基于北京某四星级酒店集中能源站项目2014年全年实际运行能耗数据,针对装机容量,从全年能耗、设备效率、单位供能气耗、单位供能电耗4个方面对直燃机和锅炉设备进行了详细分析。一方面通过运行情况反馈设计优劣,为优化设计主设备容量提供参考,从而降低项目初投资,并为制定更为合理的设计规范提供依据;另一方面分析了系统主设备的运行情况,提出了优化运行节能改造建议,为提高项目运营节能性和经济性提供指导。
Based on actual energy consumption data of a four-star centralized energy station project in Beijing in 2014, according to the actual installed capacity of the four-star centralized energy station project in Beijing, we analyzed the energy consumption of the four-star centralized energy station in 2014 from four aspects: annual energy consumption, equipment efficiency, unit energy consumption and unit energy consumption Gas turbine and boiler equipment were analyzed in detail. On the one hand, through the design of operational feedback system, it provides a reference for optimizing the design of main equipment capacity, so as to reduce the initial investment of project and provide the basis for more reasonable design specifications; on the other hand, analyzes the operation of main equipment of the system, Optimize the operation of energy-saving suggestions for improving energy efficiency and economy of operation of the project to provide guidance.