大时。
可选用潜水泵抽水,边抽水边开挖,成孔后及时浇筑相应段的混凝土护壁,然后继续下一段的施工。
2.2 水量较大时。
当用施工孔自身水泵抽水,也不易开挖时,应从施工顺序考虑,采取对周围桩孔同时抽水,以减少开挖孔内的涌水量,并采取交替循环施工的方法,组织安排合理,能达到很好的效果。
2.3 对不太深的挖孔桩。
可在场地四周合理布置统一的轻型管井降水分流,对基础平面占地较大时,也可增加降水管井的排数,一般即可解决。
2.4 抽水时环境影响。
有时施工周围环境特殊,一是抽出地下水进出时周围环境,基础设施等影响较多,不允许无限制抽水;二是周围有江沙、湖泊、沼泽等,不可能无限制达到抽水目的。因此在抽水前均要采取可靠的措施。处理这类问题最有效的方法是截断水源,封闭水路。桩孔较浅时,可用板桩封闭;桩孔较深时,用钻孔压力灌浆形成帷幕挡水,以保证在正常抽水时,达到正常开挖。
3. 流砂
人工挖孔在开挖时,如遇细砂,粉砂层地质时,再加上地下水的作用,极易形成流砂,严重时会发生井漏,造成质量事故,因此要采取有效可靠的措施。
3.1 流砂情况较轻时。
有效的方法是缩短这一循环的开挖深度,将正常的1m左右一段,缩短为0.5m以减少挖层孔壁的暴漏时间,及时进行护壁混凝土灌注。当孔壁塌落,有泥砂流入而不能形成桩孔时,可用纺织袋逐渐堆堵,形成桩孔的外壁,并控制保证内壁满足设计要求。
3.2 流砂情况较严重时。
常用的办法是下钢套筒,钢套筒与护壁用的钢模板相似,以孔外径为直径,可分成4~6段圆弧,再加上适当的助条,相互用螺栓或钢筋环扣链接,在开挖0.5左右,即可分片将套筒装入,深入孔底不少于0.2m,插入上部混凝土护壁外侧不小于0.5m,装后即支模浇注护壁混凝土,若放入套筒后流砂仍上涌,可采取突出挖出后即用混凝土封闭孔底的方法,待混凝土凝结后,将孔心部位的混凝土清凿以形成桩孔。也可用此种方法,应用到已完成的混凝土护壁的最下段钻大,使孔位倾斜至下层护壁以外,打入浆管,压力浇注水泥浆,使下部土壤硬些,提高周围及土壤的不透水性,以解决流砂现象。
4. 淤泥质土层
在遇到淤泥质土层等软弱土层时,一般可用木方、木板模板等支挡,并要缩短这一段的开挖深度,并及时浇注混凝土护壁,这次支挡的木方模板要沿周边打入底部不少于0.2m深,上部嵌入上段已浇好的混凝土护壁后面,可斜向放置,双排布置互相反向交叉,能达到很好的支挡效果。
5. 桩身混凝土的浇筑
5.1 消除水的影响。
5.1.1 孔底积水。
浇筑桩身混凝土主要应保证其符合设计强度,要保证混凝土的均匀性,密实性。因此要防止孔内积水影响混凝土的配合比和密实性。
浇筑前要抽干孔内积水,抽水的潜水泵要装设逆流阀,保证提出水泵时,不致使抽水管中残留水又流入桩孔内。如果孔内的水抽不干,提出水泵后,可用部分干拌混凝土混合料或干水泥铺入孔底,然后再浇筑混凝土。
如果孔底水量大,确实无法采取抽水的方法解决,桩身混凝土的施工应当采取水下浇筑施工工艺了。
5.1.2 保证桩身混凝土的密实性。
对孔壁渗水不容忽视,因桩柱混凝土浇筑时间较长,如果渗水过多,将影响混凝土质量,可在桩身混凝土浇筑前采用防水材料封闭渗漏部位。对于出水量较大的孔可用木楔打入,周围再用防水材料封闭,或在集中漏水部分嵌入泄水管,装上阀门,在施工桩孔时打开阀门让水流出,浇筑桩身混凝土时,再关闭,这样也可解决其影响桩身混凝土质量的问题。
5.2 保证桩身混凝土密实性。
桩身混凝土的密实性,是保证混凝土达到设计强度的必要条件,为保证桩身混凝土浇筑的密实性,一般采用串流筒下料及分层振捣浇筑的方法,其中的浇筑速度是关键,即力求在最短时间内完成一个桩身混凝土的浇筑,特别是在有地下水情况时,要求集中足够的混凝土短时间浇入,以便领先混凝土自身重量压住水流的渗入。
对于深度大于10m的桩身下部,可依靠混凝土自身的落差形成的冲击力及混凝土自身的重量的压力面使其密实,这部分混凝土即可不用振捣,经验证明,桩身混凝土能满足均匀性和密实性。而速度优于采用串流筒施工,对于桩身上部混凝土浇筑要采取正常的施工方法,因为一般上部很少有地下水影响,浇筑速度不必很快,也不能采用自由下落的特殊施工方法。
6. 合理安排施工顺序
合理安排人工挖孔桩的施工顺序,对减少施工难度起到重要作用,在施工方案中要认真统筹,根据实际情况合理安排。
在可能的条件下,先施工比较浅的桩孔,后施工深一些的桩孔。因为一般桩孔愈深,难度相对愈大,较浅的桩孔施工后,对上部土层的稳定起到加固的作用,也减少了深孔施工时的压力。在含水层或有动水压力的土层中施工,应先施工外围(或迎水部位)的桩孔,这部分桩孔混凝土护壁完成后,可保留少量桩孔先不浇筑桩身混凝土,而做為排水井,以方便其它孔位的施工。保证了桩孔的施工速度和成孔质量。
7. 实现效果
经过对人工挖孔桩实施上述的技术控制,使其达到了预期的效果,在对44跟成桩进行的静载(堆载)试验证明,人工挖孔桩满足设计要求,达到了质量检验评定标准的优良等级。
[文章编号]1006-7619(2011)01-10-012