厦门市杏林─海沧60kt/d供水系统位于杏林区锦园村,占地约5.3hm2。系统各冷水构筑物布局合理、结构紧凑、排列美观大方。该工程于1997年5月竣工,历时460d,工程投资超过6300万元,其中自控系统投资近600万元。整个工程的设计与施工,本着“以我为主,合理设计,注重消化与吸
The Xinglin-Haicang 60kt/d water supply system in Xiamen is located in Jinyuan Village, Xinglin District and occupies an area of approximately 5.3hm2. The cold water structures of the system have a rational layout, a compact structure, and a beautiful arrangement. The project was completed in May 1997 and lasted 460 days. The project investment exceeded 63 million yuan, of which the automatic control system invested nearly 6 million yuan. The design and construction of the entire project is based on "mainly based on me, rational design, and attention to digestion and absorption.