一、冬期准备工作 根据房建办几年来的实际状况,冬施准备工作拖期的较多,因而需提前做好准备工作。 1、落实冬施项目、冬施方案,各队厂对冬施工程的方案在10月20日前提出。 2、冬施外加剂及保温材料,根据工程项目提前提出,由办材料室采购,及时供应。 3、热源设备落实,保温棚、火炕、热水箱要满足工班使用要求,冬施用锅炉提前检修,保证正常使用。 4、10月末办公室各队、厂冬施工准备工作进行检查。
First, the winter preparation work According to the actual situation of the Housing Construction Office over the past few years, winter preparations have been delayed for many preparations, and therefore need to be prepared in advance. 1. Implementing the winter plant project and the winter plant program. Each team’s plan for the winter plant project will be submitted before October 20. 2. The winter application admixtures and thermal insulation materials shall be proposed in advance according to the project, and shall be purchased by the material office for timely supply. 3, the implementation of heat source equipment, insulation shed, fire pit, hot water tank to meet the requirements of the class, the use of boilers in winter overhaul to ensure the normal use. 4. In late October, check the preparation work of each team and plant in the office.