三峡工程建设采用“三期导流、明渠通航”的施工导流方案,大江截流最大水深60 m、实测最大流量11600 m~3 s~(-1)大,河床深厚覆盖层达20 m,截流过程潜在堤头坍塌风险;明渠截流最大设计流量10300 m~3 s~(-1)、落差4.11 m、龙口流速7 m s~(-1)、水深20 m,明渠基面平整光滑、不利抛投料稳定,截流进占抛投强度11.46万立方米/日;大江截流和明渠截流均需兼顾施工期通航要求.大江截流采用“预平抛垫底,上游单戗立堵、双向进占,下游尾随进占”的截流方案;导流明渠截流采用“垫底加糙、双戗立堵、上游双向进占、下游单向进占”的方案.大江截流和明渠截流的综合困难程度乃世界截流史所罕见,两次截流的成功实施,标志中国河道截流技术跻身世界领先地位.
The construction of the Three Gorges Project adopts the construction diversion scheme with “Three-stage diversion and open channel navigation”. The maximum water depth of the major river closure is 60 m, the maximum measured flow is 11600 m -3 s -1, and the deep bed cover reaches 20 m , The risk of collapse of potential embankment in river closure process; the maximum design flow of open channel closure is 10300 m ~ 3 s -1, the gap is 4.11 m, the flow velocity of Longkou is 7 ms -1, water depth is 20 m, the surface of open channel is smooth and unfavorable Throwing material stability, interception take-up throwing strength 114,600 cubic meters / day; river closure and open channel closure must take into account the navigation requirements during construction. River closure using “pre-set to throw the bottom, the upstream single Li Li plug, Diversion channel closure using ”bottom plus rough, double 戗 vertical plug, the upstream two-way access, the downstream one-way access to " program.The comprehensive river closure and open channel closure of the degree of difficulty is the closure of the world history Rare and successful implementation of the two river closure marks China’s river closure technology among the highest in the world.