据《MetalBulletin》 2 0 0 0年提供的最新消息 ,新日铁公司名古屋 3号高炉已经停炉 ,进行第三次大修。大修工作从 1月 1 7日开始 ,预计至 4月 1 8日完成 ,工程约耗资 2 0 0亿日元。大修将明显扩大 3号高炉的容积 ,由 1 969年首次炉役开炉时的 342 4m3增至本次炉
According to the latest news from “Metal Bulletin” 2000, the Nippon Steel Corporation’s Nagoya No.3 blast furnace has been shutdown for the third overhaul. Overhaul work started from January 17 and is expected to be completed on April 18, with construction cost of about 20 billion yen. The overhaul will significantly expand the capacity of No.3 blast furnace from 342 4m3 at the first furnace opening in 1969 to this furnace