兖州矿业(集团)公司济宁二号煤矿在复杂条件下的综采工作面安撤施工中采取了一系列的安全高效技术。采取大功率回柱绞车、专用卸车平台和多绞车调整防倒的技术,解决了63下07大倾角工作面支架运输、安装倒架和歪架的问题。充分利用顺槽待回收的无极绳钢丝绳作为胶带拖放主绳,采用机架一次成型、输送带一次铺设技术,极大简化以往胶带安装每200 m一个循环的复杂工艺,减少诸多中间环节及人工投入。采取有效的“一通三防”和排放水措施,113下06综采面切眼有20 m未施工、未疏放老空水情况下开始安装;贯通切眼后重新完善安装运输设备设施,完成整个工作面安装。3304回
Yanzhou Mining (Group) Company Jining No. 2 coal mine in complex conditions under the comprehensive mining face safety construction has taken a series of safe and efficient technology. Take high-power back column winch, special unloading platform and multi-winch adjustment to prevent overwhelming the technology to solve the 63 07 large-angle face support carriage transport, installation of the frame and skew frame problems. Make full use of the non-polar rope rope to be recycled along the slot as the primary rope of the tape-dropping, forming once by the rack and laying the conveyor belt once, which greatly simplifies the complex process of once every 200 m of tape installation and greatly reduces many intermediate links and labor Put in. Take effective “one through three” and discharge water measures, 113 under 06 fully mechanized mining face cut 20 m without construction, did not dredge the case of old empty water began to install; cut through the eye to re-perfect the installation of transport equipment and facilities , To complete the entire face installation. 3304 back