论文部分内容阅读
【摘 要】措通过对盖孜河近期防洪规划上、中、下游防洪工程的布置和工程措施的确定,总结出在今后进行防洪规划或防洪工程设计时要注意的问题,为类似工程在设计时在节约投资方面提供一些借鉴的经验。
【关键词】防洪规划;工程;措施;探讨;盖孜河
Discussion of Gaizi River recent flood control planning of Engineering Measures
Chen Qiang-lun
(Kashi Gaizi River Management Office Engineering Section Kashi Xinjiang 844000)
【Abstract】The measures recently by Gaizi River flood control planning, the middle and lower reaches of the layout of flood control works and engineering measures to identify, summed up flood protection in the future planning or design of flood control projects should pay attention to the problem, when in the design of similar projects saving investment experience to provide some reference.
【Key words】Flood control planning; Project; Measures; Discussion; Gaizi River
1. 盖孜河流域概况
盖孜河流域位于新疆维吾尔自治区的西南部,塔里木盆地的西部边缘,为我国内陆河-喀什噶尔河水系的源流之一。盖孜河源流在布仑口以上主要有两源,一源发源于沙里阔勒岭东北麓,名曰木吉河,全长160Km,称为西北源;另一源为慕士塔格阿塔冰山的东西两侧,名曰喀拉库里河,全长71 Km,称为南源;两源于布仑口山间盆地汇合,流入盖孜峡谷。流域范围介于东经73°42′~77°08′,北纬38°10′~39°10′之间,流域总面积18542.55 Km2,其中山区面积10712 Km2,平原面积7830.55 Km2。
盖孜河在布仑口以上为上游河段长160Km,布仑口至吐木休克出山口为中游河段长76.7Km,吐木休克山口至风口闸为下游河段,长130.3Km。风口闸至卡木尕克闸河道基本渠系化。
盖孜河自上而下沿途又先后汇入了黑水沟、维他克河等多条支流,年径流量由5.8×108 m3增加到11.83×108m3。经吐木休克山口进入平原灌区,在乌帕尔处又接纳季节性支流乌鲁瓦提、且木干等几条河沟的水量,其中乌鲁瓦提河1958年观测记载年径流量为1.165×108m3。在三道桥以下称为岳普湖河;最后在岳普湖县境内以东消失。
2. 洪灾情况及防洪工程现状
盖孜河由于目前盖孜河山区尚无控制性水库工程,干流和支流均无水库控制调节巨大的洪峰,洪峰直接进入平原区河段,使平原灌区形成频繁的大范围的灾害。从克州阿克陶维他镇至岳普湖县铁力木乡约159.50Km公里长的河段上形成的防洪险工段达50多处。据统计从1980~2002年的23年间,盖孜河发生洪灾12年。
多年来盖孜河流域各族人民写洪水灾害进行了不懈的斗争,修建堤坝,改建引水龙口。加国险工段。取得一定的成效。塔什米力克渠首、三道桥枢纽、合理闸等被改建为永久性的引水枢纽。中下游河段修筑堤防及护岸工程60余公里,对改善防洪条件发挥了重要作用。但因资金困难,绝大部分堤防护岸工程是临时性的梢木土石主程,多采用梢木卵石压坝,梢料草皮筑堤或用编织袋装砂压梢坝。少数采用铅丝石笼护坝。工程标准低,使用周期短。抗洪能力差。目前盖孜河出山口的河道无重大灾害的洪峰流量约为100 m3/s,尚达不到抗御5年一遇洪水水平。每年汛期需投入青壮劳力8000~10000人防洪,据l980!2001年年统计平均年耗用劳力8.50万工,年消耗材料、人工及机械运输费用1501.75余万元。防洪工料用款使全流域人均年负担近百花。汛期处在夏收夏管大忙季节,数万青壮劳力在防汛第一线劳动近两个月,对农业生产影响极大,粗估农民由于防洪岁修耽误田间管理减少农业收入的间接损失在2000万元以上,每户农民的直接负担和间接付出达610元/年。因此使灌区农民收入减少。
3. 洪水的成因和类型
盖孜河、维他克河发源于帕米尔高原的冰峰雪岭,河源分布着大量的大陆型冰川、永久性积雪和季节性积雪。其中盖孜河克勒克站以上冰川面积1439.6Km2,冰川覆盖度为14.8%,维他克河以上冰川面积为227.3 Km2,冰川覆盖率竟高达45.7%,3500m以上的山区终年降水多以雪的形式降落,这些冰川和永久性积雪为消融性洪水提供了丰富的物质条件。每年夏季,随着气温的上升,冰雪消融补给河流,每次大的升温过程,必然伴随着消融洪水的发生。消融型河流最大特点是水量的季节变化很大,全年有70%以上的水量集中在洪水期(6~9月)。一般在七月中旬至八月下旬出现较强的洪峰。当出现降水天气时,冰雪消融往往减少,这是因为高寒山区一次降水伴随着一次降温过程,而且多为固态降水,冰面为新雪覆盖,反射率增大,消融明显减弱,致使流量锐减。如遇到1500~3500mm中低山区大降水甚至暴雨,则会形成盖孜河暴雨洪水。此类洪水在克勒克站以下,维他克河以及乌帕尔地区经常发生。分析盖孜河干流克勒克站实测洪峰系列(1959~2002)44年,除1977年年最大洪峰流量发生在6月下旬外,其余洪峰均发生在7月至8月之间,最晚发生的时间为1987年8月24日,且这44年中发生的洪峰流量除1999年和2002年年最大洪峰流量为混合型洪水外其余年份年最大洪峰流量均为消融水洪水。分析维他克站实测洪峰系列(1957~2002)39年,其中暴雨洪水6场,其余29场均属消融型洪水。分析克勒克站、维他克站历史调查洪水,其中克勒克站1926年1010m3/s流量洪水成因不明,其余4场洪水均属于暴雨洪水。经分析盖孜河洪水主要并存有以下四种类型:
(1)消融型洪水。
消融型洪水变化过程较平缓,洪峰出现在7~8月,与升温过程关系密切,洪水过程有明显日变化,但峰谷相差不很大,洪水历时较长,涨洪平缓,峰型多为复式,洪水波沿程衰减较小。
(2)暴雨型洪水。
暴雨型发生在5~9月,洪峰年际变化较大,洪水历时较短,洪水过程单一,陡涨陡落,洪水波沿程衰减较大,此类洪水洪峰流量特别高,但洪量并不大。
(3)暴雨——消融混合型洪水。
暴雨——消融混合型洪水是两类不同类型洪水的叠加,从理论上讲该型洪水的特征取决于参与叠加的两类洪水的特定的生成条件、规模洪水遭遇的时机等多方面的因素。因而场次洪水千差万别,较单型洪水复杂,不宜一概而论。
混合型洪水的最主要特征是在有规律的流量日变化过程上叠加一尖瘦的降水洪峰。此类洪水峰高量大、历时长,对防洪对象最具有威胁。
(4)泥石流堵塞型。
由区域持续降雨,当雨强较大,流域超渗产流形成暴雨洪水,洪水来时泥石流俱下堵塞河道,上游形成水库,山坡径流继续汇入,大水漫“坝”溃决下泄,成陡涨陡落的洪峰。该洪水历时短,洪峰高,洪量不大,洪峰过程从起涨到峰顶落平,似大坝决口之状。自80年代,大陆冰川在历史气候变暖条件下强烈退宿,形成冰崩、雪崩及冰湖溃决,当冰碛沟谷沉积大量粘土、砂砾时,导致泥石流发生。
4. 防洪工程护岸结构形式的确定
盖孜河防洪工程保护对象主要有一般城镇、乡村、工矿企业、交通桥、水库、渠首、水电站、灌溉渠道等,首先要依据国家技术监督局、中华人民共和国建设部 1994~06.02发布的中华人民共和国防洪标准,对防洪工程保护对象进行防洪标准的确定,对保护对象进行其相应的防洪标准的设计。因此,应针对河床性质、洪水特点及保护 对象的不同,采取不同的结构形式和工程措施,以导流和顺流相结合,永久性工程和临时性工程相结合,重点治理和分散 保护相结合。在顺势利导时,应不与河争道,要照顾上下游和左右岸,绝对不能顾此失彼。
在防洪工程的结构形式上,要考虑河床的质地、河床的纵坡、天然建筑材料等因素。现分段对盖孜河防洪工程的结构形式选取作如下介绍:
(1)维他克河入河口——卡拉瓦克河段。
维他克河入河口至红山河段,该段属于盖孜河从山区到平原的过渡段,全长17.3Km,河床宽780~1300m,卵砾石河床,河道纵坡大,为1/52~1/100,河水流速大,河段河床纵坡陡。盖孜河在红山处开始分叉,分为喀拉克其克北支和南支两条河流,到卡拉瓦克后又汇合在一起。北支全长25.7Km,河床宽250~800m,南支全长24.7Km,河床宽约300~600m。河床为砂卵石,河道纵坡大,为1/200~1/500,主流不稳定,左右摆动,河弯处冲刷河岸严重。此段为盖孜河近期防洪规划的上游段,河床为砂卵石,砾石石料丰富,因纵坡陡,冲刷严重,采用顺坝及短丁坝相结合的卵石坝体,砼及浆砌卵石护面形式,以增强坝体的防冲、防磨能力。挑水坝护岸工程,挑水坝长度要适宜,一般不超过60米,与岸边要有一定长度的衔接段,挑流角度30。~40。之间。顺坝则应紧贴岸基,不能建在河床内,并应有适当的防冲曲率,做到顺势利导。
浆砌石丁坝、顺坝结构形式断面如下:顶冲段为砂卵石筑堤,浆砌石护坡;堤顶宽度为5m,地面以上边坡采用1:1.5,浆砌石厚度30~50cm,地面以下的边坡采用1:1,浆砌石厚度50~150cm;采用一系列顺坝、丁坝形成治导线,丁坝为非淹没下挑式。由于凹岸水流顶冲强烈,不同流量的顶冲部位不同,小水上堤,大水下挫,因此布置丁坝应遵循上疏下密、上顺下挑的原则。
(2)卡拉瓦克(南北支汇合口处)—合理闸河段。
河道长56Km,河床宽300~1200m,粉细砂河床,两岸为砂土、亚砂土,纵坡为1/500~1/800,河道游荡性大,河床在汛期冲刷下切,汛末又淤积回升,基本处于冲淤平衡,两岸多有淘刷。此段为盖孜河近期防洪规划的中游段,河床为粉细砂,砾石石料缺乏,河床纵坡变缓,但河床和两岸的土质不耐冲刷,河床在汛期冲刷下切严重。此段在防洪标准高的重要防护段,采用防洪工程的结构形式为,基础设抓斗槽孔砼防护,护坡采用砼板防护。在防洪标准较高的较重要防护段,采用防洪工程的结构形式为,以电杆冲沉柱压铅丝笼作丁坝,混凝土板护坡顺坝防护。在防洪标准一般的防护段,采用防洪工程的结构形式为,坝基以铅丝笼装石,顺坝护面以铅丝笼装石护坡。
抓斗槽孔混凝土板护坡顺坝结构形式断面如下:采用混凝土护坡顺坝,堤顶宽度为5m,边坡1:2,混凝土板厚度为13cm,基础采用抓斗槽孔砼护基。丁坝采用钢筋笼抛石。
混凝土板护坡顺坝结构形式断面如下:混凝土护坡顺坝,其堤顶宽度为5m,边坡1:2,混凝土板厚度为13~15cm,坡底根据护堤先护滩的道理,在河床表面筑一条宽5m的平台,平台混凝土板厚度为30cm,两边设深50cm、宽30cm的齿墙,基础采用大粒径的混凝土骨料,边坡1:2,护坡混凝土板厚度为30cm,虽有平台,基础不可太浅。
钢筋混凝土管冲沉丁坝结构形式断面如下:在粉细沙河床段,重要的防洪工程可采用水力冲沉将特制钢筋混凝土管作骨架,水力冲沉钢筋混凝土管设两排,两排钢筋混凝土管之间的间距为5米,每两米设一根钢筋混凝土管,钢筋混凝土管上部布设钢筋,用砼帽梁的型式把各钢筋混凝土管连结成一个整体,两排钢筋混凝土管之间用铅丝笼抛石和树梢填充。
(3)合理闸-夏甫阔旦泄洪闸河段。
河道长26Km,河床宽为370~620m。粉细砂河床,两岸为砂土、亚砂土,纵坡为1/800~1/1000。夏甫阔旦泄洪闸以下的河道已经渠系化,渠系化的河道不考虑防洪问题。此段河道防洪工程的布置,以护岸为主,重点设防,只在有建筑物的地方护岸。此段为盖孜河近期防洪规划的下游段,河床为粉细砂,砾石石料缺乏。此段在防洪标准高的重要防护段,采用防洪工程的结构形式为,以电杆冲沉柱压铅丝笼作丁坝,以土坝为顺坝,混凝土板护坡顺坝防护。在防洪标准一般的的防护段,采用防洪工程的结构形式为,以土坝为顺坝,顺坝以铅丝笼装石护面,坝基以铅丝笼装石护基。
5. 结语
通过对盖孜河近期防洪规划中工程措施的设计,有以下几点体会:(1)在今后防洪工程的规划和设计时,依据国家技术监督局、中华人民共和国建设部 1994- 06.02发布的中华人民共和国防洪标准,对防洪工程保护对象进行防洪标准的确定,对保护对象进行其相应的防洪标准的设计;(2)在设计防洪工程的结构形式前,仔细勘测要修建工程处河床的质地、河床的纵坡、流量、天然建筑材料等情况,在设计时要充分考虑以上因素,才能使设计出来的防洪工程的结构形式又节约又安全;(3)根据已勘测的河床质地、河床纵坡、流量等条件,详细计算防洪工程的冲刷深度,并要调查河道上下游已建的防洪工程的基础深度,和大洪水来时对现有防洪工程实际的淘刷深度,综合比较确定防洪工程的冲刷深度,这样设计出来的防洪工程的基础才能即节约又安全;(4)充分借鉴河道上下游已建防洪工程的成功经验,使设计的防洪工程少走弯路,更适合于本河道的具体情况。
[文章编号]1006-7619(2010)04-26-359
[作者简介]陈强伦(1964-),男,新疆喀什地区盖孜河管理处工程科副科长。
【关键词】防洪规划;工程;措施;探讨;盖孜河
Discussion of Gaizi River recent flood control planning of Engineering Measures
Chen Qiang-lun
(Kashi Gaizi River Management Office Engineering Section Kashi Xinjiang 844000)
【Abstract】The measures recently by Gaizi River flood control planning, the middle and lower reaches of the layout of flood control works and engineering measures to identify, summed up flood protection in the future planning or design of flood control projects should pay attention to the problem, when in the design of similar projects saving investment experience to provide some reference.
【Key words】Flood control planning; Project; Measures; Discussion; Gaizi River
1. 盖孜河流域概况
盖孜河流域位于新疆维吾尔自治区的西南部,塔里木盆地的西部边缘,为我国内陆河-喀什噶尔河水系的源流之一。盖孜河源流在布仑口以上主要有两源,一源发源于沙里阔勒岭东北麓,名曰木吉河,全长160Km,称为西北源;另一源为慕士塔格阿塔冰山的东西两侧,名曰喀拉库里河,全长71 Km,称为南源;两源于布仑口山间盆地汇合,流入盖孜峡谷。流域范围介于东经73°42′~77°08′,北纬38°10′~39°10′之间,流域总面积18542.55 Km2,其中山区面积10712 Km2,平原面积7830.55 Km2。
盖孜河在布仑口以上为上游河段长160Km,布仑口至吐木休克出山口为中游河段长76.7Km,吐木休克山口至风口闸为下游河段,长130.3Km。风口闸至卡木尕克闸河道基本渠系化。
盖孜河自上而下沿途又先后汇入了黑水沟、维他克河等多条支流,年径流量由5.8×108 m3增加到11.83×108m3。经吐木休克山口进入平原灌区,在乌帕尔处又接纳季节性支流乌鲁瓦提、且木干等几条河沟的水量,其中乌鲁瓦提河1958年观测记载年径流量为1.165×108m3。在三道桥以下称为岳普湖河;最后在岳普湖县境内以东消失。
2. 洪灾情况及防洪工程现状
盖孜河由于目前盖孜河山区尚无控制性水库工程,干流和支流均无水库控制调节巨大的洪峰,洪峰直接进入平原区河段,使平原灌区形成频繁的大范围的灾害。从克州阿克陶维他镇至岳普湖县铁力木乡约159.50Km公里长的河段上形成的防洪险工段达50多处。据统计从1980~2002年的23年间,盖孜河发生洪灾12年。
多年来盖孜河流域各族人民写洪水灾害进行了不懈的斗争,修建堤坝,改建引水龙口。加国险工段。取得一定的成效。塔什米力克渠首、三道桥枢纽、合理闸等被改建为永久性的引水枢纽。中下游河段修筑堤防及护岸工程60余公里,对改善防洪条件发挥了重要作用。但因资金困难,绝大部分堤防护岸工程是临时性的梢木土石主程,多采用梢木卵石压坝,梢料草皮筑堤或用编织袋装砂压梢坝。少数采用铅丝石笼护坝。工程标准低,使用周期短。抗洪能力差。目前盖孜河出山口的河道无重大灾害的洪峰流量约为100 m3/s,尚达不到抗御5年一遇洪水水平。每年汛期需投入青壮劳力8000~10000人防洪,据l980!2001年年统计平均年耗用劳力8.50万工,年消耗材料、人工及机械运输费用1501.75余万元。防洪工料用款使全流域人均年负担近百花。汛期处在夏收夏管大忙季节,数万青壮劳力在防汛第一线劳动近两个月,对农业生产影响极大,粗估农民由于防洪岁修耽误田间管理减少农业收入的间接损失在2000万元以上,每户农民的直接负担和间接付出达610元/年。因此使灌区农民收入减少。
3. 洪水的成因和类型
盖孜河、维他克河发源于帕米尔高原的冰峰雪岭,河源分布着大量的大陆型冰川、永久性积雪和季节性积雪。其中盖孜河克勒克站以上冰川面积1439.6Km2,冰川覆盖度为14.8%,维他克河以上冰川面积为227.3 Km2,冰川覆盖率竟高达45.7%,3500m以上的山区终年降水多以雪的形式降落,这些冰川和永久性积雪为消融性洪水提供了丰富的物质条件。每年夏季,随着气温的上升,冰雪消融补给河流,每次大的升温过程,必然伴随着消融洪水的发生。消融型河流最大特点是水量的季节变化很大,全年有70%以上的水量集中在洪水期(6~9月)。一般在七月中旬至八月下旬出现较强的洪峰。当出现降水天气时,冰雪消融往往减少,这是因为高寒山区一次降水伴随着一次降温过程,而且多为固态降水,冰面为新雪覆盖,反射率增大,消融明显减弱,致使流量锐减。如遇到1500~3500mm中低山区大降水甚至暴雨,则会形成盖孜河暴雨洪水。此类洪水在克勒克站以下,维他克河以及乌帕尔地区经常发生。分析盖孜河干流克勒克站实测洪峰系列(1959~2002)44年,除1977年年最大洪峰流量发生在6月下旬外,其余洪峰均发生在7月至8月之间,最晚发生的时间为1987年8月24日,且这44年中发生的洪峰流量除1999年和2002年年最大洪峰流量为混合型洪水外其余年份年最大洪峰流量均为消融水洪水。分析维他克站实测洪峰系列(1957~2002)39年,其中暴雨洪水6场,其余29场均属消融型洪水。分析克勒克站、维他克站历史调查洪水,其中克勒克站1926年1010m3/s流量洪水成因不明,其余4场洪水均属于暴雨洪水。经分析盖孜河洪水主要并存有以下四种类型:
(1)消融型洪水。
消融型洪水变化过程较平缓,洪峰出现在7~8月,与升温过程关系密切,洪水过程有明显日变化,但峰谷相差不很大,洪水历时较长,涨洪平缓,峰型多为复式,洪水波沿程衰减较小。
(2)暴雨型洪水。
暴雨型发生在5~9月,洪峰年际变化较大,洪水历时较短,洪水过程单一,陡涨陡落,洪水波沿程衰减较大,此类洪水洪峰流量特别高,但洪量并不大。
(3)暴雨——消融混合型洪水。
暴雨——消融混合型洪水是两类不同类型洪水的叠加,从理论上讲该型洪水的特征取决于参与叠加的两类洪水的特定的生成条件、规模洪水遭遇的时机等多方面的因素。因而场次洪水千差万别,较单型洪水复杂,不宜一概而论。
混合型洪水的最主要特征是在有规律的流量日变化过程上叠加一尖瘦的降水洪峰。此类洪水峰高量大、历时长,对防洪对象最具有威胁。
(4)泥石流堵塞型。
由区域持续降雨,当雨强较大,流域超渗产流形成暴雨洪水,洪水来时泥石流俱下堵塞河道,上游形成水库,山坡径流继续汇入,大水漫“坝”溃决下泄,成陡涨陡落的洪峰。该洪水历时短,洪峰高,洪量不大,洪峰过程从起涨到峰顶落平,似大坝决口之状。自80年代,大陆冰川在历史气候变暖条件下强烈退宿,形成冰崩、雪崩及冰湖溃决,当冰碛沟谷沉积大量粘土、砂砾时,导致泥石流发生。
4. 防洪工程护岸结构形式的确定
盖孜河防洪工程保护对象主要有一般城镇、乡村、工矿企业、交通桥、水库、渠首、水电站、灌溉渠道等,首先要依据国家技术监督局、中华人民共和国建设部 1994~06.02发布的中华人民共和国防洪标准,对防洪工程保护对象进行防洪标准的确定,对保护对象进行其相应的防洪标准的设计。因此,应针对河床性质、洪水特点及保护 对象的不同,采取不同的结构形式和工程措施,以导流和顺流相结合,永久性工程和临时性工程相结合,重点治理和分散 保护相结合。在顺势利导时,应不与河争道,要照顾上下游和左右岸,绝对不能顾此失彼。
在防洪工程的结构形式上,要考虑河床的质地、河床的纵坡、天然建筑材料等因素。现分段对盖孜河防洪工程的结构形式选取作如下介绍:
(1)维他克河入河口——卡拉瓦克河段。
维他克河入河口至红山河段,该段属于盖孜河从山区到平原的过渡段,全长17.3Km,河床宽780~1300m,卵砾石河床,河道纵坡大,为1/52~1/100,河水流速大,河段河床纵坡陡。盖孜河在红山处开始分叉,分为喀拉克其克北支和南支两条河流,到卡拉瓦克后又汇合在一起。北支全长25.7Km,河床宽250~800m,南支全长24.7Km,河床宽约300~600m。河床为砂卵石,河道纵坡大,为1/200~1/500,主流不稳定,左右摆动,河弯处冲刷河岸严重。此段为盖孜河近期防洪规划的上游段,河床为砂卵石,砾石石料丰富,因纵坡陡,冲刷严重,采用顺坝及短丁坝相结合的卵石坝体,砼及浆砌卵石护面形式,以增强坝体的防冲、防磨能力。挑水坝护岸工程,挑水坝长度要适宜,一般不超过60米,与岸边要有一定长度的衔接段,挑流角度30。~40。之间。顺坝则应紧贴岸基,不能建在河床内,并应有适当的防冲曲率,做到顺势利导。
浆砌石丁坝、顺坝结构形式断面如下:顶冲段为砂卵石筑堤,浆砌石护坡;堤顶宽度为5m,地面以上边坡采用1:1.5,浆砌石厚度30~50cm,地面以下的边坡采用1:1,浆砌石厚度50~150cm;采用一系列顺坝、丁坝形成治导线,丁坝为非淹没下挑式。由于凹岸水流顶冲强烈,不同流量的顶冲部位不同,小水上堤,大水下挫,因此布置丁坝应遵循上疏下密、上顺下挑的原则。
(2)卡拉瓦克(南北支汇合口处)—合理闸河段。
河道长56Km,河床宽300~1200m,粉细砂河床,两岸为砂土、亚砂土,纵坡为1/500~1/800,河道游荡性大,河床在汛期冲刷下切,汛末又淤积回升,基本处于冲淤平衡,两岸多有淘刷。此段为盖孜河近期防洪规划的中游段,河床为粉细砂,砾石石料缺乏,河床纵坡变缓,但河床和两岸的土质不耐冲刷,河床在汛期冲刷下切严重。此段在防洪标准高的重要防护段,采用防洪工程的结构形式为,基础设抓斗槽孔砼防护,护坡采用砼板防护。在防洪标准较高的较重要防护段,采用防洪工程的结构形式为,以电杆冲沉柱压铅丝笼作丁坝,混凝土板护坡顺坝防护。在防洪标准一般的防护段,采用防洪工程的结构形式为,坝基以铅丝笼装石,顺坝护面以铅丝笼装石护坡。
抓斗槽孔混凝土板护坡顺坝结构形式断面如下:采用混凝土护坡顺坝,堤顶宽度为5m,边坡1:2,混凝土板厚度为13cm,基础采用抓斗槽孔砼护基。丁坝采用钢筋笼抛石。
混凝土板护坡顺坝结构形式断面如下:混凝土护坡顺坝,其堤顶宽度为5m,边坡1:2,混凝土板厚度为13~15cm,坡底根据护堤先护滩的道理,在河床表面筑一条宽5m的平台,平台混凝土板厚度为30cm,两边设深50cm、宽30cm的齿墙,基础采用大粒径的混凝土骨料,边坡1:2,护坡混凝土板厚度为30cm,虽有平台,基础不可太浅。
钢筋混凝土管冲沉丁坝结构形式断面如下:在粉细沙河床段,重要的防洪工程可采用水力冲沉将特制钢筋混凝土管作骨架,水力冲沉钢筋混凝土管设两排,两排钢筋混凝土管之间的间距为5米,每两米设一根钢筋混凝土管,钢筋混凝土管上部布设钢筋,用砼帽梁的型式把各钢筋混凝土管连结成一个整体,两排钢筋混凝土管之间用铅丝笼抛石和树梢填充。
(3)合理闸-夏甫阔旦泄洪闸河段。
河道长26Km,河床宽为370~620m。粉细砂河床,两岸为砂土、亚砂土,纵坡为1/800~1/1000。夏甫阔旦泄洪闸以下的河道已经渠系化,渠系化的河道不考虑防洪问题。此段河道防洪工程的布置,以护岸为主,重点设防,只在有建筑物的地方护岸。此段为盖孜河近期防洪规划的下游段,河床为粉细砂,砾石石料缺乏。此段在防洪标准高的重要防护段,采用防洪工程的结构形式为,以电杆冲沉柱压铅丝笼作丁坝,以土坝为顺坝,混凝土板护坡顺坝防护。在防洪标准一般的的防护段,采用防洪工程的结构形式为,以土坝为顺坝,顺坝以铅丝笼装石护面,坝基以铅丝笼装石护基。
5. 结语
通过对盖孜河近期防洪规划中工程措施的设计,有以下几点体会:(1)在今后防洪工程的规划和设计时,依据国家技术监督局、中华人民共和国建设部 1994- 06.02发布的中华人民共和国防洪标准,对防洪工程保护对象进行防洪标准的确定,对保护对象进行其相应的防洪标准的设计;(2)在设计防洪工程的结构形式前,仔细勘测要修建工程处河床的质地、河床的纵坡、流量、天然建筑材料等情况,在设计时要充分考虑以上因素,才能使设计出来的防洪工程的结构形式又节约又安全;(3)根据已勘测的河床质地、河床纵坡、流量等条件,详细计算防洪工程的冲刷深度,并要调查河道上下游已建的防洪工程的基础深度,和大洪水来时对现有防洪工程实际的淘刷深度,综合比较确定防洪工程的冲刷深度,这样设计出来的防洪工程的基础才能即节约又安全;(4)充分借鉴河道上下游已建防洪工程的成功经验,使设计的防洪工程少走弯路,更适合于本河道的具体情况。
[文章编号]1006-7619(2010)04-26-359
[作者简介]陈强伦(1964-),男,新疆喀什地区盖孜河管理处工程科副科长。