一、工程概况上海市外滩防汛墙座落在黄浦江浦西一侧的外滩地区,是上海市区防汛墙加高加固工程中重要的一段。原有的外滩防汛墙的墙顶标高比较低,为了达到千年一遇的防汛标准,要对其重新进行改造。同时,原有外滩的道路、绿化等也已经难以适应当前的交通和市容景观的需要。因此,由外滩防汛墙外移改造工程、道路拓宽和滨江绿地改造工程共同组成的外滩综合改造工程立项实施。其中,外滩防汛墙外移
First, the project overview Shanghai Bund flood wall is located in the Huangpu River Puxi side of the Bund area, is the Shanghai Urban Flood Control Wall heightening reinforcement project an important section. The original Bund flood wall wall top elevation is relatively low, in order to meet the once-in-a-lifetime flood control standards, to be re-transformed. At the same time, the original Bund roads, greening, etc. have also been difficult to adapt to the current traffic and city landscape needs. Therefore, the Bund comprehensive renovation project consisting of the Bund flood control wall relocation project, road widening and Riverside green space renovation project jointly implemented. Among them, the Bund flood wall moved